← Back
BuildNYC
Miscellaneous educational facility
Herald Center Leasehold Condominium
1293 BROADWAY · BIN 1015199
💬 Discuss this project
1902Year Built
9Stories
W9Building Class
—Zoning
258,412 sfGross Floor Area
10Units
LL97 Covered0 Active ViolationsFISP: SAFEFDNY Report ↗
Miscellaneous educational facility · Owner of record: Herald Center Department Store of New YO RK · 24,393 sf lot · 10.59 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofYU Dental School, Yeshiva University Dental School +1Under Construction104p · 10 filings · 14 docs
Floor 9YU Dental School, Yeshiva University Dental School +1Under Construction141p · 11 filings · 14 docs
Floor 8YU Dental School, Yeshiva University Dental School +1Under Construction135p · 10 filings · 14 docs
Floor 7YU Dental School, Yeshiva University Dental SchoolUnder Construction147p · 9 filings · 14 docs
Floor 6YU Dental School, Yeshiva University Dental SchoolUnder Construction149p · 9 filings · 14 docs
Floor 5YU Dental School, Yeshiva University Dental SchoolUnder Construction146p · 13 filings · 14 docs
Floor 4YU Dental SchoolUnder Construction71p · 2 filings · 14 docs
Floor 3
Floor 2
Floor 1YU Dental School, Yeshiva University Dental School +3Under Construction171p · 21 filings · 14 docs
MezzanineYU Dental School, Yeshiva University Dental School +2Under Construction156p · 10 filings · 14 docs
CellarYU Dental School, Yeshiva University Dental SchoolUnder Construction9p · 3 filings · 17 docs
Sub-CellarYU Dental School, Yeshiva University Dental SchoolUnder Construction132p · 7 filings · 14 docs
Sub-BasementSprint site antenna removal1 filing · 4 docs
Site & exteriorVerizon, Bank of America +123p · 10 filings · 20 docs
Filed — no permit issuedInstall ADA compliant exterior ramp1p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Herald Center Department Store40207/08/2026
Jemb Realty11510/13/2026
75 Broad603/22/2026
Modells Sporting Goods403/21/2026
Staples203/21/2026
50 West 34 Associates203/21/2026
Lembo Design & Development103/22/2026
EMC103/22/2026
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Clune Construction CoGeneral Contractor2707/08/2026
Structure ToneGeneral Contractor1009/02/2026
National MaintenanceSign hanger607/08/2026
Archstone BuildersGeneral Contractor407/08/2026
Sirina Fire ProtectionFire Protection407/23/2026
Capital Builders GroupGeneral Contractor407/08/2026
Watch Hill Wireless SoluGeneral Contractor303/21/2026
Cadena ConstructionGeneral Contractor303/21/2026
Kings Group NYScaffold303/21/2026
Alliance PlumbingPlumbing307/08/2026
Clune Construction CoScaffold307/08/2026
Sean Coakley P & HFire Protection307/08/2026
Ark Design & BuildScaffold303/21/2026
Ark Design & BuildGeneral Contractor303/21/2026
Stat ElectricElectrical203/21/2026
SRM Electrical ServiceElectrical203/22/2026
Par Plumbing Co., Inc.oFire Protection203/21/2026
North Shore Neon Sign CoSign hanger207/08/2026
Abco-Peerless SprinklerFire Protection207/08/2026
JRM Construction ManagementGeneral Contractor207/08/2026
Metro RF ServicesGeneral Contractor207/08/2026
F & P Electrical ContractorsElectrical203/21/2026
TT MechanicalPlumbing107/08/2026
Uni-Lite ElectricElectrical103/21/2026
JB ElectricElectrical103/21/2026
Moore RichardElectrical103/21/2026
Power Tech ElectricElectrical103/21/2026
S.E. Electl ContngElectrical103/22/2026
Stabile ChristopherElectrical103/21/2026
Scientific Electric CoElectrical103/21/2026
Urban-ServwellElectrical103/21/2026
Pavarini McGovernGeneral Contractor107/08/2026
Platinum General ServicesGeneral Contractor107/08/2026
Valentine Construction ManagementGeneral Contractor107/08/2026
Horizon Retail ConstructionScaffold107/08/2026
City SignsSign hanger107/08/2026
Neptune Signs & AwningsSign hanger107/08/2026
Paul SignsSign hanger107/08/2026
AAA Total PlumbingPlumbing107/08/2026
Aggressive Fire ProtectionFire Protection107/08/2026
Mac FelderPlumbing107/08/2026
Stability Electric EnterprisesElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Socotec Engineering49832310/05/2026
Goldman Copeland Associates2826212/16/2025
Ace Structural Engineering496507/08/2025
Wavic Engineering1733202/21/2025
Trolydia Testing & Inspec44221201/27/2025
City Building NY Architects1394305/29/2024
Socotec301105/11/2023
Joseph Martines PE14281007/07/2022
Grant Engineering Consulting3512106/29/2022
Sag Engineering & Consulting608101/21/2022
Building Lifecycle
All (300)Filed (80)Permit Issued (69)Signed Off (37)Facade (FISP) (3)Violation (21)Inspection (22)Objection (38)Special Inspection (30)
10/06/2026
Filed — Alteration
MECHANICAL MODIFICATIONS AND INSTALLATION OF SYSTEMS ASSOCIATED DUCTS AND PIPING
M01154825-P6
10/05/2026
Filed — Alteration
FILING FOR SPRINKLER MODIFICATION AND ALTERATION FOR TENANT FIT-OUT
M01235011-P3
10/05/2026
Filed — Alteration
MECHANICAL MODIFICATIONS AND INSTALLATION OF SYSTEMS ASSOCIATED DUCTS AND PIPING
M01154825-P5
10/05/2026
Objection raised — Other
10/01/2026
Filed — No Work
M01467093-I1
09/28/2026
Objection raised — Other
09/24/2026
Filed — Alteration
install ADA compliant exterior ramp. No change in use, egress or occupancy under this application.
M01462847-I1
09/23/2026
Special inspection requirement — Final
09/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
09/11/2026
Special inspection requirement — Interior lighting power
ALEXIS SCHLESSINGERMAN
09/11/2026
Special inspection requirement — Lighting controls
ALEXIS SCHLESSINGERMAN
09/11/2026
Special inspection requirement — Fire-Resistance Rated Construction
ALEXIS SCHLESSINGERMAN
09/10/2026
Filed — Alteration
General Construction for installation of interior partitions, floors, ceilings and related finishes as per plans for tenant fitout
M01280194-P3
09/10/2026
Objection raised — Other
09/10/2026
Objection raised — Other
09/09/2026
Filed — No Work
M01456799-I1
09/02/2026
Filed — Alteration CO
FILING ALTERATION TO ESTABLISH PLACE OF ASSEMBLY SPACES ON 5TH AND 8TH FLOOR WITH RELATED CONSTRUCTION WORK
M01411446-P1
09/01/2026
Permit issued — Mechanical Systems
M01154825-S1-MS
09/01/2026
Permit issued — General Construction
M01280194-I1-GC
08/25/2026
Special inspection requirement — Interior lighting power
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Lighting controls
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Maintenance information
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Lighting controls
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Duct leakage testing, insulation and design
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Sprinkler Systems
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Luminous Exit Path Markings
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — HVAC-R and service water heating equipment
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Post-installed Anchors
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — HVAC-R and service water heating system controls
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Final
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Shutoff dampers
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Interior lighting power
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Mechanical Systems
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Maintenance information
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Final
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Metering
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — High-Pressure Steam Piping (Welding)
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
ALEXIS SCHLESSINGERMAN
08/25/2026
Special inspection requirement — Sprayed fire-resistant materials
ALEXIS SCHLESSINGERMAN
08/14/2026
Signed off — Alteration
FILING FOR STRUCTURAL MODIFICATION FOR REMOVAL AND INFILL AS PER PLANS
M01196336-I1
07/29/2026
Signed off — Alteration
STRUCTURAL MODIFCATIONS AND REINFORCMENT OF FLOORS AS PER PLANS FOR TENANT FIT-OUT
M01235019-I1
07/22/2026
Permit issued — Sprinklers
M01235011-I1-EW-SP
07/02/2026
Permit issued — General Construction
M01411446-I1-GC
07/01/2026
Filed — No Work
M01411410-I1
06/23/2026
Objection resolved — Addressed
06/23/2026
Objection resolved — Addressed
06/20/2026
Objection raised — Accessibility
06/20/2026
Objection raised — Structural
06/17/2026
Objection resolved — Addressed
06/12/2026
Objection raised — Admin
06/08/2026
Filed — Alteration CO
FILING ALTERATION TO ESTABLISH PLACE OF ASSEMBLY SPACES ON 5TH AND 8TH FLOOR WITH RELATED CONSTRUCTION WORK
M01411446-I1
05/04/2026
Filed — No Work
M01382411-I1
04/22/2026
Permit issued — Mechanical Systems
M01311515-I1-MS
04/21/2026
Signed off — Alteration
REMOVAL OF SPRINKLER HEADS AND PIPING AS PER PLANS
M01196386-I1
04/03/2026
Permit issued — Plumbing
M01154825-S2-PL
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedStructure Tone09/01/2026
DOB NOWGeneral ConstructionPermit IssuedStructure Tone09/01/2026
DOB NOWSprinklersPermit IssuedSirina Fire Protection07/22/2026
DOB NOWGeneral ConstructionPermit IssuedStructure Tone07/02/2026
DOB NOWMechanical SystemsPermit IssuedPavarini McGovern04/22/2026
DOB NOWPlumbingPermit IssuedCardoza Plumbing Wmbe04/03/2026
DOB NOWPlumbingPermit IssuedTT Mechanical03/12/2026
DOB NOWStructuralSigned-offStructure Tone10/30/2025
DOB NOWPlumbingPermit IssuedCardoza Plumbing Wmbe10/09/2025
DOB NOWGeneral ConstructionPermit IssuedStructure Tone09/09/2025
DOB NOWSprinklersSigned-offSirina Fire Protection08/27/2025
DOB NOWSprinklersPermit IssuedSirina Fire Protection07/31/2025
DOB NOWPlumbingSigned-offCardoza Plumbing Wmbe07/29/2025
DOB NOWMechanical SystemsPermit IssuedStructure Tone07/29/2025
DOB NOWSprinklersSigned-offAbco-Peerless Sprinkler07/22/2025
DOB NOWGeneral ConstructionSigned-offCapital Builders Group07/16/2025
DOB NOWStructuralSigned-offStructure Tone04/30/2025
DOB NOWMechanical SystemsSigned-offStructure Tone04/01/2025
DOB NOWGeneral ConstructionSigned-offPlatinum General Services04/01/2025
DOB NOWGeneral ConstructionSigned-offStructure Tone03/26/2025
DOB NOWSprinklersPermit IssuedSean Coakley P & H02/28/2025
DOB NOWGeneral ConstructionSigned-offArchstone Builders12/18/2024
DOB NOWSignSigned-offNorth Shore Neon Sign Co09/04/2024
DOB NOWSignPermit IssuedElmer Dawson09/03/2024
DOB NOWSignSigned-offNorth Shore Neon Sign Co09/03/2024
DOB NOWGeneral ConstructionSigned-offArchstone Builders08/23/2024
DOB NOWConstruction FenceSigned-offArk Design & Build08/06/2024
DOB NOWPlumbingSigned-offAAA Total Plumbing07/23/2024
DOB NOWSprinklersSigned-offAbco-Peerless Sprinkler07/18/2024
DOB NOWMechanical SystemsSigned-offCapital Builders Group07/05/2024
DOB NOWGeneral ConstructionSigned-offCapital Builders Group07/03/2024
DOB NOWGeneral ConstructionSigned-offArk Design & Build06/05/2024
DOB NOWSuspended ScaffoldPermit IssuedR & R Scaffolding03/28/2024
DOB NOWGeneral ConstructionSigned-offArchstone Builders01/16/2024
DOB NOWSignSigned-offNational Maintenance08/29/2023
DOB NOWSignSigned-offNational Maintenance08/29/2023
DOB NOWSignSigned-offNational Maintenance08/29/2023
DOB NOWGeneral ConstructionSigned-offClune Construction Co08/11/2023
DOB NOWConstruction FenceSigned-offClune Construction Co08/11/2023
DOB NOWSprinklersSigned-offSirina Fire Protection07/24/2023
+ 60 more permits on file
2 projects · most recent 10/06/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
10/06/2026Permit IssuedStructure ToneHeating and Air Conditioning Systems
Heat / Cool
Daikin DAIKIN WSCH060 1,700 CFM · Wshp ×4
DAIKIN WSCH012 350 CFM · Wshp ×2
DAIKIN WSCV060 2,200 CFM · Wshp ×2
DAIKIN WSCV070 2,200 CFM · Wshp ×2
DAIKIN WSCV048 1,600 CFM · Wshp ×1
DAIKIN-MCQUAY RPS 075 CLA 26,000 CFM · Rooftop Unit ×1
DAIKIN-MCQUAY RPS 090 CLA 30,000 CFM · Rooftop Unit ×1
DPS015AHMG2DV 6,000 CFM · Rooftop Unit ×1
12/16/2025Permit IssuedPavarini McGovernHeating and Air Conditioning Systems
Heat / Cool
Trane SFHPF75EK 24,100 CFM · Rooftop Unit ×1
SFHRC904T 30,000 CFM · Rooftop Unit ×1
YSK180ASAL 6,000 CFM · Chiller ×1
2 projects · most recent 10/05/2026
FiledStatusContractorScope
10/05/2026Permit IssuedSirina Fire Protection3,339 heads
02/21/2025Permit IssuedSean Coakley P & H1 heads
1 project · most recent 10/05/2026
FiledStatusContractorScope
10/05/2026———
25 projects · most recent 01/20/2026
General Wiring Lighting
FiledStatusContractorScope
01/20/2026Permit IssuedUni-Lite ElectricGeneral Wiring
07/19/2025CompleteS.E. Electl ContngGeneral Wiring
05/16/2025CompleteT. Dirusso Electrical Cont—
05/16/2025CancelledT. Dirusso Electrical ContGeneral Wiring
04/16/2025Permit IssuedUni-Lite ElectricGeneral Wiring
02/04/2025Permit IssuedNee Electrical—
11/19/2024Permit IssuedCity Electrical Sign Erectors—
09/09/2024CompleteR & T Electrical—
05/31/2024Permit IssuedSRM Electrical ServiceGeneral Wiring, Lighting
05/29/2024CompleteHome Run Electric—
05/29/2024CompleteHome Run Electric—
05/28/2024CompleteHome Run Electric—
05/22/2024CompleteElpo Electrical Contg—
07/25/2023CompletePolo Electric Corp D/B/AGeneral Wiring
04/03/2023Permit IssuedNational Maintenance—
2 projects · most recent 12/12/2025
Steel Concrete
FiledStatusContractorScope
12/12/2025Signed-offStructure ToneSteel, Concrete
07/31/2025Signed-offStructure ToneSteel, Concrete
▾Field Inspections (DOB CAP) — 22
DateTypeResultReport
03/17/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/15/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/29/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/19/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/18/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/23/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/14/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/11/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/30/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/18/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/18/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/01/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/19/2024Pass-Final General Construction Non-Directive 14PassView ↗
08/07/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/19/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/16/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/03/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/03/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/24/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/07/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/05/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
09/23/2026Final—progress
09/11/2026Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
09/11/2026Fire-Resistance Rated ConstructionALEXIS SCHLESSINGERMANprogress
09/11/2026Interior lighting powerALEXIS SCHLESSINGERMANenergy_progress
09/11/2026Lighting controlsALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Mechanical SystemsALEXIS SCHLESSINGERMANspecial
08/25/2026High-Pressure Steam Piping (Welding)ALEXIS SCHLESSINGERMANspecial
08/25/2026Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
08/25/2026HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Sprayed fire-resistant materialsALEXIS SCHLESSINGERMANspecial
08/25/2026FinalALEXIS SCHLESSINGERMANprogress
08/25/2026HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Shutoff dampersALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Sprinkler SystemsALEXIS SCHLESSINGERMANspecial
08/25/2026Interior lighting powerALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Lighting controlsALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Fire-Resistance Rated ConstructionALEXIS SCHLESSINGERMANprogress
08/25/2026HVAC-R and service water piping design and insulationALEXIS SCHLESSINGERMANenergy_progress
08/25/2026HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Maintenance informationALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Duct leakage testing, insulation and designALEXIS SCHLESSINGERMANenergy_progress
08/25/2026Luminous Exit Path MarkingsALEXIS SCHLESSINGERMANspecial
08/25/2026HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
08/25/2026HVAC-R and service water piping design and insulationALEXIS SCHLESSINGERMANenergy_progress
08/25/2026MeteringALEXIS SCHLESSINGERMANenergy_progress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Yeshiva University Dental SchoolEducationSub-cellar, Cellar, Floors 1, 5–9, Mezzanine, Roof
Project M01411410 No Work · Approved · 07/01/2026
Project M01411446 Alteration CO · Permit Entire · 06/08/2026
Project M01280194 Alteration · Permit Entire · 09/05/2025
Project M01235019 Alteration · LOC Issued · 07/18/2025
Project M01196336 Alteration · LOC Issued · 03/25/2025
Project M01145874 Alteration · LOC Issued · 03/21/2025
RuudindsOfficeFloors 8, 9
Project M01311515 Alteration · Permit Entire · 11/25/2025
YU Dental SchoolEducationSub-cellar, Floors 1, 4–9, Mezzanine, Roof
Project M01235011 Alteration · Permit Entire · 07/09/2025
Project M01246556 Alteration · LOC Issued · 07/08/2025
Project M01246575 Alteration · LOC Issued · 07/08/2025
Project M01154825 Alteration · Permit Entire · 07/07/2025
Bank of AmericaBank / Financial branchFloor 1, Mezzanine
Project M01090377 Alteration · LOC Issued · 03/27/2025
Project M00840781 Alteration · LOC Issued · 03/27/2023
Project M00840795 Alteration · LOC Issued · 03/27/2023
Project M00840804 Alteration · LOC Issued · 03/27/2023
Project M00708359 Alteration · LOC Issued · 04/04/2022
Project M00458118 Alteration · LOC Issued · 06/27/2021
Project M00479165 Alteration · LOC Issued · 06/21/2021
Project M00458139 Alteration · LOC Issued · 06/17/2021
Project M00458006 Alteration · LOC Issued · 05/27/2021
VerizonTelecom siteFloor 1, Mezzanine
Project M01103259 Alteration · LOC Issued · 09/03/2024
Project M01103283 Alteration · LOC Issued · 09/03/2024
Project M01068968 Alteration · LOC Issued · 06/28/2024
Project M01068872 Alteration · LOC Issued · 06/27/2024
Project M01068996 Alteration · LOC Issued · 06/27/2024
Project M00415271 Alteration · LOC Issued · 11/12/2020
InnisfreeRetailFloor 1
Project M00174318 Alteration · Permit Entire · 09/03/2019
Project M00153009 Alteration · LOC Issued · 07/29/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 2,254 on file (BIS + DOB NOW)
▸Plans & Drawings83
▸DOB NOWPlans/Sketch68
10/04/2026M01462847-I1Request digital key ↗
09/03/2026M00479165-I1Request digital key ↗
09/03/2026M00479165-P2Request digital key ↗
Showing 3 of 68 on file for this type
▸DOB NOWPlans/Sketch - Structural3
09/03/2026M00458118-P1Request digital key ↗
09/03/2026M00458118-I1Request digital key ↗
09/03/2026M00458118-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/02/2026M00458139-P2Request digital key ↗
09/02/2026M00458139-I1Request digital key ↗
09/02/2026M00458139-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sign2
09/05/2026M00174318-I1Request digital key ↗
09/04/2026M00415271-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Temporary Place of Assembly2
10/13/2026M01456799-I1Request digital key ↗
10/04/2026M01467093-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
09/03/2026M00458006-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/05/2026M00283384-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/05/2026M00153009-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Antenna1
09/04/2026M00369243-I1Request digital key ↗
▸Applications & Permits383
▸BISPLAN / WORK APPROVAL APPLICATION224
10/30/2024124039316Open ↗
10/17/2024124039316Open ↗
10/01/2024124039316Open ↗
Showing 3 of 224 on file for this type
▸BISWORK PERMIT APPLICATION154
05/18/2022123356386Open ↗
12/11/2019123693191Open ↗
08/20/2019123735565Open ↗
Showing 3 of 154 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISApplication Withdrawal/Address Change Form OP-1132
05/22/2019123675362Open ↗
04/26/2019123675362Open ↗
▸Seals & Professional Certifications722
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION321
02/28/2020104584148Open ↗
01/15/2020123735565Open ↗
01/15/2020123735565Open ↗
Showing 3 of 321 on file for this type
▸DOB NOWProgress Inspector Seal & Signature112
10/14/2026M01280194-P3Open ↗
10/14/2026M01280194-P3Open ↗
10/14/2026M01411446-P1Open ↗
Showing 3 of 112 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature85
10/14/2026M01280194-P3Open ↗
10/14/2026M01411446-P1Open ↗
10/13/2026M01456799-I1Open ↗
Showing 3 of 85 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature71
10/14/2026M01280194-P3Open ↗
10/14/2026M01280194-P3Open ↗
10/14/2026M01411446-P1Open ↗
Showing 3 of 71 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST58
12/11/2019123693191Open ↗
11/15/2019123790460Open ↗
07/24/2019123735565Open ↗
Showing 3 of 58 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT53
12/11/2019123693191Open ↗
11/15/2019123790460Open ↗
07/24/2019123735565Open ↗
Showing 3 of 53 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
10/02/2018140808133Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
10/02/2018140808133Open ↗
Showing 1 of 3 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment155
▸BISSELF-CERT PLUMBING NOTICE62
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 62 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE28
10/22/2019123735565Open ↗
10/22/2019123735565Open ↗
07/24/2019123735565Open ↗
Showing 3 of 28 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT18
09/24/2020123735565Open ↗
Showing 1 of 18 on file for this type
▸BISSCHEDULE B - PLUMBING16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISEQUIPMENT USE PERMITS14
09/24/2020123735565Open ↗
Showing 1 of 14 on file for this type
▸BISSPRINKLER INSP REPORT : FP-859
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA5
07/12/2022123434266Open ↗
08/23/2018123356386Open ↗
Showing 2 of 5 on file for this type
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMITEQUIPMENT USE PERMITS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection2
▸BISST-1 Street Tree Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWStreet Tree Checklist1
10/14/2026M01411446-P1Open ↗
▸Environmental & Asbestos161
▸BISASBESTOS: CERTIFICATION (DEP ACP5)71
12/11/2019123693191Open ↗
11/15/2019123790460Open ↗
07/24/2019123735565Open ↗
Showing 3 of 71 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report71
10/14/2026M01280194-P3Open ↗
10/14/2026M01411446-P1Open ↗
09/05/2026M00283384-I1Open ↗
Showing 3 of 71 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISASBESTOS: EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance128
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS80
12/11/2019123693191Open ↗
12/11/2019123693191Open ↗
11/15/2019123790460Open ↗
Showing 3 of 80 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS34
11/02/2021122404558Open ↗
11/02/2021122404558Open ↗
01/06/2021123693191Open ↗
Showing 3 of 34 on file for this type
▸BISTR8: Energy Code Progress Inspections6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.4
09/02/2026M00458139-I1Open ↗
09/03/2026M00652291-I1Open ↗
09/02/2026M00651192-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
01/06/2021123693191Open ↗
09/24/2020123735565Open ↗
09/24/2020123735565Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY7
01/06/2021123693191Open ↗
09/24/2020123735565Open ↗
09/24/2020123735565Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: CONCRETE-TEST CYLINDER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCertificate of Inspection Construct Manhole or Catch Basin and Basin Connection1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs214
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST116
11/03/2021122404558Open ↗
01/06/2021123693191Open ↗
09/24/2020123735565Open ↗
Showing 3 of 116 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION41
12/11/2019123693191Open ↗
Showing 1 of 41 on file for this type
▸BISADMINISTRATIVE OBJECTIONS19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸DOB NOWTransit Authority Approval17
09/05/2026M00153009-I1Open ↗
09/05/2026M00283384-I1Open ↗
09/03/2026M00458118-P1Open ↗
Showing 3 of 17 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL4
07/24/2019123735565Open ↗
10/02/2018140808133Open ↗
05/21/2018123392952Open ↗
Showing 3 of 4 on file for this type
▸BISSHED LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION2
02/07/2019123675362Open ↗
Showing 1 of 2 on file for this type
▸BISTRANSIT AUTHORITY APPROVAL2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Cost, Insurance & Ownership174
▸BISCOST AFFIDAVIT165
01/06/2021123693191Open ↗
12/11/2019123693191Open ↗
11/15/2019123790460Open ↗
Showing 3 of 165 on file for this type
▸BISDEPT OF FINANCE VERIFICATION5
10/11/2024124039316Open ↗
10/11/2024124039316Open ↗
10/01/2024124039316Open ↗
Showing 3 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
08/18/2022123434266Open ↗
08/18/2022123434266Open ↗
08/18/2022123356386Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms177
▸BISEFILING COVER SHEET113
10/01/2024124039316Open ↗
05/12/2023123917413Open ↗
12/11/2019123693191Open ↗
Showing 3 of 113 on file for this type
▸BISADDITIONAL INFORMATION41
11/01/2024124039316Open ↗
10/22/2019123735565Open ↗
Showing 2 of 41 on file for this type
▸BISBOROUGH INTAKE FORM17
10/01/2024124039316Open ↗
05/12/2023123917413Open ↗
02/28/2020104584148Open ↗
Showing 3 of 17 on file for this type
▸BISeFiling Job Application Cover Sheet6
10/02/2018140808133Open ↗
Showing 1 of 6 on file for this type
▸Other Documents35
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION29
10/11/2024124039316Open ↗
10/11/2024124039316Open ↗
10/11/2024124039316Open ↗
Showing 3 of 29 on file for this type
▸BISSupporting Document: Fee Exempt3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWCalculations1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWProperty Ownership Certification1
10/14/2026M01411446-P1Open ↗
▸DOB NOWManufacturer's Specifications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type