| Owner | Filings | Most Recent |
|---|---|---|
| 60G MGMT | 1 | 09/13/2026 |
| L H CHARNEY ASSOCIATES | 50 | 07/29/2026 |
| CHARNEY MANAGEMENT | 30 | 07/08/2026 |
| LECHAR 1441 LLC | 3 | 03/22/2026 |
| JRM CONSTRUCTION MGMT | 1 | 03/22/2026 |
| LECHAR REALITY SERVICES | 413 | 03/22/2026 |
| LH CHARRY ASSOC INC | 1 | 03/22/2026 |
| LECHAR REALTY % WINOKER R | 1 | 03/22/2026 |
| OWNER OF 569 7 AV | 1 | 03/22/2026 |
| ELLEN TRACY CO. | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LILKER ASSOCIATES CONSULTING ENGINE | 8 | 01/06/2026 |
| SCA CODE CONSULTING AND PLANNING | 4 | 11/26/2025 |
| RICHARD WAINER ARCHITECT, PLLC | 1 | 10/22/2025 |
| MG ENGINEERING D.P.C. | 4 | 08/06/2025 |
| MCLAREN ENGINEERING GROUP | 12 | 05/27/2025 |
| ASDA ARCHITECTURE + DESIGN | 3 | 04/17/2025 |
| THE SWITZER GROUP | 1 | 09/29/2023 |
| WRG ENGINEERING, P.C. | 4 | 07/06/2023 |
| FUTURE MADE ARCHITECTURE, PLLC | 1 | 05/01/2023 |
| ROSINI ENGINEERING, PC | 7 | 03/10/2023 |
| ROMIT GAJJAR | 3 | 03/08/2023 |
| IW ARCHITECTURE, PLLC | 2 | 11/10/2022 |
| JACK GREEN ASSOCIATES | 1 | 08/31/2022 |
| DATTNER ARCHITECTS | 1 | 08/05/2022 |
| SILMAN | 1 | 05/09/2022 |
| JAMES R LENCIONI | 1 | 05/06/2022 |
| ENTHINK ENGINEERS LLC | 1 | 10/20/2021 |
| RAKSHAN MALEK ASSOCIATES, INC. | 8 | 08/03/2021 |
| ROCK ARCH ENG CORP | 1 | 06/04/2021 |
| KMB DESIGN GROUP, LLC | 1 | 11/13/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARCHETYPE CONSULTANTS | 18 | 03/21/2026 |
| NEXUS CONSULTING NYC, INC | 12 | 03/21/2026 |
| JME BUILDING CONSULTING, LLC | 1 | 03/21/2026 |
| D R BROWN | 22 | 03/21/2026 |
| 3 AXIS CONSTRUCTION | 8 | 03/21/2026 |
| M G MCLAREN ENGINEERING | 4 | 03/21/2026 |
| WRG ENGINEERING P C | 8 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 18 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 10 | 03/21/2026 |
| NEW YORK SIGN CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| G.B.C. CORPORATION | General Contractor | 13 | 07/08/2026 |
| WELLBUILT CONSTRUCTION | General Contractor | 9 | 07/08/2026 |
| A M A HOLDINGS | Scaffold | 9 | 07/08/2026 |
| WH INTERIORS & DESIGN COR | General Contractor | 6 | 03/21/2026 |
| MERCURY FIRE SUPP INC | Fire Protection | 5 | 07/08/2026 |
| CONSTRUCTOMICS LLC | General Contractor | 5 | 07/08/2026 |
| V & M DRAIN CLEANING INC | Plumbing | 5 | 07/08/2026 |
| PREMIER SANITATION LLC | General Contractor | 3 | 03/21/2026 |
| AQUA PLUMBING & HTNG CORP | Plumbing | 3 | 07/08/2026 |
| SKH MECHANICAL CORP | Fire Protection | 3 | 07/08/2026 |
| LCS RESTORATION CORP | General Contractor | 3 | 03/21/2026 |
| CONSIGLI CONSTRUCTION CO | General Contractor | 3 | 07/08/2026 |
| NORTH SHORE NEON SIGN LLC | General Contractor | 2 | 03/21/2026 |
| PSI PARTNERS, LLC | Fire Protection | 2 | 07/08/2026 |
| VICTOR HOLNESS | Electrical | 2 | 03/21/2026 |
| MAUCERI SIGN | Scaffold | 2 | 07/08/2026 |
| DONE RIGHT HOOD & FIRE SA | General Contractor | 1 | 07/08/2026 |
| JACOBS TELECOMMUN. INC | General Contractor | 1 | 07/08/2026 |
| PHASE 3 INTERIORS LLC | General Contractor | 1 | 09/13/2026 |
| UNIQUE FIRE SYSTEMS INC | General Contractor | 1 | 07/08/2026 |
| DONATO PLUMBING GROUP INC | Plumbing | 1 | 07/08/2026 |
| FRANKIE PLBG & HTG L.L.C | Plumbing | 1 | 07/08/2026 |
| BALATON CONSULTING LLC | Scaffold | 1 | 07/08/2026 |
| ABE HIMELFARB | Electrical | 1 | 03/21/2026 |
| TEE BEE SIGN INST | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BROADWAY INSPECTIONS | 8735 | 2 | 01/06/2026 |
| SCA CODE AND PLANNING, LL | 6599 | 4 | 11/26/2025 |
| COLE TECHNOLOGIES/CONTROL | 1290 | 4 | 08/06/2025 |
| DOMANI INSPECTION SERVICE | 843 | 1 | 05/22/2025 |
| JACK GREEN ASSOCIATES | 422 | 4 | 04/17/2025 |
| HANSEN ENGINEERING PC | 8174 | 3 | 09/29/2023 |
| WRG ENGINEERING, P.C. | 4403 | 4 | 07/06/2023 |
| RAKSHAN MALEK ASSOCIATES | 3352 | 12 | 03/10/2023 |
| MILROSE CONSULTANTS LLC | 2003 | 1 | 05/09/2022 |
| ASE ENGINEERING PLLC | 5785 | 2 | 08/03/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | PHASE 3 INTERIORS LLC | 09/11/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | CUSTOM METAL CRAFTERS INC | 07/28/2026 |
| DOB NOW | Mechanical Systems | Signed-off | JJK BUILDING CONSULTING | 01/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | MORA FIRE PROTECTION LLC | 12/30/2025 |
| DOB NOW | Sign | Signed-off | WEINFELD, ELLIOT | 10/24/2025 |
| DOB NOW | Plumbing | Signed-off | FRANKIE PLBG & HTG L.L.C | 08/28/2025 |
| DOB NOW | Mechanical Systems | Signed-off | DEMHA TILE INC | 08/15/2025 |
| DOB NOW | Structural | Permit Issued | NORTH SHORE NEON SIGN LLC | 06/03/2025 |
| DOB NOW | Sign | Permit Issued | NORTH SHORE NEON SIGN CO | 05/30/2025 |
| DOB NOW | Mechanical Systems | Signed-off | WELLBUILT CONSTRUCTION | 05/05/2025 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING GROUP INC | 03/26/2025 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 03/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CONSIGLI CONSTRUCTION CO | 03/12/2025 |
| DOB NOW | General Construction | Permit Issued | CONSTRUCTOMICS LLC | 09/27/2024 |
| DOB NOW | Plumbing | Permit Issued | AQUA PLUMBING & HTNG CORP | 01/18/2024 |
| DOB NOW | Sprinklers | Permit Issued | MORA FIRE PROTECTION LLC | 01/05/2024 |
| DOB NOW | General Construction | Permit Issued | CONSTRUCTOMICS LLC | 12/13/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | CONSTRUCTOMICS LLC | 12/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WELLBUILT CONSTRUCTION | 12/01/2023 |
| DOB NOW | Structural | Signed-off | WELLBUILT CONSTRUCTION | 08/18/2023 |
| DOB NOW | Structural | Signed-off | WELLBUILT CONSTRUCTION | 08/17/2023 |
| DOB NOW | General Construction | Permit Issued | WELLBUILT CONSTRUCTION | 08/16/2023 |
| DOB NOW | General Construction | Permit Issued | WELLBUILT CONSTRUCTION | 08/16/2023 |
| DOB NOW | General Construction | Signed-off | PREMIER SANITATION LLC | 05/19/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WH INTERIORS & DESIGN COR | 04/19/2023 |
| DOB NOW | General Construction | Signed-off | WH INTERIORS & DESIGN COR | 01/18/2023 |
| DOB NOW | Mechanical Systems | Signed-off | DNJ INDUSTRIES INC | 12/15/2022 |
| DOB NOW | Structural | Signed-off | G.B.C. CORPORATION | 12/06/2022 |
| DOB NOW | General Construction | Signed-off | G.B.C. CORPORATION | 12/06/2022 |
| DOB NOW | Sign | Signed-off | MAUCERI SIGN CO., INC | 11/15/2022 |
| DOB NOW | Sign | Signed-off | MAUCERI SIGN CO., INC | 11/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | DONE RIGHT HOOD & FIRE SA | 09/19/2022 |
| DOB NOW | Plumbing | Signed-off | V & M DRAIN CLEANING INC | 08/24/2022 |
| DOB NOW | Sprinklers | Permit Issued | SKH MECHANICAL CORP | 08/15/2022 |
| DOB NOW | General Construction | Signed-off | CONSIGLI CONSTRUCTION CO | 08/09/2022 |
| DOB NOW | Sprinklers | Signed-off | MERCURY FIRE SUPP INC | 07/23/2022 |
| DOB NOW | General Construction | Signed-off | G.B.C. CORPORATION | 06/01/2022 |
| DOB NOW | Plumbing | Signed-off | V & M DRAIN CLEANING INC | 05/19/2022 |
| DOB NOW | Sprinklers | Permit Issued | FULL CAPACITY FIRE CORP | 11/04/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 10/20/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/06/2026 | Signed-off | CONSTRUCTOMICS LLC | Air Conditioning Systems, Ventilation Systems | Cooling Liebert DME037E-PNC 1,430 CFM · Condensing Unit ×2 Mitsubishi Electric ACCU-16-1: PUMY-48NKMU1
AC-16-1: PEFY-P18NMAU-E3
AC-16-2: PEFY-P24NMAU-E3 3,885 CFM · Vrf Outdoor ×2 Ventilation Johnson Controls DSV300C2N14HDA4B00A 9,125 CFM · Chiller ×4 |
| 09/29/2023 | Permit Issued | CONSTRUCTOMICS LLC | Air Conditioning Systems | Cooling Skypeak SKY-SDSV-C.300-2-F2MZHASA2LBS000A00 9,200 CFM ×2 |
| 08/03/2021 | Permit Issued | G.B.C. CORPORATION | Air Conditioning Systems, Ventilation Systems | Cooling Trane CICD-30 30 tons · Water Cooled Chiller ×12 Ventilation Trane UCCAG08A0 3,000 CFM · Ahu ×12 BCHD012E2 400 CFM · Ahu ×6 BCHD018B2 400 CFM · Ahu ×3 BCHD018E2 630 CFM · Ahu ×3 BCHD024E2 800 CFM · Ahu ×3 BCHD036E2 1,000 CFM · Ahu ×3 UCCAG12A0 5,755 CFM · Ahu ×3 UCCAG17A 8,742 CFM · Ahu ×3 UCCAG17A0 9,270 CFM · Ahu ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2023 | Permit Issued | PSI PARTNERS, LLC | — |
| 11/04/2020 | Permit Issued | SKH MECHANICAL CORP | 280 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2025 | Permit Issued | AURORA ELECL CONTG INC | — |
| 05/01/2024 | Complete | CORZO ELECTL SYS CORP | General Wiring |
| 08/12/2023 | Permit Issued | V A ELECTRIC LLC | General Wiring |
| 01/11/2023 | Complete | Y.S ELECTRIC | General Wiring, Lighting |
| 08/26/2022 | Permit Issued | PATRIOT ELECTRIC CORP | General Wiring |
| 08/26/2022 | Complete | PATRIOT ELECTRIC CORP | — |
| 12/13/2021 | Complete | APOLLO ELECTRIC INSDUS IN | General Wiring |
| 12/13/2021 | Complete | APOLLO ELECTRIC INSDUS IN | General Wiring |
| 10/22/2021 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 07/15/2021 | Complete | Y.S ELECTRIC | General Wiring, Lighting |
| 10/13/2020 | Complete | THYSSENKRUPP ELEVATOR CO | — |
| 12/31/2019 | Cancelled | SURE ELEC'L CONTR'G CORP. | General Wiring |
| 01/24/2019 | Permit Issued | G ENERGY SOLTN AND SVCS I | General Wiring |
| 10/11/2018 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 07/24/2018 | Complete | USIS ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/22/2025 | Permit Issued | NORTH SHORE NEON SIGN LLC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | Permit Issued | CUSTOM METALCRAFTERS INC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/12/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/21/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/27/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/24/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/01/2024 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 02/28/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/23/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/03/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/26/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/21/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/15/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/06/2026 | Mechanical Systems | Salvatore Chiarelli | special |
| 01/06/2026 | Maintenance information | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | Electrical motors | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | Shutoff dampers | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | Duct leakage testing | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | HVAC and service water heating system controls | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | Permanent certificate | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | HVAC and service water heating equipment | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | HVAC insulation and sealing | Salvatore Chiarelli | energy_progress |
| 01/06/2026 | Final | Salvatore Chiarelli | progress |
| 11/23/2025 | Fire-Resistant Penetrations and Joints | JOMO CHARLES | special |
| 10/17/2025 | Fire-Resistant Penetrations and Joints | JOMO CHARLES | special |
| 08/25/2025 | Mechanical Systems | GEORGE ANDERSEN | special |
| 08/25/2025 | Final | GEORGE ANDERSEN | progress |
| 08/18/2025 | Final | Richard Wainer | progress |
| 07/30/2025 | Mechanical Systems | GEORGE ANDERSEN | special |
| 07/30/2025 | Final | GEORGE ANDERSEN | progress |
| 07/22/2025 | HVAC-R and service water heating system controls | JOMO CHARLES | energy_progress |
| 07/22/2025 | HVAC-R and service water piping design and insulation | JOMO CHARLES | energy_progress |
| 06/16/2025 | Interior lighting power | JOMO CHARLES | energy_progress |
| 06/08/2025 | Fire-Resistant Penetrations and Joints | JOMO CHARLES | special |
| 06/08/2025 | Mechanical Systems | JOMO CHARLES | special |
| 06/08/2025 | Final | JOMO CHARLES | progress |
| 06/08/2025 | Energy Code Compliance Inspections | JOMO CHARLES | progress |
| 03/05/2025 | Structural Steel - Details | JOHN MCMONAGLE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Spot | Office | Floor 27 | Project M08047313 |
| Yard House | Restaurant / Food Service | Cellar, Floors 1, 2, Mezzanine | Project M00366344 Project M00216500 Project M00206671 Project M00216458 |
| Wellspring Philanthropic Fund | Office | Floor 16 | Project M00374212 Project M00374199 Project M00374207 |