💬 Discuss this project
1914Year Built
12Stories
D4Building Class
R10AZoning
62,155 sfGross Floor Area
28Units
LL97 CoveredRent Stabilized0 Active ViolationsFISP: SWARMP
Elevator cooperative · Owner of record: 151-161 Owners · 7,550 sf lot · 8.23 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofRoof replacement, deck and insulation4p · 3 filings · 20 docs
Floor 10Unit 10C7p · 1 filing · 15 docs
Floor 9Unit 9CUnder Construction11p · 1 filing · 10 docs
Floor 8Unit 8D42p · 3 filings · 20 docs
Floor 7Unit 7D27p · 1 filing · 20 docs
Floor 6
Floor 5
Floor 4
Floor 3Unit 3C1p · 1 filing · 4 docs
Floor 2
Floor 1Unit 1CWUnder Construction24p · 3 filings · 19 docs
CellarNew gas service, line, and meter installationUnder Construction1 filing · 20 docs
Site & exteriorTemporary sidewalk shed erection15p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
151-161 Owners11209/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Cowley Engineering406/11/2026
Robert Germain Jr. PE305/08/2026
Volume Space Consulting103/17/2026
A2 Architect508/25/2025
Motoko Tisza208/15/2025
BO Lee Architect705/28/2025
Ethelind Coblin Architect205/03/2024
IP Group104/24/2024
Chang Park Architect103/26/2024
Edward I. Schachner402/23/2023
PCS Engineering402/17/2023
Kinlin Rutherfurd Architects306/13/2022
Charles G. Michel Engineering103/07/2022
Green Design111/27/2019
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Constructors Trades & SkiScaffold1207/08/2026
Executech InteriorsGeneral Contractor807/08/2026
Constructors Trades & SkiGeneral Contractor603/21/2026
Amaro ConstructionGeneral Contractor403/21/2026
Andreu RemodelingGeneral Contractor406/27/2026
Nice PlumbingPlumbing207/08/2026
Pna ContractingGeneral Contractor207/08/2026
Poler ContractingGeneral Contractor207/08/2026
Balog ConstructionGeneral Contractor203/21/2026
Allstate Electrical ContElectrical203/21/2026
BuildopsGeneral Contractor204/09/2026
DNA Plumbing ContractorsPlumbing107/08/2026
NY City PlumberPlumbing109/22/2026
Practical Plumbing & HeatingPlumbing107/08/2026
Tap PlumbingPlumbing107/08/2026
Accurate ElectricalElectrical103/21/2026
Wynne Plumbing & HeatingPlumbing106/27/2026
Cresco ElectricalElectrical103/22/2026
Mike Lewkovicz Electric CompanyElectrical103/21/2026
Redline ElectricElectrical103/22/2026
AbileneGeneral Contractor106/02/2026
Airtronics Air CondGeneral Contractor104/09/2026
Ace Group NYScaffold107/08/2026
New Force ConstructionScaffold107/08/2026
S & S General ConstructionScaffold107/08/2026
Adriatic Plumbing & HeatingPlumbing107/08/2026
Apollo Plumbing & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Cowley Engineering186406/11/2026
AG Engineering8899206/11/2026
Robert F. Germain Jr. PE5100305/08/2026
A2 Architect2504808/25/2025
Metrospec Sia6420208/15/2025
Keyowner Engineering4817505/28/2025
Leo Y Lee Associates2481103/19/2025
D'Antonio Consulting Engineering931202/26/2025
IP Group2542205/03/2024
Wavic Engineering1733104/24/2024
Chang Park Arch663103/26/2024
PCS Engineering3745102/17/2023
H. A. Bader Consultants2332203/07/2022
Charles G Michel Engineering2871103/07/2022
Winton Group Architecture4343102/24/2022
AK Engineering678109/14/2021
Building Lifecycle
All (212)Filed (42)Permit Issued (43)Signed Off (18)Facade (FISP) (22)Violation (35)Inspection (16)Objection (6)Special Inspection (30)
09/21/2026
Permit issued — Plumbing
M01359055-S1-PL
07/09/2026
Permit issued — Suspended Scaffold
M01093095-I1-SC
06/24/2026
Permit issued — General Construction
M01261193-I1-GC
06/15/2026
Signed off — Alteration
Roof replacement as per plans filed herewith. No change to use, egress, or occupancy.
M01143435-I1
06/15/2026
Special inspection requirement — Post-installed Anchors
Eric Cowley
06/15/2026
Special inspection requirement — Final
Eric Cowley
06/15/2026
Special inspection requirement — Tenant Protection Plan Compliance
ARIEL GOLSHAN
06/11/2026
Filed — Alteration
Roof replacement as per plans filed herewith. No change to use, egress, or occupancy.
M01143435-P1
05/26/2026
Permit issued — General Construction
M01359055-I1-GC
05/08/2026
Filed — Alteration
NEW BREECHING, NEW GAS METER ROOM. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01359055-S2
05/08/2026
Filed — Alteration
NEW BREECHING, NEW GAS METER ROOM. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01359055-S1
05/07/2026
Filed — Alteration
NEW BREECHING, NEW GAS METER ROOM. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01359055-I1
05/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Robert Germain Jr.
05/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Robert Germain Jr.
05/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Robert Germain Jr.
03/19/2026
Permit issued — Supported Scaffold
M01372737-I1-SF
03/17/2026
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01372737-I1
02/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Robert Germain Jr.
02/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Robert Germain Jr.
02/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
02/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
02/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Robert Germain Jr.
02/12/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/12/2026
Special inspection requirement — Fuel-Oil Storage and Fuel-Oil Piping Systems
Robert Germain Jr.
02/12/2026
Special inspection requirement — Chimneys and vents
Robert Germain Jr.
02/12/2026
Special inspection requirement — Final
Robert Germain Jr.
12/12/2025
Permit issued — Plumbing
M01261193-S1-PL
12/03/2025
Signed off — Alteration
Plumbing fixture work in apartment 1CW. No change to use egress or occupancy.
M01033231-S1
12/03/2025
Signed off — Alteration
Plumbing fixture work in apartment 1CW. No change to use egress or occupancy.
M01033231-I1
12/03/2025
Signed off — Alteration
Plumbing fixture work in apartment 1CW. No change to use egress or occupancy.
M01033231-S2
11/14/2025
Signed off — Alteration
INTERIOR RENOVATION OF APARTMENT 7D ON THE 7TH FLOOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01075398-S1
11/14/2025
Signed off — Alteration
INTERIOR RENOVATION OF APARTMENT 7D ON THE 7TH FLOOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01075398-I1
10/10/2025
Permit issued — General Construction
M01261193-I1-GC
09/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ann Macklin
09/11/2025
Special inspection requirement — Post-installed Anchors
Ann Macklin
09/11/2025
Special inspection requirement — Final
Ann Macklin
09/11/2025
Special inspection requirement — Energy Code Compliance Inspections
Ann Macklin
09/11/2025
Special inspection requirement — Lighting in dwelling units
Ann Macklin
09/11/2025
Special inspection requirement — Fire-Resistance Rated Construction
Ann Macklin
09/11/2025
Special inspection requirement — Mechanical Systems
Ann Macklin
09/02/2025
Objection resolved — Addressed
09/02/2025
Objection resolved — Addressed
08/27/2025
Objection raised — Cost
08/26/2025
Objection raised — Cost
08/25/2025
Filed — Alteration
INTERIOR RENOVATION OF APARTMENT 7D ON THE 7TH FLOOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01075398-P3
08/15/2025
Filed — Alteration
Modify existing and install new plumbing fixtures in existing apartment as per plan. No change to use, egress or ocupancy under this application.
M01261193-S1
08/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH YOUNG
08/15/2025
Special inspection requirement — Tenant Protection Plan Compliance
JOSEPH YOUNG
08/13/2025
Filed — Alteration
Modify existing and install new plumbing fixtures in existing apartment as per plan. No change to use, egress or ocupancy under this application.
M01261193-I1
08/13/2025
Special inspection requirement — Interior lighting power
JOSEPH YOUNG
08/13/2025
Special inspection requirement — Post-installed Anchors
JOSEPH YOUNG
08/13/2025
Special inspection requirement — Fenestration air leakage
JOSEPH YOUNG
08/13/2025
Special inspection requirement — Energy Code Compliance Inspections
JOSEPH YOUNG
08/13/2025
Special inspection requirement — Air barrier - visual inspection
JOSEPH YOUNG
08/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH YOUNG
07/29/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/25/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/24/2025
Special inspection requirement — Final
JOSEPH YOUNG
07/18/2025
Permit issued — Suspended Scaffold
M01093095-I1-SC
06/18/2025
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH GENERAL CONSTRUCTION RENOVATION. RELOCATE & REPLACE BATHROOM & KITCHEN FIXTURES AS SHOWN ON PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M01043580-S1
Latest 60 of 212 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedNY City Plumber09/21/2026
DOB NOWSuspended ScaffoldPermit IssuedConstructors Trades & Ski07/09/2026
DOB NOWGeneral ConstructionPermit IssuedAndreu Remodeling06/24/2026
DOB NOWGeneral ConstructionPermit IssuedAbilene05/26/2026
DOB NOWSupported ScaffoldPermit IssuedAce Group NY03/19/2026
DOB NOWPlumbingPermit IssuedWynne Plumbing & Heating12/12/2025
DOB NOWGeneral ConstructionPermit IssuedAndreu Remodeling10/10/2025
DOB NOWSuspended ScaffoldPermit IssuedNew Force Construction07/18/2025
DOB NOWGeneral ConstructionSigned-offPna Contracting04/07/2025
DOB NOWGeneral ConstructionSigned-offPna Contracting04/04/2025
DOB NOWPlumbingSigned-offTap Plumbing04/01/2025
DOB NOWSuspended ScaffoldPermit IssuedPna Contracting03/28/2025
DOB NOWPlumbingSigned-offAdriatic Plumbing & Heating01/13/2025
DOB NOWSupported ScaffoldPermit IssuedConstructors Trades & Ski01/06/2025
DOB NOWMechanical SystemsSigned-offPoler Contracting12/31/2024
DOB NOWGeneral ConstructionSigned-offPoler Contracting12/31/2024
DOB NOWSuspended ScaffoldSigned-offSkytrac Access Group12/03/2024
DOB NOWSidewalk ShedPermit IssuedConstructors Trades & Ski11/12/2024
DOB NOWMechanical SystemsSigned-offBuildops10/22/2024
DOB NOWSuspended ScaffoldPermit IssuedNew Force Construction08/14/2024
DOB NOWPlumbingSigned-offNice Plumbing08/12/2024
DOB NOWGeneral ConstructionSigned-offBuildops08/09/2024
DOB NOWGeneral ConstructionSigned-offAirtronics Air Cond08/09/2024
DOB NOWMechanical SystemsSigned-offAmaro Construction08/01/2024
DOB NOWPlumbingSigned-offDNA Plumbing Contractors07/18/2024
DOB NOWGeneral ConstructionSigned-offAmaro Construction06/18/2024
DOB NOWPlumbingSigned-offPractical Plumbing & Heating04/17/2024
DOB NOWGeneral ConstructionSigned-offConstructors Trades & Ski02/05/2024
DOB NOWSupported ScaffoldPermit IssuedConstructors Trades & Ski02/01/2024
DOB NOWSidewalk ShedPermit IssuedConstructors Trades & Ski12/08/2023
DOB NOWGeneral ConstructionSigned-offConstructors Trades & Ski03/06/2023
DOB NOWSupported ScaffoldPermit IssuedConstructors Trades & Ski02/18/2023
DOB NOWGeneral ConstructionSigned-offExecutech Interiors12/28/2022
DOB NOWMechanical SystemsSigned-offExecutech Interiors12/28/2022
DOB NOWSidewalk ShedPermit IssuedConstructors Trades & Ski12/21/2022
DOB NOWGeneral ConstructionSigned-offExecutech Interiors11/02/2022
DOB NOWPlumbingSigned-offApollo Plumbing & Heating04/20/2022
DOB NOWMechanical SystemsSigned-offExecutech Interiors04/19/2022
DOB NOWGeneral ConstructionSigned-offExecutech Interiors04/13/2022
DOB NOWPlumbingSigned-offNice Plumbing11/04/2021
+ 53 more permits on file
2 projects · most recent 05/08/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/08/2026Permit IssuedNY City PlumberGas
08/15/2025Permit IssuedWynne Plumbing & HeatingGas, Water/Sanitary
18 projects · most recent 06/25/2026
General Wiring Boiler Controls
FiledStatusContractorScope
06/25/2026Permit IssuedAbilene ElectricBoiler Controls
12/18/2025Permit IssuedAllstate Electrical Cont1 meters, 1 new_meters
12/17/2025Permit IssuedAllstate Electrical ContGeneral Wiring
08/26/2025CompletePaul M. & Son's Electrical ConGeneral Wiring
03/08/2025CompleteCMY ElectricalGeneral Wiring
10/30/2024Permit IssuedMonforte Electirc—
06/17/2024CompleteD & W Electrical ContGeneral Wiring
06/12/2024CompleteRedline ElectricGeneral Wiring
04/02/2024CompleteElpo Electrical ContgGeneral Wiring
02/24/2024CompleteRedline Electric—
03/21/2023Permit IssuedAccurate ElectricalGeneral Wiring
02/02/2023CompleteArgon ElectricalGeneral Wiring
04/13/2021CompleteGRX Euro ElectricGeneral Wiring
03/08/2021CompleteGRX Euro Electric1 meters, 1 new_meters
10/29/2020CompleteDream Team ElectricalGeneral Wiring
3 projects · most recent 03/17/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
03/17/2026Permit IssuedAce Group NYScaffold
12/20/2022Permit IssuedConstructors Trades & SkiSidewalk Shed
11/27/2019Permit IssuedS & S General ConstructionScaffold
1 project · most recent 03/19/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
03/19/2025Permit IssuedPna ContractingSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 16
DateTypeResultReport
02/12/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/29/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/25/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
04/21/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/03/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/28/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/21/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/21/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/19/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/19/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/06/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/24/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/17/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/24/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/24/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 105
DateRequirementInspectorRole
06/15/2026Post-installed AnchorsEric Cowleyspecial
06/15/2026FinalEric Cowleyprogress
06/15/2026Tenant Protection Plan ComplianceARIEL GOLSHANspecial
05/06/2026Tenant Protection Plan ComplianceRobert Germain Jr.special
05/06/2026Tenant Protection Plan ComplianceRobert Germain Jr.special
05/06/2026Tenant Protection Plan ComplianceRobert Germain Jr.special
02/17/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
02/17/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
02/17/2026HVAC-R and service water heating equipmentRobert Germain Jr.energy_progress
02/17/2026HVAC-R and service water heating system controlsRobert Germain Jr.energy_progress
02/17/2026HVAC-R and service water piping design and insulationRobert Germain Jr.energy_progress
02/12/2026FinalRobert Germain Jr.progress
02/12/2026Fuel-Oil Storage and Fuel-Oil Piping SystemsRobert Germain Jr.special
02/12/2026Chimneys and ventsRobert Germain Jr.special
09/11/2025Energy Code Compliance InspectionsAnn Macklinprogress
09/11/2025Fire-Resistant Penetrations and JointsAnn Macklinspecial
09/11/2025Post-installed AnchorsAnn Macklinspecial
09/11/2025Lighting in dwelling unitsAnn Macklinenergy_progress
09/11/2025Fire-Resistance Rated ConstructionAnn Macklinprogress
09/11/2025Mechanical SystemsAnn Macklinspecial
09/11/2025FinalAnn Macklinprogress
08/15/2025Fire-Resistant Penetrations and JointsJOSEPH YOUNGspecial
08/15/2025Tenant Protection Plan ComplianceJOSEPH YOUNGspecial
08/13/2025Fire-Resistant Penetrations and JointsJOSEPH YOUNGspecial
08/13/2025Interior lighting powerJOSEPH YOUNGenergy_progress
Latest 25 of 105.
▾Documents — 753 on file (BIS + DOB NOW)
▸Plans & Drawings42
▸DOB NOWPlans/Sketch39
09/02/2026M00656519-S1Request digital key ↗
09/02/2026M00656519-S2Request digital key ↗
09/02/2026M00656519-P1Request digital key ↗
Showing 3 of 39 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold3
09/05/2026M00273233-I1Request digital key ↗
09/05/2026M00255099-I1Request digital key ↗
08/15/2026M00255099-P1Request digital key ↗
▸Applications & Permits118
▸BISPLAN / WORK APPROVAL APPLICATION60
04/22/2021123871293Open ↗
01/02/2021140870564Open ↗
12/16/2020140870564Open ↗
Showing 3 of 60 on file for this type
▸BISWORK PERMIT APPLICATION58
09/09/2020140941827Open ↗
02/12/2020123871293Open ↗
02/12/2020123871293Open ↗
Showing 3 of 58 on file for this type
▸Seals & Professional Certifications226
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION65
08/09/2019123871293Open ↗
08/09/2019123871293Open ↗
05/17/2019123871293Open ↗
Showing 3 of 65 on file for this type
▸DOB NOWProgress Inspector Seal & Signature51
09/28/2026M00656519-S2Open ↗
09/25/2026M01043580-S2Open ↗
09/25/2026M01043580-S2Open ↗
Showing 3 of 51 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature40
09/28/2026M00656519-S2Open ↗
09/28/2026M00656519-S2Open ↗
09/25/2026M01043580-S2Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature39
09/05/2026M00255099-I1Open ↗
09/02/2026M00656519-P1Open ↗
09/02/2026M00656519-I1Open ↗
Showing 3 of 39 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
10/06/2017140703656Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
10/06/2017140703656Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
10/06/2017140703656Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment49
▸BISSELF-CERT PLUMBING NOTICE19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE15
08/30/2019123871293Open ↗
05/17/2019123871293Open ↗
04/17/2018123454056Open ↗
Showing 3 of 15 on file for this type
▸BISSCHEDULE B - PLUMBING9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISEQUIPMENT USE PERMITS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection14
▸BISTenant Protection Plan and Notes8
05/17/2019123871293Open ↗
04/17/2018123454056Open ↗
08/07/2017123305645Open ↗
Showing 3 of 8 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM4
08/09/2019123871293Open ↗
05/17/2019123871293Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWTenant Protection Plan2
09/05/2026M00255099-I1Open ↗
Showing 1 of 2 on file for this type
▸Environmental & Asbestos59
▸DOB NOWDEP ACP-5: Asbestos Assessment Report30
09/02/2026M00656519-S1Open ↗
09/02/2026M00656519-S2Open ↗
09/02/2026M00656519-P1Open ↗
Showing 3 of 30 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)14
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
05/17/2019123871293Open ↗
Showing 3 of 14 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/27/2026M01033231-S2Open ↗
08/27/2026M01033231-I1Open ↗
08/27/2026M01033231-S1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance57
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS19
08/09/2019123871293Open ↗
05/17/2019123871293Open ↗
05/17/2019123871293Open ↗
Showing 3 of 19 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS13
03/22/2021123871293Open ↗
05/07/2019123305645Open ↗
12/11/2018123454056Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY6
03/22/2021123871293Open ↗
01/04/2021140870564Open ↗
12/08/2020140941827Open ↗
Showing 3 of 6 on file for this type
▸BISTR8: Energy Code Progress Inspections5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
Showing 2 of 3 on file for this type
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISNYCECC ANALYSIS2
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
01/04/2021140870564Open ↗
12/08/2020140941827Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
09/02/2026M00524503-I1Open ↗
Showing 1 of 2 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
10/06/2017140703656Open ↗
▸BISENERGY CODE 1ST REVIEW COMPLETE1
05/04/2016122643728Open ↗
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY9
03/04/2021123871293Open ↗
03/04/2021123871293Open ↗
01/04/2021140870564Open ↗
Showing 3 of 9 on file for this type
▸BISMASONRY1
09/08/2020140941827Open ↗
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
09/08/2020140941827Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
09/08/2020140941827Open ↗
▸Approvals, Objections & Sign-offs51
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST23
05/27/2021123871293Open ↗
01/04/2021140870564Open ↗
12/08/2020140941827Open ↗
Showing 3 of 23 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION13
05/11/2018140703656Open ↗
03/06/2017122643728Open ↗
03/06/2017122643728Open ↗
Showing 3 of 13 on file for this type
▸BISADMINISTRATIVE OBJECTIONS13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISSUPERSEDING LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFINAL1
09/08/2020140941827Open ↗
▸Cost, Insurance & Ownership49
▸BISCOST AFFIDAVIT47
05/27/2021123871293Open ↗
05/05/2021123871293Open ↗
01/02/2021140870564Open ↗
Showing 3 of 47 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
01/04/2021140870564Open ↗
12/08/2020140941827Open ↗
▸Filing & Intake Forms63
▸BISADDITIONAL INFORMATION27
01/02/2021140870564Open ↗
12/14/2020140870564Open ↗
09/08/2020140941827Open ↗
Showing 3 of 27 on file for this type
▸BISEFILING COVER SHEET23
05/17/2019123871293Open ↗
05/17/2019123871293Open ↗
04/17/2018123454056Open ↗
Showing 3 of 23 on file for this type
▸BISBOROUGH INTAKE FORM7
05/07/2019123305645Open ↗
05/02/2019123305645Open ↗
12/11/2018123454056Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
08/20/2020140941827Open ↗
09/25/2019140870564Open ↗
10/06/2017140703656Open ↗
Showing 3 of 6 on file for this type
▸Other Documents13
▸DOB NOWCalculations3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWManufacturer's Specifications3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form2
05/23/2016122643728Open ↗
Showing 1 of 2 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/25/2026M01143435-P1Open ↗
Showing 1 of 2 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
10/19/2017123305645Open ↗