| Owner | Filings | Most Recent |
|---|---|---|
| KINGS GROUP NY | 18 | 07/08/2026 |
| T-MOBILE | 3 | 03/22/2026 |
| NYCAN BUILDERS | 2 | 03/21/2026 |
| FC BEEKMAN ASSOCIATES | 2 | 03/21/2026 |
| PACE COLLEGE PLAZA | 2 | 03/21/2026 |
| SHAWMUT DESIGN CONSTRUCTION | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| FXCOLLABORATIVE ARCHITECTS LLP | 19 | 07/28/2026 |
| TAREK M. ZEID, PE, PLLC | 3 | 06/24/2026 |
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 06/24/2026 |
| KOHLER RONAN, LLC | 18 | 05/14/2026 |
| GRM CONSULTANTS LLC | 1 | 03/22/2026 |
| BEDNASH CONSULTING, INC. | 3 | 12/10/2025 |
| VS CONSULTING ENGINEERING, PC | 1 | 11/10/2025 |
| WALTER T. GORMAN, P.E., P.C. | 1 | 10/15/2025 |
| PS ENGINEERS, INC. | 3 | 06/19/2025 |
| KZ ENGINEERING, P.C | 2 | 05/20/2025 |
| ASDA ARCHITECTURE + DESIGN | 1 | 03/11/2025 |
| JACOB FEINBERG KATZ & MICHAELI CONS | 10 | 02/12/2025 |
| BRAND ACCESS SOLUTIONS | 7 | 12/18/2024 |
| HOWARD I SHAPIRO & ASSOCIATES | 7 | 05/15/2024 |
| ASHRAF CORP | 1 | 04/04/2024 |
| LOCI ARCHITECTURE PLLC | 2 | 01/17/2024 |
| LERA CONSULTING STRUCTURAL ENGINEER | 2 | 12/18/2023 |
| JAMES H. FAHEY | 4 | 10/04/2023 |
| HIGHLAND ASSOCIATES | 2 | 06/08/2023 |
| MOHAMMAD AHEAD, PE | 1 | 05/09/2023 |
| KMB DESIGN GROUP, LLC | 1 | 06/13/2022 |
| CANNON DESIGN | 2 | 09/07/2021 |
| THE MTM DESIGN GROUP, LLC | 1 | 02/15/2021 |
| YSRAEL A. SEINUK, P.C. | 1 | 02/13/2020 |
| SAFWAY ATLANTIC LLC | 1 | 02/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| WALTER T GORMAN PE | 100 | 03/21/2026 |
| JMV ASSOCIATES | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 16 | 03/21/2026 |
| HOWARD I SHAPIRO ASSOCIATES | 14 | 03/21/2026 |
| PS ENGINEERS | 8 | 03/21/2026 |
| KMA DESIGNS LLC | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 6 | 03/21/2026 |
| GC1 EXPEDITING | 2 | 03/21/2026 |
| CCM CONSULTING GROUP, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TURNER CONSTRUCTION COMPANY | General Contractor | 31 | 08/20/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 15 | 07/08/2026 |
| KINGS GROUP NY CORP | General Contractor | 13 | 07/08/2026 |
| TITAN INDUSTRIAL SVC CORP | General Contractor | 10 | 04/09/2026 |
| ALMAR PLUMBING & HTG CORP | Plumbing | 7 | 07/08/2026 |
| PREMIER FIRE SPRNKLR CO | Fire Protection | 6 | 09/30/2026 |
| RAMAPO COMMUNICATION CORP | General Contractor | 6 | 03/21/2026 |
| TRIBUTE RESTORATION INC | General Contractor | 5 | 04/09/2026 |
| KMM TELECOMMUNICATIONS | General Contractor | 4 | 04/09/2026 |
| RAEL AUTOMATIC SPR.CO INC | Fire Protection | 4 | 07/08/2026 |
| HAS, MEHMET | Electrical | 3 | 03/21/2026 |
| PTS DATA CENTER SOLUTION* | General Contractor | 3 | 03/21/2026 |
| KATZEN, BARRY | Electrical | 3 | 03/21/2026 |
| MAC FELDER INC | Plumbing | 3 | 07/08/2026 |
| JANSONS ASSOICATES, INC | General Contractor | 3 | 04/09/2026 |
| FRANK PUGLIESE | Electrical | 2 | 03/21/2026 |
| L.E.C.INC | General Contractor | 2 | 03/21/2026 |
| SQUAN CONSTRUCTION SERVIC | General Contractor | 2 | 03/21/2026 |
| MANENGEERING BUREAU INC | Fire Protection | 2 | 07/08/2026 |
| PUGLIESE FRANK | Electrical | 2 | 03/21/2026 |
| ACTIVE SIGNS | Scaffold | 1 | 07/08/2026 |
| FIVE TOWN NEON SIGN CO IN | Scaffold | 1 | 07/08/2026 |
| BIGMAN BROS., INC. | Electrical | 1 | 03/22/2026 |
| SERVICE SIGN ERECTORS | Scaffold | 1 | 07/08/2026 |
| CAPUTEK ELEC'L SERVICES, | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FENAGH, INC | 6942 | 19 | 07/22/2026 |
| CLARKE ENGINEERING SERVIC | 3795 | 2 | 06/24/2026 |
| FRANCISCO D. PEREZ PE | 3306 | 4 | 07/25/2025 |
| SOCOTEC ENGINEERING | 4983 | 2 | 02/12/2025 |
| DOMANI INSPECTION SERVICE | 843 | 10 | 05/15/2024 |
| STRUCTURAL CONSULTING SER | 1919 | 3 | 10/04/2023 |
| PSI AGENCY INC. | 254 | 3 | 06/08/2023 |
| KMB DESIGN GROUP, LLC | 513 | 1 | 06/13/2022 |
| PROJECT TACTICAL SOLUTION | 5859 | 8 | 03/08/2022 |
| THE MTM DESIGN GROUP, LLC | 1319 | 1 | 02/15/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Standpipe | Permit Issued | PREMIER FIRE SPRNKLR CO | 09/29/2026 |
| DOB NOW | General Construction | Signed-off | TURNER CONSTRUCTION COMPANY | 08/18/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | PALLADIUM WINDOW SOLUTION | 06/25/2026 |
| DOB NOW | Supported Scaffold | Signed-off | KINGS GROUP NY CORP | 04/22/2026 |
| DOB NOW | Supported Scaffold | Signed-off | KINGS GROUP NY CORP | 04/21/2026 |
| DOB NOW | Sprinklers | Signed-off | RAEL AUTOMATIC SPR.CO INC | 04/21/2026 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 04/14/2026 |
| DOB NOW | Structural | Signed-off | JANSONS ASSOICATES, INC | 01/08/2026 |
| DOB NOW | Sprinklers | Signed-off | PREMIER FIRE SPRNKLR CO | 01/06/2026 |
| DOB NOW | Plumbing | Signed-off | ALMAR PLUMBING & HTG CORP | 01/06/2026 |
| DOB NOW | Standpipe | Signed-off | PREMIER FIRE SPRNKLR CO | 01/06/2026 |
| DOB NOW | Mechanical Systems | Signed-off | JANSONS ASSOICATES, INC | 12/02/2025 |
| DOB NOW | General Construction | Signed-off | TURNER CONSTRUCTION COMPANY | 10/31/2025 |
| DOB NOW | General Construction | Signed-off | TURNER CONSTRUCTION COMPANY | 10/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | TURNER CONSTRUCTION COMPANY | 10/21/2025 |
| DOB NOW | Foundation | Signed-off | TURNER CONSTRUCTION COMPANY | 10/21/2025 |
| DOB NOW | General Construction | Signed-off | TURNER CONSTRUCTION COMPANY | 10/07/2025 |
| DOB NOW | Mechanical Systems | Signed-off | TURNER CONSTRUCTION COMPANY | 10/07/2025 |
| DOB NOW | Foundation | Signed-off | TURNER CONSTRUCTION COMPANY | 10/07/2025 |
| DOB NOW | Structural | Signed-off | TURNER CONSTRUCTION COMPANY | 10/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | TURNER CONSTRUCTION COMPANY | 10/03/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | TRIBUTE RESTORATION INC | 10/02/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 09/26/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 09/26/2025 |
| DOB NOW | Construction Fence | Signed-off | SAFWAY ATLANTIC, LLC | 09/26/2025 |
| DOB NOW | Structural | Permit Issued | SERVICE SIGN ERECTORS CO | 08/11/2025 |
| DOB NOW | Sign | Permit Issued | SERVICE SIGN ERECTORS CO | 08/08/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | TRIBUTE RESTORATION INC | 07/31/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 06/05/2025 |
| DOB NOW | General Construction | Signed-off | TRIBUTE RESTORATION INC | 05/15/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | TRIBUTE RESTORATION INC | 05/15/2025 |
| DOB NOW | Standpipe | Signed-off | PREMIER FIRE SPRNKLR CO | 05/09/2025 |
| DOB NOW | Supported Scaffold | Signed-off | KINGS GROUP NY CORP | 04/23/2025 |
| DOB NOW | Supported Scaffold | Signed-off | KINGS GROUP NY CORP | 04/23/2025 |
| DOB NOW | Structural | Signed-off | TURNER CONSTRUCTION COMPANY | 04/23/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | TITAN INDUSTRIAL SVC CORP | 02/19/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | TITAN INDUSTRIAL SVC CORP | 02/18/2025 |
| DOB NOW | Plumbing | Signed-off | ALMAR PLUMBING & HTG CORP | 01/30/2025 |
| DOB NOW | Standpipe | Signed-off | RAEL AUTOMATIC SPR.CO INC | 01/28/2025 |
| DOB NOW | Sprinklers | Signed-off | PREMIER FIRE SPRNKLR CO | 01/06/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/09/2026 | Signed-off | JANSONS ASSOICATES, INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool __Junk__ - 9,000 BTU ×260 Climacool UWWS70AFS-0001 68 tons · Chiller ×20 Nortek ITF 320,000 BTU · Ahu ×4 CSU-10K 465,000 BTU · Ahu ×2 CSU-16K 1,022,000 BTU · Ahu ×2 CSU-28K 1,393,000 BTU · Ahu ×2 CSU-40K 1,157,000 BTU · Ahu ×2 CSU-8K 342,000 BTU · Ahu ×2 Aaon V3-BRB-3-0-26HC-12M 80,000 BTU · Ahu ×2 Daikin RXYQ72AATJB 6 tons · Vrf Outdoor ×2 Ventilation Aaon 256152 369,000 BTU · Heat Pump Outdoor ×2 |
| 05/14/2026 | Signed-off | TURNER CONSTRUCTION COMPA | Others | Other N/A n/a Ductwork |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Signed-off | PREMIER FIRE SPRNKLR CO | Sprinkler System |
| 05/14/2026 | Signed-off | RAEL AUTOMATIC SPR.CO INC | 975 heads |
| 04/24/2026 | Permit Issued | PREMIER FIRE SPRNKLR CO | 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Signed-off | ALMAR PLUMBING & HTG CORP | Storm, Water/Sanitary |
| 05/14/2026 | Signed-off | ALMAR PLUMBING & HTG CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2026 | Permit Issued | TUXEDO ELEC'L CONTR'G INC | — |
| 09/14/2026 | Permit Issued | TUXEDO ELEC'L CONTR'G INC | — |
| 09/14/2026 | Permit Issued | TUXEDO ELEC'L CONTR'G INC | — |
| 09/14/2026 | Permit Issued | TUXEDO ELEC'L CONTR'G INC | — |
| 04/02/2026 | Complete | ECO ELECTRICAL SERVCS LLC | General Wiring |
| 04/02/2026 | Permit Issued | ECO ELECTRICAL SERVCS LLC | General Wiring |
| 02/09/2026 | Complete | ECO ELECTRICAL SERVCS LLC | General Wiring |
| 11/24/2025 | Permit Issued | ALLBRIGHT ELECTRIC, INC | — |
| 03/24/2025 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| 01/06/2025 | Complete | B & G ELECL CONTR OF NY I | — |
| 10/30/2024 | Complete | B & G ELECL CONTR OF NY I | General Wiring |
| 10/18/2024 | Permit Issued | B & G ELECL CONTR OF NY I | 2 meters, 2 new_meters |
| 10/01/2024 | Complete | S. J. ELECTRIC INC. | General Wiring |
| 08/06/2024 | Permit Issued | PRIMIANO CORP DBA | 3 meters |
| 06/22/2023 | Complete | TEAM ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Permit Issued | SERVICE SIGN ERECTORS CO | 2 scope_items |
| 06/09/2026 | Signed-off | PREMIER FIRE SPRNKLR CO | Steel |
| 06/18/2024 | Signed-off | TURNER CONSTRUCTION COMPA | Steel |
| 02/13/2020 | — | — | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2025 | Signed-off | KINGS GROUP NY CORP | Sidewalk Shed |
| 04/04/2024 | Signed-off | KINGS GROUP NY CORP | Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2025 | Signed-off | TRIBUTE RESTORATION INC | Suspended Scaffold (SC) |
| 06/19/2025 | Permit Issued | DOMUM, LLC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/27/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/22/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/21/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/20/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/14/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/12/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/12/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/19/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/16/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/01/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 01/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/18/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/21/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/18/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/10/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/13/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 02/21/2024 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 02/21/2024 | Certified Sprinkler (PL) - SP - Roughing | Certified | View ↗ |
| 02/19/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/30/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/24/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/27/2026 | Public Assembly Emergency Lighting | AILANTO DANIEL MINAWI | progress |
| 07/27/2026 | Public Assembly Emergency Lighting | AILANTO DANIEL MINAWI | progress |
| 07/01/2026 | Final | AILANTO DANIEL MINAWI | progress |
| 07/01/2026 | Air barrier continuity plan testing | AILANTO DANIEL MINAWI | energy_progress |
| 07/01/2026 | Insulation placement and R values | AILANTO DANIEL MINAWI | energy_progress |
| 07/01/2026 | Exterior lighting power | AILANTO DANIEL MINAWI | energy_progress |
| 07/01/2026 | Lighting controls | AILANTO DANIEL MINAWI | energy_progress |
| 07/01/2026 | Air barrier - visual inspection | AILANTO DANIEL MINAWI | energy_progress |
| 07/01/2026 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 07/01/2026 | Sprayed fire-resistant materials | AILANTO DANIEL MINAWI | special |
| 06/24/2026 | Post-installed Anchors | Brian Clarke | special |
| 06/24/2026 | Final | tarek zeid | progress |
| 06/24/2026 | Structural Stability – Alterations of existing buildings | Brian Clarke | special |
| 06/13/2026 | Sprayed fire-resistant materials | AILANTO DANIEL MINAWI | special |
| 06/13/2026 | Alternative Materials - OTCR Buildings Bulletin Number | AILANTO DANIEL MINAWI | special |
| 06/13/2026 | Exterior Insulation and Finish Systems (EIFS) | AILANTO DANIEL MINAWI | special |
| 06/13/2026 | Fire-Resistance Rated Construction | AILANTO DANIEL MINAWI | progress |
| 06/13/2026 | Energy Code Compliance Inspections | AILANTO DANIEL MINAWI | progress |
| 06/13/2026 | Final | AILANTO DANIEL MINAWI | progress |
| 06/13/2026 | Insulation placement and R values | AILANTO DANIEL MINAWI | energy_progress |
| 06/13/2026 | Lighting in dwelling units | AILANTO DANIEL MINAWI | energy_progress |
| 06/13/2026 | Lighting controls | AILANTO DANIEL MINAWI | energy_progress |
| 06/13/2026 | Fenestration areas | AILANTO DANIEL MINAWI | energy_progress |
| 06/13/2026 | Exterior lighting power | AILANTO DANIEL MINAWI | energy_progress |
| 06/13/2026 | Air barrier - visual inspection | AILANTO DANIEL MINAWI | energy_progress |