← Back
Other college and university
Pace University - NYC Campus
154 NASSAU STREET · Financial District-Battery Park City · BIN 1001357
💬 Discuss this project
1968Year Built
18Stories
W6Building Class
C6-4Zoning
526,781 sfGross Floor Area
0Units
LL97 Covered1 Open Violation 0 unresolved · 1 paperwork only ▸FISP: SAFEFDNY Report ↗
Other college and university · Owner of record: PACE UNIVERSITY · 108,027 sf lot · 4.88 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction15p · 12 filings
Penthouse1 filing
Floor 63p · 3 filings
Floor 55p · 4 filings
Floor 46p · 6 filings
Floor 3Under Construction4p · 5 filings · 4 docs
Floor 2Under Construction2p · 5 filings · 4 docs
Floor 1Under Construction4p · 5 filings · 4 docs
CellarUnder Construction1p · 5 filings · 4 docs
Sub-BasementUnder Construction5 filings · 4 docs
Site & exterior14 filings · 20 docs
Filed — no permit issued10 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KINGS GROUP NY1807/08/2026
T-MOBILE303/22/2026
NYCAN BUILDERS203/21/2026
FC BEEKMAN ASSOCIATES203/21/2026
PACE COLLEGE PLAZA203/21/2026
SHAWMUT DESIGN CONSTRUCTION103/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
WALTER T GORMAN PE10003/21/2026
JMV ASSOCIATES403/21/2026
A1 EXPEDITING SERVICE1603/21/2026
HOWARD I SHAPIRO ASSOCIATES1403/21/2026
PS ENGINEERS803/21/2026
KMA DESIGNS LLC203/21/2026
SYNERGY BUILDING CONSULTANTS203/21/2026
CONSTRUCTION PERMIT SERVICES603/21/2026
GC1 EXPEDITING203/21/2026
CCM CONSULTING GROUP, INC.203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TURNER CONSTRUCTION COMPANYGeneral Contractor3108/20/2026
SAFWAY ATLANTIC, LLCGeneral Contractor1507/08/2026
KINGS GROUP NY CORPGeneral Contractor1307/08/2026
TITAN INDUSTRIAL SVC CORPGeneral Contractor1004/09/2026
ALMAR PLUMBING & HTG CORPPlumbing707/08/2026
PREMIER FIRE SPRNKLR COFire Protection609/30/2026
RAMAPO COMMUNICATION CORPGeneral Contractor603/21/2026
TRIBUTE RESTORATION INCGeneral Contractor504/09/2026
KMM TELECOMMUNICATIONSGeneral Contractor404/09/2026
RAEL AUTOMATIC SPR.CO INCFire Protection407/08/2026
HAS, MEHMETElectrical303/21/2026
PTS DATA CENTER SOLUTION*General Contractor303/21/2026
KATZEN, BARRYElectrical303/21/2026
MAC FELDER INCPlumbing307/08/2026
JANSONS ASSOICATES, INCGeneral Contractor304/09/2026
FRANK PUGLIESEElectrical203/21/2026
L.E.C.INCGeneral Contractor203/21/2026
SQUAN CONSTRUCTION SERVICGeneral Contractor203/21/2026
MANENGEERING BUREAU INCFire Protection207/08/2026
PUGLIESE FRANKElectrical203/21/2026
ACTIVE SIGNSScaffold107/08/2026
FIVE TOWN NEON SIGN CO INScaffold107/08/2026
BIGMAN BROS., INC.Electrical103/22/2026
SERVICE SIGN ERECTORSScaffold107/08/2026
CAPUTEK ELEC'L SERVICES,Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FENAGH, INC69421907/22/2026
CLARKE ENGINEERING SERVIC3795206/24/2026
FRANCISCO D. PEREZ PE3306407/25/2025
SOCOTEC ENGINEERING4983202/12/2025
DOMANI INSPECTION SERVICE8431005/15/2024
STRUCTURAL CONSULTING SER1919310/04/2023
PSI AGENCY INC.254306/08/2023
KMB DESIGN GROUP, LLC513106/13/2022
PROJECT TACTICAL SOLUTION5859803/08/2022
THE MTM DESIGN GROUP, LLC1319102/15/2021
Building Lifecycle
All (300)Filed (55)Permit Issued (74)Signed Off (33)Facade (FISP) (9)Violation (30)Inspection (22)Objection (47)Special Inspection (30)
09/29/2026
Permit issued — Standpipe
M01386388-I1-EW-SD
08/18/2026
Permit issued — General Construction
M01310724-I1-GC
08/12/2026
Signed off — Alteration
Preoposed removal of HVAC units, condensers, ducts, piping, registers, controls, exhaust fans, High pressure steam piping form cellar to penthouse and roof , all as per plan. No change to use, occupancy or egress.
M00907240-S3
07/29/2026
Signed off — Alteration
File SUSPENDED SCAFFOLD OUTRIGGER SYSTEMS FOR FACADE RESTORATION AND INSPECTION.
M01261430-I1
07/28/2026
Filed — No Work
M01272064-P1
07/28/2026
Filed — No Work
M01272069-P1
07/27/2026
Special inspection requirement — Public Assembly Emergency Lighting
AILANTO DANIEL MINAWI
07/27/2026
Special inspection requirement — Public Assembly Emergency Lighting
AILANTO DANIEL MINAWI
07/22/2026
Filed — Alteration
Proposed repair of the underside of the existing walking bridge in the courtyard, replacement of the existing fence in the courtyard, all as per plan. No change of use, occupancy, or egress.
M01310724-P1
07/16/2026
Signed off — Alteration
Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01215384-I1
07/16/2026
Signed off — Alteration
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLDING. NO CHANGE IN USE, OCCUPANCY OR EGRESS. WORK SHALL COMPLY WITH CHAPTER 33 OF NYCC.
M01021932-I1
07/01/2026
Special inspection requirement — Air barrier continuity plan testing
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Lighting controls
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Exterior lighting power
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Air barrier - visual inspection
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Sprayed fire-resistant materials
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Final
AILANTO DANIEL MINAWI
07/01/2026
Special inspection requirement — Insulation placement and R values
AILANTO DANIEL MINAWI
06/30/2026
Signed off — Alteration
Install new sprinkler system, all as per plan. no change of use, egress, or occupancy.
M00976708-S4
06/25/2026
Signed off — Alteration
Permanent structural framing and supports for the installation of a kitchen exhaust riser under parent Mechanical Job # M00976708-S4.
M01322205-I1
06/25/2026
Permit issued — Suspended Scaffold
M01415541-I1-SC
06/24/2026
Filed — Alteration
STRUCTURAL APPLICATION FOR PROPOSED INSTALLATION OF A NON-ILLUMINATED BANNER ACCESSORY BUSINESS SIGN (56'-6" X 54'-5") WALL MOUNTED, ACCESSORY TO AN EDUCATION COMMUNITY FACILITY.
M01234767-P1
06/24/2026
Filed — Alteration
Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy.
M01415541-I1
06/24/2026
Special inspection requirement — Final
tarek zeid
06/24/2026
Special inspection requirement — Post-installed Anchors
Brian Clarke
06/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Brian Clarke
06/22/2026
Signed off — Alteration
Install new sprinkler system, all as per plan. no change of use, egress, or occupancy.
M00976708-S3
06/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Air barrier - visual inspection
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Fenestration areas
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Lighting controls
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Lighting in dwelling units
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Interior lighting power
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Insulation placement and R values
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Final
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Energy Code Compliance Inspections
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Exterior lighting power
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Fenestration air leakage
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Air barrier continuity plan testing
AILANTO DANIEL MINAWI
06/13/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
AILANTO DANIEL MINAWI
06/11/2026
Cycle 9 facade report signed — SAFE
06/10/2026
Signed off — Alteration
Install new sprinkler system, all as per plan. no change of use, egress, or occupancy.
M00976708-S2
06/09/2026
Filed — Alteration
Install new sprinkler system, all as per plan. no change of use, egress, or occupancy.
M00976708-P9
05/18/2026
Signed off — Alteration
Proposed Interior structural modification, new foundation all as per plan. No change of egress, occupancy or use.
M00960574-I1
05/14/2026
Filed — Alteration
Preoposed removal of HVAC units, condensers, ducts, piping, registers, controls, exhaust fans, High pressure steam piping form cellar to penthouse and roof , all as per plan. No change to use, occupancy or egress.
M00907240-P5
05/07/2026
Signed off — Alteration
Proposed facade repair as per plan for East building and Tower. No change of use, egress or occupancy.
M00930848-I1
05/07/2026
Signed off — Alteration
M00959676-I1
05/06/2026
Signed off — Alteration
Removal of existing stairs and stringer in Stairwell J for future construction. No change to use, occupancy or egress.
M00920573-I1
05/05/2026
Signed off — Alteration
Install new sprinkler system, all as per plan. no change of use, egress, or occupancy.
M00976708-S1
05/05/2026
Signed off — Alteration
Proposed Interior structural modification, new foundation all as per plan. No change of egress, occupancy or use.
M00960574-S1
05/05/2026
Signed off — Alteration
M00919640-I1
04/29/2026
Signed off — Alteration
CONSTRUCTION FENCE AS PER DRAWINGS. CONSTRUCTION FENCE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. DOT PERMITS BY OTHERS FOR FENCE INSTALLED ON SIDEWALK/ROADWAY.
M00954692-I1
04/27/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/27/2026
Objection resolved — Resolved
04/24/2026
Filed — Alteration
PROPOSED NEW STANDPIPE SYSTEM IN STAIR J, STAGE AREA, AND FLOOR, ALL AS PER PLAN. NO CHANGE TO EGRESS, OCCUPANCY, OR USE.
M01386388-I1
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStandpipePermit IssuedPREMIER FIRE SPRNKLR CO09/29/2026
DOB NOWGeneral ConstructionSigned-offTURNER CONSTRUCTION COMPANY08/18/2026
DOB NOWSuspended ScaffoldSigned-offPALLADIUM WINDOW SOLUTION06/25/2026
DOB NOWSupported ScaffoldSigned-offKINGS GROUP NY CORP04/22/2026
DOB NOWSupported ScaffoldSigned-offKINGS GROUP NY CORP04/21/2026
DOB NOWSprinklersSigned-offRAEL AUTOMATIC SPR.CO INC04/21/2026
DOB NOWSignSigned-offACTIVE SIGNS INC04/14/2026
DOB NOWStructuralSigned-offJANSONS ASSOICATES, INC01/08/2026
DOB NOWSprinklersSigned-offPREMIER FIRE SPRNKLR CO01/06/2026
DOB NOWPlumbingSigned-offALMAR PLUMBING & HTG CORP01/06/2026
DOB NOWStandpipeSigned-offPREMIER FIRE SPRNKLR CO01/06/2026
DOB NOWMechanical SystemsSigned-offJANSONS ASSOICATES, INC12/02/2025
DOB NOWGeneral ConstructionSigned-offTURNER CONSTRUCTION COMPANY10/31/2025
DOB NOWGeneral ConstructionSigned-offTURNER CONSTRUCTION COMPANY10/23/2025
DOB NOWMechanical SystemsSigned-offTURNER CONSTRUCTION COMPANY10/21/2025
DOB NOWFoundationSigned-offTURNER CONSTRUCTION COMPANY10/21/2025
DOB NOWGeneral ConstructionSigned-offTURNER CONSTRUCTION COMPANY10/07/2025
DOB NOWMechanical SystemsSigned-offTURNER CONSTRUCTION COMPANY10/07/2025
DOB NOWFoundationSigned-offTURNER CONSTRUCTION COMPANY10/07/2025
DOB NOWStructuralSigned-offTURNER CONSTRUCTION COMPANY10/03/2025
DOB NOWMechanical SystemsSigned-offTURNER CONSTRUCTION COMPANY10/03/2025
DOB NOWSuspended ScaffoldSigned-offTRIBUTE RESTORATION INC10/02/2025
DOB NOWProtection and Mechanical MethodsSigned-offSAFWAY ATLANTIC, LLC09/26/2025
DOB NOWProtection and Mechanical MethodsSigned-offSAFWAY ATLANTIC, LLC09/26/2025
DOB NOWConstruction FenceSigned-offSAFWAY ATLANTIC, LLC09/26/2025
DOB NOWStructuralPermit IssuedSERVICE SIGN ERECTORS CO08/11/2025
DOB NOWSignPermit IssuedSERVICE SIGN ERECTORS CO08/08/2025
DOB NOWSuspended ScaffoldSigned-offTRIBUTE RESTORATION INC07/31/2025
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP06/05/2025
DOB NOWGeneral ConstructionSigned-offTRIBUTE RESTORATION INC05/15/2025
DOB NOWSuspended ScaffoldPermit IssuedTRIBUTE RESTORATION INC05/15/2025
DOB NOWStandpipeSigned-offPREMIER FIRE SPRNKLR CO05/09/2025
DOB NOWSupported ScaffoldSigned-offKINGS GROUP NY CORP04/23/2025
DOB NOWSupported ScaffoldSigned-offKINGS GROUP NY CORP04/23/2025
DOB NOWStructuralSigned-offTURNER CONSTRUCTION COMPANY04/23/2025
DOB NOWProtection and Mechanical MethodsSigned-offTITAN INDUSTRIAL SVC CORP02/19/2025
DOB NOWProtection and Mechanical MethodsSigned-offTITAN INDUSTRIAL SVC CORP02/18/2025
DOB NOWPlumbingSigned-offALMAR PLUMBING & HTG CORP01/30/2025
DOB NOWStandpipeSigned-offRAEL AUTOMATIC SPR.CO INC01/28/2025
DOB NOWSprinklersSigned-offPREMIER FIRE SPRNKLR CO01/06/2025
+ 60 more permits on file
2 projects · most recent 06/09/2026
Heating and Air Conditioning Systems Ventilation Systems Others
FiledStatusContractorScopeMake / Model / Capacity
06/09/2026Signed-offJANSONS ASSOICATES, INCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
__Junk__ - 9,000 BTU ×260
Climacool UWWS70AFS-0001 68 tons · Chiller ×20
Nortek ITF 320,000 BTU · Ahu ×4
CSU-10K 465,000 BTU · Ahu ×2
CSU-16K 1,022,000 BTU · Ahu ×2
CSU-28K 1,393,000 BTU · Ahu ×2
CSU-40K 1,157,000 BTU · Ahu ×2
CSU-8K 342,000 BTU · Ahu ×2
Aaon V3-BRB-3-0-26HC-12M 80,000 BTU · Ahu ×2
Daikin RXYQ72AATJB 6 tons · Vrf Outdoor ×2
Climatemaster TRC09 9,000 BTU · Wshp ×260
TRC15 14,000 BTU · Wshp ×14
Ventilation
Aaon 256152 369,000 BTU · Heat Pump Outdoor ×2
05/14/2026Signed-offTURNER CONSTRUCTION COMPAOthers
Other
N/A n/a Ductwork
3 projects · most recent 06/09/2026
Sprinkler System
FiledStatusContractorScope
06/09/2026Signed-offPREMIER FIRE SPRNKLR COSprinkler System
05/14/2026Signed-offRAEL AUTOMATIC SPR.CO INC975 heads
04/24/2026Permit IssuedPREMIER FIRE SPRNKLR CO1 outlets
2 projects · most recent 06/09/2026
Water/Sanitary Storm Gas
FiledStatusContractorScope
06/09/2026Signed-offALMAR PLUMBING & HTG CORPStorm, Water/Sanitary
05/14/2026Signed-offALMAR PLUMBING & HTG CORPGas, Water/Sanitary
25 projects · most recent 09/14/2026
General Wiring Lighting
FiledStatusContractorScope
09/14/2026Permit IssuedTUXEDO ELEC'L CONTR'G INC—
09/14/2026Permit IssuedTUXEDO ELEC'L CONTR'G INC—
09/14/2026Permit IssuedTUXEDO ELEC'L CONTR'G INC—
09/14/2026Permit IssuedTUXEDO ELEC'L CONTR'G INC—
04/02/2026CompleteECO ELECTRICAL SERVCS LLCGeneral Wiring
04/02/2026Permit IssuedECO ELECTRICAL SERVCS LLCGeneral Wiring
02/09/2026CompleteECO ELECTRICAL SERVCS LLCGeneral Wiring
11/24/2025Permit IssuedALLBRIGHT ELECTRIC, INC—
03/24/2025CompleteTUXEDO ELEC'L CONTR'G INC—
01/06/2025CompleteB & G ELECL CONTR OF NY I—
10/30/2024CompleteB & G ELECL CONTR OF NY IGeneral Wiring
10/18/2024Permit IssuedB & G ELECL CONTR OF NY I2 meters, 2 new_meters
10/01/2024CompleteS. J. ELECTRIC INC.General Wiring
08/06/2024Permit IssuedPRIMIANO CORP DBA3 meters
06/22/2023CompleteTEAM ELECTRIC, INCGeneral Wiring
4 projects · most recent 06/24/2026
Steel
FiledStatusContractorScope
06/24/2026Permit IssuedSERVICE SIGN ERECTORS CO2 scope_items
06/09/2026Signed-offPREMIER FIRE SPRNKLR COSteel
06/18/2024Signed-offTURNER CONSTRUCTION COMPASteel
02/13/2020——Steel
2 projects · most recent 05/20/2025
Sidewalk Shed Scaffold
FiledStatusContractorScope
05/20/2025Signed-offKINGS GROUP NY CORPSidewalk Shed
04/04/2024Signed-offKINGS GROUP NY CORPScaffold, Sidewalk Shed
2 projects · most recent 07/25/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
07/25/2025Signed-offTRIBUTE RESTORATION INCSuspended Scaffold (SC)
06/19/2025Permit IssuedDOMUM, LLCSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 29
DateTypeResultReport
04/27/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/22/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/21/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/20/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
01/20/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
01/14/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/12/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/12/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/19/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/16/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/16/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/23/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/01/2025Pass-Final SP - Up to 3 Requested FloorsPassView ↗
01/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/18/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/21/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/18/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/10/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/13/2024Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
02/21/2024Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
02/21/2024Certified Sprinkler (PL) - SP - RoughingCertifiedView ↗
02/19/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/22/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/30/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/24/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
Latest 25 of 29.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
07/27/2026Public Assembly Emergency LightingAILANTO DANIEL MINAWIprogress
07/27/2026Public Assembly Emergency LightingAILANTO DANIEL MINAWIprogress
07/01/2026FinalAILANTO DANIEL MINAWIprogress
07/01/2026Air barrier continuity plan testingAILANTO DANIEL MINAWIenergy_progress
07/01/2026Insulation placement and R valuesAILANTO DANIEL MINAWIenergy_progress
07/01/2026Exterior lighting powerAILANTO DANIEL MINAWIenergy_progress
07/01/2026Lighting controlsAILANTO DANIEL MINAWIenergy_progress
07/01/2026Air barrier - visual inspectionAILANTO DANIEL MINAWIenergy_progress
07/01/2026Fire-Resistant Penetrations and JointsAILANTO DANIEL MINAWIspecial
07/01/2026Sprayed fire-resistant materialsAILANTO DANIEL MINAWIspecial
06/24/2026Post-installed AnchorsBrian Clarkespecial
06/24/2026Finaltarek zeidprogress
06/24/2026Structural Stability – Alterations of existing buildingsBrian Clarkespecial
06/13/2026Sprayed fire-resistant materialsAILANTO DANIEL MINAWIspecial
06/13/2026Alternative Materials - OTCR Buildings Bulletin NumberAILANTO DANIEL MINAWIspecial
06/13/2026Exterior Insulation and Finish Systems (EIFS)AILANTO DANIEL MINAWIspecial
06/13/2026Fire-Resistance Rated ConstructionAILANTO DANIEL MINAWIprogress
06/13/2026Energy Code Compliance InspectionsAILANTO DANIEL MINAWIprogress
06/13/2026FinalAILANTO DANIEL MINAWIprogress
06/13/2026Insulation placement and R valuesAILANTO DANIEL MINAWIenergy_progress
06/13/2026Lighting in dwelling unitsAILANTO DANIEL MINAWIenergy_progress
06/13/2026Lighting controlsAILANTO DANIEL MINAWIenergy_progress
06/13/2026Fenestration areasAILANTO DANIEL MINAWIenergy_progress
06/13/2026Exterior lighting powerAILANTO DANIEL MINAWIenergy_progress
06/13/2026Air barrier - visual inspectionAILANTO DANIEL MINAWIenergy_progress
Latest 25 of 150.
▾Documents — 2,487 on file (BIS + DOB NOW)
▸Plans & Drawings100
▸DOB NOWPlans/Sketch75
09/06/2026M01386388-I1Request digital key ↗
09/06/2026M00006434-I1Request digital key ↗
09/06/2026M00064890-I1Request digital key ↗
Showing 3 of 75 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly7
09/03/2026M00292449-I1Request digital key ↗
09/03/2026M00292402-I1Request digital key ↗
Showing 2 of 7 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems4
09/02/2026M00277477-P3Request digital key ↗
09/02/2026M00277477-I1Request digital key ↗
09/02/2026M00277477-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler3
09/05/2026M00274343-P2Request digital key ↗
Showing 1 of 3 on file for this type
▸DOB NOWPlans/Sketch - Antenna3
09/02/2026M00223996-P2Request digital key ↗
Showing 1 of 3 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Structural2
09/05/2026M00202319-I1Request digital key ↗
09/05/2026M00277916-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/05/2026M00311930-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sign1
09/05/2026M00117610-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
09/04/2026M00458818-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/05/2026M00274507-I1Request digital key ↗
▸Applications & Permits457
▸BISPLAN / WORK APPROVAL APPLICATION266
03/05/2026123039504Open ↗
03/05/2026123039504Open ↗
03/03/2026123039504Open ↗
Showing 3 of 266 on file for this type
▸BISWORK PERMIT APPLICATION146
02/26/2026123039504Open ↗
11/28/2025123039504Open ↗
10/03/2023123077071Open ↗
Showing 3 of 146 on file for this type
▸BISPLACE OF ASSEMBLY41
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 41 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
10/25/2021122519042Open ↗
Showing 1 of 2 on file for this type
▸Zoning, Tax Lot & Property Records2
▸BISVERIFY TAX LOT2
01/28/2026122808621Open ↗
07/31/2025122519042Open ↗
▸Seals & Professional Certifications629
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION242
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 242 on file for this type
▸DOB NOWProgress Inspector Seal & Signature112
09/29/2026M00277477-P2Open ↗
09/29/2026M00277477-P2Open ↗
09/29/2026M00277477-P2Open ↗
Showing 3 of 112 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature99
09/06/2026M01386388-I1Open ↗
09/05/2026M00122183-I1Open ↗
09/05/2026M00100710-I1Open ↗
Showing 3 of 99 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature73
09/29/2026M00277477-P2Open ↗
09/29/2026M00277477-P2Open ↗
09/29/2026M00277477-P2Open ↗
Showing 3 of 73 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT47
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 47 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST40
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 40 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Trade Schedules & Equipment121
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE54
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 54 on file for this type
▸BISSELF-CERT PLUMBING NOTICE22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA21
05/06/2024123074546Open ↗
Showing 1 of 21 on file for this type
▸BISSCHEDULE B - PLUMBING9
06/02/2022123333366Open ↗
Showing 1 of 9 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISEQUIPMENT USE PERMITS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWFDNY: Letter of No Objection4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Safety & Tenant Protection33
▸BISTenant Protection Plan and Notes20
08/04/2021123772462Open ↗
Showing 1 of 20 on file for this type
▸DOB NOWTenant Protection Plan13
09/05/2026M00274343-P1Open ↗
09/02/2026M00277477-P3Open ↗
09/02/2026M00277477-I1Open ↗
Showing 3 of 13 on file for this type
▸Environmental & Asbestos108
▸BISASBESTOS: CERTIFICATION (DEP ACP5)52
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 52 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report28
09/06/2026M01386388-I1Open ↗
09/05/2026M00274507-I1Open ↗
09/05/2026M00274343-P1Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form12
09/02/2026M00277477-I1Open ↗
08/28/2026M00976708-S2Open ↗
08/28/2026M00976708-S1Open ↗
Showing 3 of 12 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)9
11/07/2024123074546Open ↗
Showing 1 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance174
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS117
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 117 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS27
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 27 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY7
02/18/2026123039504Open ↗
02/18/2026123324928Open ↗
07/18/2025123077071Open ↗
Showing 3 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)5
10/28/2025123039504Open ↗
10/28/2025123324928Open ↗
10/20/2021140893790Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISINTERIOR LIGHTING POWER3
10/28/2025123039504Open ↗
10/28/2025123324928Open ↗
10/08/2021123772462Open ↗
▸BISEMERGENCY LIGHTING - PA3
05/30/2025123561065Open ↗
05/30/2025123478156Open ↗
05/30/2025122565385Open ↗
▸BISLIGHTING CONTROLS3
10/28/2025123039504Open ↗
10/28/2025123324928Open ↗
10/08/2021123772462Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS2
10/28/2025123039504Open ↗
10/08/2021123772462Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification1
08/28/2026M00976708-S3Open ↗
▸Inspections & Test Reports45
▸BISTECHNICAL REPORT: RESPONSIBILITY28
02/18/2026123039504Open ↗
02/18/2026123324928Open ↗
07/23/2025123077071Open ↗
Showing 3 of 28 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)3
10/28/2025123324928Open ↗
07/29/2025122519042Open ↗
10/08/2021123772462Open ↗
▸BISMECHANICAL SYSTEMS3
10/28/2025123039504Open ↗
10/28/2025123324928Open ↗
07/31/2025122519042Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION2
10/28/2025123324928Open ↗
10/08/2021123772462Open ↗
▸BISSPRAYED FIRE-RESISTANT MATERIALS2
10/08/2021123772462Open ↗
Showing 1 of 2 on file for this type
▸Approvals, Objections & Sign-offs242
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter86
09/06/2026M01386388-I1Open ↗
09/05/2026M00277916-I1Open ↗
09/05/2026M00274507-I1Open ↗
Showing 3 of 86 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST72
02/18/2026123324928Open ↗
11/07/2024123074546Open ↗
05/02/2024122950262Open ↗
Showing 3 of 72 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE17
02/26/2026122808621Open ↗
02/25/2026122808621Open ↗
02/20/2026122808621Open ↗
Showing 3 of 17 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION17
02/10/2025123730588Open ↗
Showing 1 of 17 on file for this type
▸BISADMINISTRATIVE OBJECTIONS17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION10
05/01/2024122808621Open ↗
05/01/2024122519042Open ↗
02/14/2022122519042Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDEP Variance (V5) letter8
09/02/2026M00277477-I1Open ↗
Showing 1 of 8 on file for this type
▸BISSUPERSEDING LETTER7
10/03/2023123077071Open ↗
Showing 1 of 7 on file for this type
▸BISFINAL6
10/28/2025123039504Open ↗
10/28/2025123324928Open ↗
04/23/2024122950262Open ↗
Showing 3 of 6 on file for this type
▸BISFA LETTER OF DEFECT : FD-FALD2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Cost, Insurance & Ownership180
▸BISCOST AFFIDAVIT163
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 163 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW312
01/28/2026122519042Open ↗
01/28/2026122808621Open ↗
09/18/2025123039504Open ↗
Showing 3 of 12 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDEPT OF FINANCE VERIFICATION2
03/19/2021123772462Open ↗
Showing 1 of 2 on file for this type
▸Filing & Intake Forms264
▸BISEFILING COVER SHEET103
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 103 on file for this type
▸BISBOROUGH INTAKE FORM84
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 84 on file for this type
▸BISADDITIONAL INFORMATION70
02/26/2026122808621Open ↗
02/03/2026122519042Open ↗
12/24/2025123077071Open ↗
Showing 3 of 70 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸Other Documents85
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION61
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 61 on file for this type
▸DOB NOWManufacturer's Specifications5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWCalculations5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSupporting Document: Fee Deferment4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWAlternate Plan 14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSupporting Document: Fee Exempt3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWStructural Peer Review Report1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPro Cert Restriction Exception (LL158/17)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type