1922Year Built
4Stories
C1Building Class
R6Zoning
24,700 sfGross Floor Area
31Units
Rent Stabilized8 Active Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: NYC Pact Preservation Partners · 7,816 sf lot · 3.16 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipment
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofNYCHA Reid Park Rock facade and roof13p · 3 filings · 20 docs
Floor 4Cold water piping insulation71p · 3 filings · 20 docs
Floor 3Cold water piping insulation71p · 3 filings · 20 docs
Floor 2Cold water piping insulation71p · 3 filings · 20 docs
Floor 1Unit 178p · 3 filings · 20 docs
Cellar69p · 1 filing · 14 docs
Site & exteriorFire escape landing repairs19p · 5 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New York City Housing Authority707/09/2026
NYC Pact Preservation Partners511/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Asr Engineering107/13/2026
Socotec209/10/2025
Ashraf208/26/2025
Dagher Engineering312/23/2024
SLM Architecture111/13/2024
Madsen Consulting Engineering109/26/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Metropolis Group1003/21/2026
Rybak Development203/21/2026
Socotec103/21/2026
KD Designs103/21/2026
Rigging Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FSC D&CGeneral Contractor404/09/2026
LS GeneralGeneral Contractor407/09/2026
LS GeneralScaffold204/09/2026
RJ BrunoPlumbing203/21/2026
A & E PlumbingPlumbing107/08/2026
High Point ConstructionGeneral Contractor108/05/2026
Arsenal ScaffoldScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Metric Consulting1803807/13/2026
PCS Engineering3745110/21/2025
Building Lifecycle
11/17/2026
Permit renewed — Suspended Scaffold
Renewed without changes
B01292984-I1-SC
11/10/2026
Signed off — Alteration
INSTALLATION OF NEW RAILING OVER EXISTING PARAPET WALLS AT ROOF AREA. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B01365794-I1
11/10/2026
Boiler inspection report filed
Initial · no defects · Accepted
10/19/2026
Closed: Failure to file 2024 external low pressure inspection
DOB violation · closed on the city's record
10/13/2026
Closed: Failure to file 2024 external low pressure inspection
DOB violation · closed on the city's record
164 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedLS General11/17/2026
DOB NOWGeneral ConstructionSigned-offHigh Point Construction08/04/2026
DOB NOWStructuralSigned-offLS General07/07/2026
DOB NOWGeneral ConstructionSigned-offLS General04/09/2026
DOB NOWGeneral ConstructionSigned-offLS General02/10/2026
DOB NOWSupported ScaffoldPermit IssuedLS General02/10/2026
DOB NOWSuspended ScaffoldPermit IssuedLuan Sela02/10/2026
DOB NOWGeneral ConstructionSigned-offFSC D&C11/21/2025
DOB NOWSuspended ScaffoldPermit IssuedLuan Sela11/03/2025
DOB NOWGeneral ConstructionSigned-offLS General09/24/2025
DOB NOWSupported ScaffoldPermit IssuedLS General08/26/2025
DOB NOWSidewalk ShedSigned-offArsenal Scaffold04/01/2025
DOB NOWPlumbingSigned-offA & E Plumbing01/03/2025
DOB NOWMechanical SystemsSigned-offPyramid Etc Companies01/02/2025
DOB NOWGeneral ConstructionSigned-offFSC D&C11/25/2024
BISBLISSUEDRJ Bruno03/27/2019
BISPLISSUEDRJ Bruno03/27/2019
1 project · most recent 08/15/2024
Water/Sanitary
FiledStatusContractorScope
08/15/2024——Water/Sanitary
1 project · most recent 02/26/2018
General Wiring
FiledStatusContractorScope
02/26/2018CompleteA Tech Electric EnterprisesGeneral Wiring
1 project · most recent 09/26/2023
Steel
FiledStatusContractorScope
09/26/2023Signed-offLS GeneralSteel
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/18/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
07/13/2026FinalAKM RAHMANprogress
03/12/2026Tenant Protection Plan ComplianceAKM RAHMANspecial
10/21/2025Post-installed AnchorsMichael Walshspecial
10/21/2025Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
08/29/2025MasonrySAMI HAJJAR P.Especial
08/29/2025FinalSAMI HAJJAR P.Eprogress
08/29/2025Tenant Protection Plan Compliance—special
08/29/2025Insulation placement and R valuesSAMI HAJJAR P.Eenergy_progress
11/12/2024Lighting controlsSAMI HAJJAR P.Eenergy_progress
11/12/2024Lighting in dwelling unitsSAMI HAJJAR P.Eenergy_progress
11/12/2024VestibulesSAMI HAJJAR P.Eenergy_progress
11/12/2024Interior lighting powerSAMI HAJJAR P.Eenergy_progress
11/12/2024Fire-Resistant Penetrations and JointsSAMI HAJJAR P.Especial
11/12/2024Energy Code Compliance InspectionsSAMI HAJJAR P.Eprogress
11/12/2024Fire-Resistance Rated ConstructionSAMI HAJJAR P.Eprogress
11/12/2024Air barrier - visual inspectionSAMI HAJJAR P.Eenergy_progress
11/12/2024Fenestration and door U-factor and product ratingsSAMI HAJJAR P.Eenergy_progress
11/12/2024Exterior lighting powerSAMI HAJJAR P.Eenergy_progress
11/12/2024Fenestration areasSAMI HAJJAR P.Eenergy_progress
06/19/2024FinalSAMI HAJJAR P.Eprogress
12/18/2023Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
12/18/2023HVAC-R and service water piping design and insulationSAMI HAJJAR P.Eenergy_progress
12/18/2023Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
08/28/2023Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
08/03/2023Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
Latest 25 of 29.
90 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account