Roof2p · 2 filings · 15 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Mechanical work as shown on plans for existing 1st floor restaurant and lounge.
On file for this project
13 documents · 1 drawing sheet
This application is filed to replace roof @ 2nd Floor West Courtyard. No change in Use, Egress, or Occupancy under this application.
On file for this project
4 documents · 1 drawing sheet
BulkheadUnder Construction1p · 1 filing · 3 docs
Equipment
Installation of suspended scaffold for facade work or inspection.
On file for this project
3 documents · 1 drawing sheet
Floor 403 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Structural
Modifications to existing Plumbing fixtures as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
10 documents
Modifications to existing HVAC System as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
6 documents
INTERIOR RENOVATION OF AN EXISTING APARTMENT, INCLUDING MINOR NON-STRUCTURAL PARTITION REMOVAL AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
Floor 393 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Structural
Modifications to existing Plumbing fixtures as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
10 documents
Modifications to existing HVAC System as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
6 documents
INTERIOR RENOVATION OF AN EXISTING APARTMENT, INCLUDING MINOR NON-STRUCTURAL PARTITION REMOVAL AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
Floor 38Under Construction4p · 2 filings · 7 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Structural
Modifications to existing Plumbing and Sprinkler System as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
4 documents · 1 drawing sheet
Relocation and redistribution of existing HVAC and bathroom exhaust systems as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
3 documents · 4 drawing sheets
Floor 37Under Construction1p · 5 filings · 10 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
Modifications to existing Plumbing and Sprinkler System as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
4 documents
Relocation and redistribution of existing HVAC and bathroom exhaust systems as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
3 documents
General alterations to guestroom suite and corridor on portion of 37th floor (called 38th) as per plans filed herewith. No change in use, egress, or occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 36
Floor 35Under Construction2 filings · 3 docs
ArchitectureEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Structural
INTERIOR ALTERATIONS TO APT. 3503/05. NO CHANGE TO USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION. ALL WORK SHOULD COMPLY WITH ADEQUATE PROTECTIONS IN ACCORDANCE WITH THE ALTERATION AGREEMENT AND NYC LOCAL LAW 106/19.
On file for this project
2 documents
Project M01326882Permit Issued · 02/18/2026
Combination of apartment 3503 and 3505. Installation of partitions with wall and floor finishes. No change of use, egress or occupancy under this application. Work will comply with TPPN/ 3/97
On file for this project
1 document
Floor 342 filings · 7 docs
ArchitectureEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Structural
This alteration is being filed herewith for the renovation in apt 2303. Work to include removal and installation of partitions, fin floor, millwork, fixtures. No change in use, egress or occupancy.
On file for this project
4 documents
This application is being filed herewith for plumbing work related to GC #M00749145. No change in use, egress or occupancy
On file for this project
4 documents
Floor 33
Floor 32
Floor 31Under Construction2p · 6 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
Sprinkler work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
4 documents · 1 drawing sheet
Mechanical work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
7 documents · 1 drawing sheet
Renovation of existing kitchen and bathroom fixtures in apt#3101 and 3118. No change of use, egress, or occupancy under this application. Combination of apartment work to comply with TPPN 3/97
On file for this project
9 documents
Latest 3 of 6 filings on this floor.
Floor 302 filings · 7 docs
ArchitectureEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Structural
Renovation of existing kitchen and bathroom fixtures in apt#3007. No change of use, egress or occupancy under this application.
On file for this project
4 documents
Interior Alterations to existing apartment#3007. No change of use, egress or occupancy under this application.
On file for this project
3 documents
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25Under Construction7p · 6 filings · 11 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
Sprinkler work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
4 documents · 1 drawing sheet
Mechanical work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
7 documents · 1 drawing sheet
Plumbing work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
4 documents
Latest 3 of 6 filings on this floor.
Floor 24
Floor 232p · 5 filings · 11 docs
ArchitectureEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Structural
DEMOLITION OF EXISTING HOT WATER HEATERS, HOT WATER RETURN PUMPS, AND ASSOCIATED COMPONENTS. INSTALLATION OF NEW HOT WATER HEATERS, RETURN PUMPS, SIDE STREAM FILTER PUMP, MIXING VALUES AND ASSOCIATED COMPONENTS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
11 documents · 1 drawing sheet
DEMOLITION OF EXISTING HOT WATER HEATERS, HOT WATER RETURN PUMPS, AND ASSOCIATED COMPONENTS. INSTALLATION OF NEW HOT WATER HEATERS, RETURN PUMPS, SIDE STREAM FILTER PUMP, MIXING VALUES AND ASSOCIATED COMPONENTS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
This alteration is being filed herewith for the renovation in apt 2303. Work to include removal and installation of partitions, fin floor, millwork, fixtures. No change in use, egress or occupancy.
On file for this project
8 documents
Latest 3 of 5 filings on this floor.
Floor 22
Floor 21
Floor 201p · 1 filing · 8 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Structural
INSTALLATION OF INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH FOR UNIT 1903 & 2003. NO CHANGE IN USE, EGRESS OR OCCUPANCY. M00356501, M00356557, M01225418.
On file for this project
8 documents · 1 drawing sheet
Floor 195p · 2 filings · 8 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Structural · Supported Scaffold
INSTALLATION OF INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH FOR UNIT 1903 & 2003. NO CHANGE IN USE, EGRESS OR OCCUPANCY. M00356501, M00356557, M01225418.
On file for this project
8 documents · 4 drawing sheets
Filing this application to reinforce the existing steel framing of 19th floor framing, which will be installed in the ceiling of the 18th at unit/room number 1837. no change in Use, egress, occupancy under this application
On file for this project
8 documents · 1 drawing sheet
Floor 182 filings · 8 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Structural · Supported Scaffold
INSTALLATION OF INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILED HEREWITH FOR UNIT 1903 & 2003. NO CHANGE IN USE, EGRESS OR OCCUPANCY. M00356501, M00356557, M01225418.
On file for this project
8 documents
Filing this application to reinforce the existing steel framing of 19th floor framing, which will be installed in the ceiling of the 18th at unit/room number 1837. no change in Use, egress, occupancy under this application
On file for this project
8 documents
Floor 172p · 3 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
Removal of 7 sprinkler heads and installation of 4 new sprinkler heads with related modifications to piping.
On file for this project
19 documents
ALT-2 FILING. PLUMBING WORK PER APPROVED PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 2 drawing sheets
Minor plumbing modifications, as per plans submitted. No change in use, egress or occupancy.
On file for this project
3 documents
Floor 162 filings · 10 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
RENOVATIONS TO APT 1601 AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
10 documents
PLUMBING WORK AND SPRINKLER MODIFICATIONS OF APARTMENT #1608 ON THE 16TH FLOOR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
16 documents
Floor 15Under Construction4p · 4 filings · 11 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
Sprinkler work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
4 documents · 1 drawing sheet
Mechanical work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
7 documents · 2 drawing sheets
Plumbing work as shown on plans for three specialty Hotel suites on 15th, 25th and 31st construction floors (Marketing floors 16th, 26th and 32nd floor)
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 72 filings · 2 docs
ArchitectureEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Structural · Supported Scaffold
FILING APPLICATION FOR INTERIOR PLUMBING WORK. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
On file for this project
3 documents
INSTALLATION OF NON-LOAD BEARING PARTITIONS, MILLWORK AND FINISHES IN APARTMENT 760. ALL; WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
On file for this project
7 documents
Floor 6
Floor 5
Floor 41 filing · 2 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Structural · Supported Scaffold
Renovation of Condo Unit # 401 per plans. No change to use, egress or occupancy.
On file for this project
3 documents
Floor 3
Floor 23p · 3 filings · 15 docs
ArchitectureElectricalEquipmentGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Supported Scaffold
Plumbing work as shown on plans associated with existing 1st floor restaurant and lounge.
On file for this project
16 documents · 2 drawing sheets
This application is filed to replace roof @ 2nd Floor West Courtyard. No change in Use, Egress, or Occupancy under this application.
On file for this project
4 documents
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
On file for this project
8 documents · 1 drawing sheet
Floor 146p · 10 filings · 20 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
Modifications to existing sprinkler system for existing lobby.
On file for this project
3 documents · 1 drawing sheet
Modifications to existing sprinkler system as shown on plans for existing 1st floor restaurant and lounge.
On file for this project
12 documents · 2 drawing sheets
Plumbing work as shown on plans associated with existing 1st floor restaurant and lounge.
On file for this project
16 documents · 13 drawing sheets
Latest 3 of 10 filings on this floor.
Mezzanine2 filings · 20 docs
MechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing
Plumbing work as shown on plans associated with existing 1st floor restaurant and lounge.
On file for this project
16 documents
Mechanical work as shown on plans for existing 1st floor restaurant and lounge.
On file for this project
13 documents
Cellar12p · 5 filings · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
DEMOLITION OF EXISTING HOT WATER HEATERS, HOT WATER RETURN PUMPS, AND ASSOCIATED COMPONENTS. INSTALLATION OF NEW HOT WATER HEATERS, RETURN PUMPS, SIDE STREAM FILTER PUMP, MIXING VALUES AND ASSOCIATED COMPONENTS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
11 documents · 1 drawing sheet
Plumbing work as shown on plans associated with existing 1st floor restaurant and lounge.
On file for this project
16 documents · 8 drawing sheets
DEMOLITION OF EXISTING HOT WATER HEATERS, HOT WATER RETURN PUMPS, AND ASSOCIATED COMPONENTS. INSTALLATION OF NEW HOT WATER HEATERS, RETURN PUMPS, SIDE STREAM FILTER PUMP, MIXING VALUES AND ASSOCIATED COMPONENTS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Site & exterior6 filings · 17 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · General Construction · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
ERECT 3 ACCESSORY AWNINGS AS PER PLANS FILED HEREWITH.
On file for this project
3 documents · 4 drawing sheets
INSTALLATION OF SIDEWALK SHED IN ACCORDANCE WITH NYC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 documents · 12 drawing sheets
INSTALLATION OF PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
2 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Filed — no permit issued7 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructural
Sprinkler work on part of 9th floor.
On file for this project
3 documents · 7 drawing sheets
Installation of mechanical ductwork
On file for this project
18 documents · 12 drawing sheets
FILING FOR STRUCTURAL FRAMING/WORK IN RELATION TO THE RENOVATION OF EXISTING CONDO UNIT 1903
On file for this project
3 documents · 4 drawing sheets
Latest 3 of 7 filings on this floor.