← Back
Condo, residential tower (mixed-use, multi-family elevator) [derived]
Rockaway Village Condominium
17-20 VILLAGE LANE · Far Rockaway-Bayswater · BIN 4621091
💬 Discuss this project
2020Year Built
10Stories
RMBuilding Class
R7-1Zoning
1,194,864 sfGross Floor Area
1,866Units
Rent Stabilized57 Open Violations 55 unresolved · 2 paperwork only ▸
Condo, residential tower (mixed-use, multi-family elevator) [derived] · Owner of record: MOTT CENTER, LLC · 327,013 sf lot · 3.65 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Permit Issued — active, not yet Signed-off
Floor 2Under Construction44p · 2 filings · 20 docs
Floor 1Under Construction40p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
UNITED INDUSTRIES CONST507/08/2026
PHIPPS HOUSES SERVICES3204/09/2026
COSAN CONSTRUCTION404/09/2026
CAIN MANAGEMENT704/09/2026
LETTIRE CONSTRUCTION903/22/2026
R.E. STRUCTURE INC103/22/2026
RSC GROUP203/21/2026
FRED STARK ESTATE803/21/2026
SHOPCO CONSULTING503/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MUNICIPAL EXPEDITING803/21/2026
MUNICIPAL BUILDING CONSULTANTS103/21/2026
A D BUILDING SOLUTIONS403/21/2026
JM ZONING, LLC.403/21/2026
INDESIGN STUDIO403/21/2026
EUROCELT EXPEDITING, INC203/21/2026
PATUXENT ENGINEERING203/21/2026
DOMANI CONSULTING103/21/2026
KD DESIGNS103/21/2026
SYNERGY BUILDING CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GILBANE BUILDING COMPANYGeneral Contractor609/09/2026
DHS FRACO LLCGeneral Contractor407/08/2026
ALLIANCE PLUMBING CORPPlumbing307/08/2026
NEPTUNE SIGNS AWNINGSScaffold207/08/2026
COSAN CONSTRUCTION CORPGeneral Contractor204/09/2026
UNITED INDUSTRIES & CONSTGeneral Contractor204/09/2026
TRI STATE PLBG & HTG INCPlumbing207/08/2026
ABCO-PEERLESS SPRKLR CORPFire Protection207/02/2026
LETTIRE CONSTRUCTION CORPGeneral Contractor104/09/2026
MICHELLE KUO CORPGeneral Contractor104/09/2026
TOP DOG PLBG & HTG CORPPlumbing107/08/2026
FULL CAPACITY FIRE CORPFire Protection107/08/2026
DIESEL CONTRACTING OF N.YGeneral Contractor104/09/2026
FHA CONTRACTING CORPGeneral Contractor104/09/2026
MEGA PLBG CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUREAU VERITAS NA69021008/25/2026
SOLANKI ENGINEERING, P.C.8451105/23/2024
UG ENGINEERING SERVICES P9041105/23/2024
CITISCAPE CONSULTING LTD762104/26/2024
W CHAN ENGINEERING PC2881106/27/2023
CHERICO KING ARCHITECT PC5674206/27/2023
DOMANI INSPECTION SERVICE843208/18/2021
Building Lifecycle
All (177)Filed (39)Permit Issued (30)Signed Off (14)Violation (23)Inspection (25)Objection (16)Special Inspection (30)
09/08/2026
Permit issued — General Construction
Q01215133-I1-GC
08/26/2026
Special inspection requirement — Sprinkler Systems
IBRAHIM MOURAD
08/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
08/25/2026
Filed — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE ALTERATIONS FOR NEW MEDICAL OFFICES AT THE 2ND FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01215133-P9
08/20/2026
Signed off — Alteration
Q00056158-I1
08/16/2026
Filed — Alteration
INSTALLATION OF AN ILLUMINATED BUSINESS ACCESSORY SIGN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01350388-I1
08/12/2026
Special inspection requirement — Sprinkler Systems
IBRAHIM MOURAD
08/12/2026
Special inspection requirement — Tenant Protection Plan Compliance
07/15/2026
Signed off — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE ALTERATIONS FOR NEW MEDICAL OFFICES AT THE 2ND FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01215133-S3
07/08/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
07/06/2026
Permit issued — Structural
Q01215133-S3-ST
06/30/2026
Permit issued — Sprinklers
Q01215133-S2-EW-SP
06/26/2026
Permit issued — Mechanical Systems
Q01215133-S1-MS
06/23/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
06/18/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/18/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/18/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/18/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/18/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/18/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/11/2026
Filed — Alteration
Q01349640-P1
06/11/2026
Filed — Alteration
Q01349798-P1
06/11/2026
Filed — Alteration
Q01349640-P2
06/11/2026
Filed — Alteration
Q01349770-P1
06/11/2026
Filed — Alteration
Q01349640-P3
06/11/2026
Filed — Alteration
Q01349770-P2
06/11/2026
Filed — Alteration
Q01349798-P2
06/08/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/08/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/08/2026
Special inspection requirement — Final
IBRAHIM MOURAD
06/04/2026
Filed — Alteration
Q01349640-S4
06/04/2026
Filed — Alteration
Q01349798-S2
06/03/2026
Filed — Alteration
Q01349640-S3
06/03/2026
Filed — Alteration
Q01349770-S4
06/03/2026
Filed — Alteration
Q01349770-I1
06/03/2026
Filed — Alteration
Q01349640-I1
06/03/2026
Filed — Alteration
Q01349798-I1
05/29/2026
Special inspection requirement — Tenant Protection Plan Compliance
IBRAHIM MOURAD
05/29/2026
Special inspection requirement — Structural Steel - Welding
IBRAHIM MOURAD
05/29/2026
Special inspection requirement — Structural Steel - High Strength Bolting
IBRAHIM MOURAD
05/29/2026
Special inspection requirement — Concrete - Cast-In-Place
IBRAHIM MOURAD
05/29/2026
Special inspection requirement — Structural Steel - Details
IBRAHIM MOURAD
05/29/2026
Special inspection requirement — Post-installed Anchors
IBRAHIM MOURAD
05/29/2026
Special inspection requirement — Final
IBRAHIM MOURAD
05/28/2026
Filed — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE ALTERATIONS FOR NEW MEDICAL OFFICES AT THE 2ND FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01215133-P8
05/25/2026
Special inspection requirement — Structural Steel - Details
IBRAHIM MOURAD
05/25/2026
Special inspection requirement — Structural Steel - High Strength Bolting
IBRAHIM MOURAD
05/25/2026
Special inspection requirement — Concrete - Cast-In-Place
IBRAHIM MOURAD
05/25/2026
Special inspection requirement — Post-installed Anchors
IBRAHIM MOURAD
05/25/2026
Special inspection requirement — Structural Steel - Welding
IBRAHIM MOURAD
05/25/2026
Special inspection requirement — Final
IBRAHIM MOURAD
05/25/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/12/2026
Filed — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE ALTERATIONS FOR NEW MEDICAL OFFICES AT THE 2ND FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01215133-P7
05/12/2026
Special inspection requirement — Shutoff dampers
IBRAHIM MOURAD
05/12/2026
Special inspection requirement — Maintenance information
IBRAHIM MOURAD
05/12/2026
Special inspection requirement — Final
IBRAHIM MOURAD
05/03/2026
Filed — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE ALTERATIONS FOR NEW MEDICAL OFFICES AT THE 2ND FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01215133-P6
04/20/2026
Filed — Alteration
PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE ALTERATIONS FOR NEW MEDICAL OFFICES AT THE 2ND FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01215133-P1
04/17/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
04/15/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
Latest 60 of 177 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offGILBANE BUILDING COMPANY09/08/2026
DOB NOWStructuralSigned-offGILBANE BUILDING COMPANY07/06/2026
DOB NOWSprinklersPermit IssuedABCO-PEERLESS SPRKLR CORP06/30/2026
DOB NOWMechanical SystemsSigned-offGILBANE BUILDING COMPANY06/26/2026
DOB NOWSprinklersPermit IssuedCARDOZA PLUMBING WMBE04/02/2026
DOB NOWPlumbingPermit IssuedCARDOZA PLUMBING WMBE11/18/2025
DOB NOWMechanical SystemsSigned-offGILBANE BUILDING COMPANY09/17/2025
DOB NOWSprinklersPermit IssuedCARDOZA PLUMBING WMBE09/05/2025
DOB NOWGeneral ConstructionSigned-offGILBANE BUILDING COMPANY08/14/2025
DOB NOWStructuralSigned-offGILBANE BUILDING COMPANY08/13/2025
DOB NOWPlumbingPermit IssuedABCO-PEERLESS SPRKLR CORP07/30/2025
DOB NOWMechanical SystemsSigned-offFHA CONTRACTING CORP12/09/2024
DOB NOWSprinklersSigned-offREAL PLUMBING CORP05/02/2024
DOB NOWGeneral ConstructionSigned-offCENTRAL CONSTRUCTION MAN*04/10/2024
DOB NOWPlumbingSigned-offDW PLUMBING INC10/24/2023
DOB NOWSignSigned-offDESTHERS, JOSEPH09/21/2023
DOB NOWSignSigned-offDESTHERS, JOSEPH09/20/2023
DOB NOWSprinklersSigned-offFULL CAPACITY FIRE CORP08/07/2023
DOB NOWPlumbingSigned-offDW PLUMBING INC08/07/2023
DOB NOWGeneral ConstructionPermit Issued18-15 REALTY LLC07/05/2023
DOB NOWCurb CutSigned-offLETTIRE CONSTRUCTION CORP02/20/2022
DOB NOWSupported ScaffoldSigned-offCOSAN CONSTRUCTION11/23/2021
DOB NOWBoiler EquipmentSigned-offTOP DOG PLBG & HTG CORP08/05/2021
DOB NOWSupported ScaffoldSigned-offCOSAN CONSTRUCTION06/03/2021
DOB NOWSidewalk ShedSigned-offDHS FRACO11/06/2020
DOB NOWSupported ScaffoldSigned-offDHS FRACO08/07/2020
DOB NOWSidewalk ShedSigned-offDHS FRACO08/19/2019
DOB NOWConstruction FenceSigned-offUNITED INDUSTRIES & CONST01/28/2019
DOB NOWSidewalk ShedSigned-offDHS FRACO10/29/2018
DOB NOWConstruction FenceSigned-offUNITED INDUSTRIES & CONST08/08/2018
BIS—ISSUEDLETTIRE CONSTRUCTION CORP11/15/2022
BISSDISSUEDUPRIGHT FIRE PROTCTN LLC11/07/2022
BISSPISSUEDUPRIGHT FIRE PROTCTN LLC10/19/2022
BISOTISSUEDLETTIRE CONSTRUCTION CORP08/17/2022
BISOTISSUEDBRIGHT POWER INC06/30/2022
BIS—ISSUEDLETTIRE CONSTRUCTION CORP03/29/2022
BIS—ISSUEDLETTIRE CONSTRUCTION CORP11/18/2021
BIS—ISSUEDLETTIRE CONSTRUCTION CORP11/05/2021
BIS—ISSUEDLETTIRE CONSTRUCTION CORP11/05/2021
BIS—ISSUEDLETTIRE CONSTRUCTION CORP11/05/2021
+ 40 more permits on file
2 projects · most recent 08/25/2026
Heating and Air Conditioning Systems Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/25/2026Signed-offGILBANE BUILDING COMPANYAir Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems
Cooling
Mitsubishi Electric PLA-AE42NL 42,000 BTU · Fan Coil Indoor ×2
PUY-AH30NL 30,000 BTU · Condensing Unit ×2
PUY-AK42NL 42,000 BTU · Condensing Unit ×2
PKA-AK18NL 18,000 BTU · Vrf Indoor ×1
PKA-AK30NL 30,000 BTU · Vrf Indoor ×1
PUY-AK18NL 18,000 BTU · Condensing Unit ×1
Heat / Cool
Mitsubishi Electric PEFY-EP36NMHU-E2 36,000 BTU · Vrf Indoor ×9
PEFY-EP24NMHU-E2 24,000 BTU · Vrf Indoor ×4
PEFY-EP48NMHU-E2 48,000 BTU · Vrf Indoor ×4
PEFY-EP15NMHU-E2 15,000 BTU · Vrf Indoor ×2
PEFY-EP18NMHU-E2 18,000 BTU · Vrf Indoor ×2
PEFY-EP30NMHU-E2 30,000 BTU · Vrf Indoor ×2
PEFY-EP96NMHSU-E 96,000 BTU · Vrf Indoor ×2
PURY-EP144TNU-A1 144,000 BTU · Vrf Outdoor ×2
TUHYE0963AN41AN <H> 96,000 BTU · Vrf Outdoor ×2
TUHYE1683AN41AN <H> 168,000 BTU · Vrf Outdoor ×2
PEAD-AA24NL 21,200 BTU · Vrf Indoor ×1
PEFY-EP12NMHU-E2 12,000 BTU · Vrf Indoor ×1
Ventilation
__Junk__ EXHAUST & RETURN DUCT & FAN 1 BTU · Exhaust Fan ×1
06/27/2023Permit IssuedMICHELLE KUO CORPHeating and Air Conditioning Systems
Heat / Cool
Sigma SDSH-C.2-0482C1SSSAGA1SA00; SDSH-C.2-0482C1SSSAGA1SA00; SDSH-C.2-0482C1SSSAGA1SA00 48,900 BTU · Wshp ×3
1 project · most recent 08/25/2026
Sprinkler System
FiledStatusContractorScope
08/25/2026Permit IssuedABCO-PEERLESS SPRKLR CORPSprinkler System
1 project · most recent 08/25/2026
Water/Sanitary
FiledStatusContractorScope
08/25/2026Permit IssuedCARDOZA PLUMBING WMBEWater/Sanitary
25 projects · most recent 08/03/2026
General Wiring Lighting
FiledStatusContractorScope
08/03/2026Permit IssuedWCK ELECTRIC CORP.General Wiring
03/14/2026CompleteJONG HYUN KIM—
09/02/2025Permit IssuedARK SYSTEMS ELEC. CORPGeneral Wiring, Lighting
10/29/2024Permit IssuedAL-LECTRIC ELECT'L CONTRG1 meters, 1 new_meters
04/12/2024CompleteAL-LECTRIC ELECT'L CONTRGGeneral Wiring
04/05/2024CompleteCMY ELECTRICAL CORPGeneral Wiring
09/27/2023CompleteAL-LECTRIC ELECT'L CONTRGGeneral Wiring
07/27/2023CompleteJEM ELEC'L CONTR. CORPGeneral Wiring
07/07/2022CompleteDIFALZO ELECTRIC NY, INCGeneral Wiring
07/07/2022CompleteDIFALZO ELECTRIC NY, INCGeneral Wiring
07/05/2022CompleteDIFALZO ELECTRIC NY, INCGeneral Wiring
07/05/2022CompleteDIFALZO ELECTRIC NY, INCGeneral Wiring
07/01/2022CompleteSIGMA ELECTRIC INC.General Wiring
06/08/2022CompleteSIGMA ELECTRIC INC.General Wiring
05/13/2022CompleteSIGMA ELECTRIC INC.—
2 projects · most recent 08/25/2026
Steel Concrete
FiledStatusContractorScope
08/25/2026Signed-offGILBANE BUILDING COMPANYSteel, Concrete
08/16/2026——1 scope_items
▾Field Inspections (DOB CAP) — 25
DateTypeResultReport
07/08/2026Pass-Final PL - UndergroundPassView ↗
06/23/2026Pass-Final PL - UndergroundPassView ↗
04/17/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/15/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/26/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/18/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/10/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
10/03/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/18/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/12/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/25/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/11/2024Pass-Final General Construction Non-Directive 14PassView ↗
11/20/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/19/2024Pass-Final General Construction Non-Directive 14PassView ↗
11/15/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/11/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/08/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/06/2024Fail-Final General Construction Non-Directive 14FailView ↗
05/07/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/24/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/19/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/26/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/08/2022Pass-Final Curb Cut Non-Directive 14PassView ↗
07/13/2022Fail-Final Curb Cut Non-Directive 14FailView ↗
09/24/2021Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 77
DateRequirementInspectorRole
08/26/2026Tenant Protection Plan Compliance—special
08/26/2026Sprinkler SystemsIBRAHIM MOURADspecial
08/12/2026Tenant Protection Plan Compliance—special
08/12/2026Sprinkler SystemsIBRAHIM MOURADspecial
06/18/2026FinalIBRAHIM MOURADprogress
06/18/2026FinalIBRAHIM MOURADprogress
06/18/2026FinalIBRAHIM MOURADprogress
06/18/2026FinalIBRAHIM MOURADprogress
06/18/2026FinalIBRAHIM MOURADprogress
06/18/2026FinalIBRAHIM MOURADprogress
06/08/2026FinalIBRAHIM MOURADprogress
06/08/2026FinalIBRAHIM MOURADprogress
06/08/2026FinalIBRAHIM MOURADprogress
05/29/2026Structural Steel - High Strength BoltingIBRAHIM MOURADspecial
05/29/2026Structural Steel - DetailsIBRAHIM MOURADspecial
05/29/2026Concrete - Cast-In-PlaceIBRAHIM MOURADspecial
05/29/2026FinalIBRAHIM MOURADprogress
05/29/2026Post-installed AnchorsIBRAHIM MOURADspecial
05/29/2026Structural Steel - WeldingIBRAHIM MOURADspecial
05/29/2026Tenant Protection Plan ComplianceIBRAHIM MOURADspecial
05/25/2026Structural Steel - High Strength BoltingIBRAHIM MOURADspecial
05/25/2026Post-installed AnchorsIBRAHIM MOURADspecial
05/25/2026Concrete - Cast-In-PlaceIBRAHIM MOURADspecial
05/25/2026Tenant Protection Plan Compliance—special
05/25/2026FinalIBRAHIM MOURADprogress
Latest 25 of 77.
▾Documents — 765 on file (BIS + DOB NOW)
▸Plans & Drawings39
▸DOB NOWPlans/Sketch37
08/28/2026Q00056158-I1Request digital key ↗
08/28/2026Q00090087-I1Request digital key ↗
08/27/2026Q00500272-P1Request digital key ↗
Showing 3 of 37 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/27/2026Q00354440-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/28/2026Q00381969-I1Request digital key ↗
▸Applications & Permits158
▸BISPLAN / WORK APPROVAL APPLICATION81
10/08/2025420663589Open ↗
08/18/2025420663589Open ↗
06/24/2025420468390Open ↗
Showing 3 of 81 on file for this type
▸BISWORK PERMIT APPLICATION71
12/20/2022440481195Open ↗
08/17/2022440695865Open ↗
05/06/2022420663589Open ↗
Showing 3 of 71 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation3
06/30/2023440489473Open ↗
09/28/2021440489473Open ↗
Showing 2 of 3 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISHPD: PERMIT NOTICE1
08/07/2025420663589Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED3
09/03/2024421134347Open ↗
Showing 1 of 3 on file for this type
▸BISZONING EXHIBIT I: CERTIFICATION2
09/03/2024421134347Open ↗
Showing 1 of 2 on file for this type
▸Seals & Professional Certifications141
▸DOB NOWDPL-1: Design Professional Seal & Signature39
08/28/2026Q00056158-I1Open ↗
08/28/2026Q00381969-I1Open ↗
08/27/2026Q00500272-I1Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
10/01/2026Q01349640-S4Open ↗
09/29/2026Q01215133-S3Open ↗
09/27/2026Q01051579-I1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/29/2026Q01215133-S3Open ↗
09/29/2026Q01215133-S3Open ↗
09/27/2026Q01051579-I1Open ↗
Showing 3 of 19 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION16
09/15/2022420663589Open ↗
09/15/2022420663589Open ↗
Showing 2 of 16 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT11
11/16/2021440695865Open ↗
Showing 1 of 11 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY10
11/16/2021440695865Open ↗
Showing 1 of 10 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION10
11/16/2021440695865Open ↗
Showing 1 of 10 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Trade Schedules & Equipment29
▸BISSCHEDULE B - PLUMBING19
09/16/2022440476520Open ↗
11/29/2021420663589Open ↗
09/20/2021420663589Open ↗
Showing 3 of 19 on file for this type
▸BISSTANDPIPE SYSTEMS2
11/02/2022440481195Open ↗
07/01/2022440476520Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT2
09/15/2022420663589Open ↗
Showing 1 of 2 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
11/22/2022421646927Open ↗
11/22/2022420663589Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection11
▸BISSTREET TREE CHECKLIST6
06/30/2023440489473Open ↗
Showing 1 of 6 on file for this type
▸BISSTREET TREES SITE PLAN3
10/11/2022420663589Open ↗
05/27/2022440489473Open ↗
Showing 2 of 3 on file for this type
▸BISSTREET TREE SIGNOFF2
11/15/2023420663589Open ↗
09/28/2023440489473Open ↗
▸Environmental & Asbestos64
▸DOB NOWOER: Notice to Proceed28
08/16/2026Q01215133-S1Open ↗
08/16/2026Q01215133-P6Open ↗
08/16/2026Q01215133-P8Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWOER: Notice of Satisfaction12
08/16/2026Q01215133-S3Open ↗
08/13/2026Q00381969-I1Open ↗
08/13/2026Q00500272-I1Open ↗
Showing 3 of 12 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION7
12/13/2022440476520Open ↗
12/13/2022440481195Open ↗
11/11/2022440633637Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED4
11/16/2021440695865Open ↗
Showing 1 of 4 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance29
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY11
09/17/2021420663589Open ↗
Showing 1 of 11 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS2
11/11/2022440633637Open ↗
03/09/2022420663589Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL2
11/11/2022440633637Open ↗
03/09/2022420663589Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
04/16/2025420663589Open ↗
11/11/2022440633637Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q00500272-I1Open ↗
▸Inspections & Test Reports45
▸BISTECHNICAL REPORT: RESPONSIBILITY30
04/09/2022440593458Open ↗
01/20/2022420663589Open ↗
11/16/2021440695865Open ↗
Showing 3 of 30 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
04/17/2025420663589Open ↗
11/11/2022440633637Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)2
10/11/2022440626404Open ↗
08/17/2022440695865Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
11/09/2022420663589Open ↗
Showing 1 of 2 on file for this type
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
11/11/2022440633637Open ↗
▸Approvals, Objections & Sign-offs60
▸BISSUPERSEDING LETTER23
12/20/2022440481195Open ↗
03/08/2022420663589Open ↗
Showing 2 of 23 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE11
08/20/2025420663589Open ↗
08/18/2025420663589Open ↗
06/05/2025420663589Open ↗
Showing 3 of 11 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION9
09/03/2024421134347Open ↗
09/03/2024421134347Open ↗
09/03/2024421134347Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST8
10/24/2025440476520Open ↗
12/14/2022440481195Open ↗
11/30/2022421646927Open ↗
Showing 3 of 8 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISFINAL4
11/11/2022440633637Open ↗
10/11/2022440626404Open ↗
09/27/2022440695865Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership24
▸BISCOST AFFIDAVIT16
11/16/2021440695865Open ↗
Showing 1 of 16 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW36
12/13/2022440476520Open ↗
12/13/2022440481195Open ↗
11/28/2022421646927Open ↗
Showing 3 of 6 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Filing & Intake Forms79
▸BISADDITIONAL INFORMATION43
06/27/2025420663589Open ↗
01/03/2025420663589Open ↗
09/28/2023440489473Open ↗
Showing 3 of 43 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET13
11/16/2021440695865Open ↗
Showing 1 of 13 on file for this type
▸BISBOROUGH INTAKE FORM12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISEFILING COVER SHEET11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸Other Documents9
▸BISBPP - SUPPORTING DOCUMENTATION3
09/28/2023440489473Open ↗
Showing 1 of 3 on file for this type
▸BISPLOT DIAGRAM2
09/03/2024421134347Open ↗
Showing 1 of 2 on file for this type
▸BISTREE REMOVAL: OUTSIDE PROP./PARKS APPR2
10/04/2023440489473Open ↗
10/04/2023440489473Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
09/28/2023440489473Open ↗
09/28/2023440489473Open ↗