| Owner | Filings | Most Recent |
|---|---|---|
| CREW CONTRACTING OF NJ | 5 | 07/08/2026 |
| 173 175 TENNANTS CORP | 76 | 03/22/2026 |
| AUGUST CONSTRUCTION GROUP | 1 | 03/22/2026 |
| 173-175 RIVERSIDE DRIVE | 7 | 03/21/2026 |
| 173-175 RIVERSIDE TENANTS CORPOR | 16 | 03/21/2026 |
| 173-75TENNAT CORP DOUGLAS ELLIMA | 4 | 03/21/2026 |
| C O INSIGNIA RESIDENTIAL GROUP | 2 | 03/21/2026 |
| 173-175TENANTSCORP C ODOUGLASELL | 2 | 03/21/2026 |
| SHAREHOLDER | 6 | 03/21/2026 |
| 173-175 TE | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| WALTER B. MELVIN ARCHITECTS, LLC | 3 | 06/02/2026 |
| ROBERT ELLIOTT LESLIE ARCHITECTURE | 2 | 11/21/2025 |
| MICHAEL ZENREICH ARCHITECT PC | 2 | 10/29/2024 |
| EN-POWER GROUP | 1 | 08/23/2024 |
| D'ANTONIO CONSULTING ENGINEERS | 3 | 03/27/2023 |
| KATE PLATT | 3 | 03/21/2023 |
| PIER FINE ASSOCIATES | 4 | 02/02/2023 |
| CHARLES G. MICHEL ENGINEERING, PC. | 2 | 01/13/2023 |
| TED PORTER ARCHITECTURE | 1 | 01/13/2023 |
| NICHOLAS A. CICHANOWSKI ARCHITECT, | 4 | 11/07/2022 |
| WILLIAM F. RYAN, JR. P.E. PC | 1 | 08/17/2022 |
| LAURA LIEVANO | 5 | 08/06/2022 |
| ROB HEGEDUS ARCHITECT | 2 | 08/01/2022 |
| FINK & PLATT ARCHITECTS | 2 | 10/19/2021 |
| JACK STONE ENGINEERS, PC | 1 | 08/01/2021 |
| EMTG CONSULTANTS INC | 8 | 07/22/2021 |
| ALLEN + KILLCOYNE ARCHITECTS LLP | 1 | 07/22/2021 |
| BLEJER ARCHITECTURE | 2 | 05/21/2021 |
| JACK GREEN ASSOCIATES | 1 | 05/21/2021 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 09/18/2020 |
| IP GROUP | 1 | 07/20/2020 |
| JOEL PHAGOO P.E. PLLC | 1 | 01/18/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Love of Design | 5 | 03/21/2026 |
| GAMILL ENGINEERING, PC | 12 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 14 | 03/21/2026 |
| BURNHAM NATIONWIDE INC | 6 | 03/21/2026 |
| BOYD CONSULTING | 4 | 03/21/2026 |
| MIKE WARSHAW ARCHITECT | 4 | 03/21/2026 |
| DOMANI CONSULTING | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 4 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BREND RESTORATION LLC | General Contractor | 9 | 03/21/2026 |
| NOVA CONSTRUCTION SERVICE | General Contractor | 7 | 07/08/2026 |
| BANNER CONSTRUCTION CORP | General Contractor | 6 | 07/08/2026 |
| SOCRATES COATING AND CON* | General Contractor | 6 | 07/08/2026 |
| PERFECTO CONSTRUCTION COR | General Contractor | 5 | 07/08/2026 |
| MACRO CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| CRYSTAL COMFORT INC | General Contractor | 4 | 03/21/2026 |
| ASA BUILDING MAINT INC | General Contractor | 3 | 04/09/2026 |
| AMM GEN'L CONTRACTING INC | Plumbing | 3 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| GLEICH, BERNARD | Electrical | 2 | 03/21/2026 |
| CREW CONTRACTING OF NJ INC | General Contractor | 2 | 07/08/2026 |
| A.M.N. CORPORATION | Plumbing | 2 | 07/08/2026 |
| ALBENGA CONTRACTING CORP | General Contractor | 2 | 03/21/2026 |
| NU-WAY HEATING & COOLING | General Contractor | 2 | 03/21/2026 |
| HAMILTON AIR COMPANY, INC. | General Contractor | 1 | 07/08/2026 |
| MAMAIS CONTRACTING CORP | General Contractor | 1 | 07/08/2026 |
| NU CREATION MECH INC | General Contractor | 1 | 07/08/2026 |
| TOLMAC CONCEPTS INC | General Contractor | 1 | 07/08/2026 |
| TRIESTE CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| VISION BLDG AND RESTORATION | General Contractor | 1 | 07/08/2026 |
| FLINT MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| AMSTERDAM ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 07/08/2026 |
| N.PAGANO P&H CONTR LTD | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WALTER B. MELVIN ARCHITEC | 6652 | 1 | 06/02/2026 |
| SITE SAFETY LLC | 8555 | 1 | 06/02/2026 |
| CROSSCHECK INSPECTION SER | 544 | 1 | 01/29/2025 |
| MICHAEL ZENREICH ARCHITEC | 1724 | 2 | 10/29/2024 |
| GROUP-S LLC | 5216 | 1 | 08/23/2024 |
| D'ANTONIO CONSULTING ENGI | 931 | 3 | 03/27/2023 |
| PLATT DANA ARCHITECTS PC | 8024 | 6 | 03/27/2023 |
| PIER, FINE ASSOCIATES | 1069 | 2 | 02/02/2023 |
| ALAN MARGOLIN & ASSOC | 423 | 2 | 02/02/2023 |
| CHARLES G MICHEL ENGINEER | 2871 | 1 | 01/13/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | BREND RESTORATION SRVC | 06/23/2026 |
| DOB NOW | General Construction | Permit Issued | ASA BUILDING MAINT | 02/18/2026 |
| DOB NOW | General Construction | Permit Issued | ASA BUILDING MAINT | 03/03/2025 |
| DOB NOW | General Construction | Signed-off | BREND RESTORATION LLC | 09/09/2024 |
| DOB NOW | Mechanical Systems | Signed-off | CRYSTAL COMFORT | 08/27/2024 |
| DOB NOW | General Construction | Signed-off | TOLMAC CONCEPTS INC | 08/13/2024 |
| DOB NOW | General Construction | Signed-off | BANNER CONSTRUCTION CORP | 03/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | BANNER CONSTRUCTION CORP | 03/07/2024 |
| DOB NOW | General Construction | Signed-off | BREND RESTORATION LLC | 09/15/2023 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 03/14/2023 |
| DOB NOW | General Construction | Signed-off | BANNER CONSTRUCTION CORP | 03/10/2023 |
| DOB NOW | General Construction | Signed-off | SOCRATES COATING AND CON* | 03/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BANNER CONSTRUCTION CORP | 03/10/2023 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 02/09/2023 |
| DOB NOW | Mechanical Systems | Signed-off | NU CREATION MECH INC | 02/07/2023 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 01/13/2023 |
| DOB NOW | General Construction | Signed-off | TRIESTE CONSTRUCTION CORP | 01/06/2023 |
| DOB NOW | Plumbing | Signed-off | FLINT MECHANICAL CORP | 12/06/2022 |
| DOB NOW | Mechanical Systems | Signed-off | PERFECTO CONSTRUCTION COR | 11/16/2022 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 11/15/2022 |
| DOB NOW | General Construction | Signed-off | NU-WAY HEATING & COOLING | 11/10/2022 |
| DOB NOW | General Construction | Signed-off | SOCRATES COATING AND CON* | 10/24/2022 |
| DOB NOW | General Construction | Signed-off | ALBENGA CONTRACTING | 09/08/2022 |
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 08/17/2022 |
| DOB NOW | General Construction | Signed-off | MAMAIS CONTRACTING CORP | 07/18/2022 |
| DOB NOW | Mechanical Systems | Signed-off | PERFECTO CONSTRUCTION COR | 04/26/2022 |
| DOB NOW | General Construction | Signed-off | MACRO CONSTRUCTION INC | 04/21/2022 |
| DOB NOW | Sprinklers | Signed-off | ALLSTATE SPRINKLER LLC | 04/21/2022 |
| DOB NOW | Plumbing | Signed-off | AMM GEN'L CONTRACTING INC | 04/12/2022 |
| DOB NOW | Plumbing | Signed-off | AMM GEN'L CONTRACTING INC | 03/30/2022 |
| DOB NOW | General Construction | Signed-off | SOCRATES COATING AND CON* | 03/18/2022 |
| DOB NOW | General Construction | Signed-off | BREND RESTORATION LLC | 03/15/2022 |
| DOB NOW | General Construction | Signed-off | PERFECTO CONSTRUCTION COR | 01/31/2022 |
| DOB NOW | General Construction | Signed-off | MACRO CONSTRUCTION INC | 01/19/2022 |
| DOB NOW | Plumbing | Signed-off | PAUL QUINN PLBG & HTG INC | 11/03/2021 |
| DOB NOW | General Construction | Signed-off | MACRO CONSTRUCTION INC | 10/28/2021 |
| DOB NOW | Mechanical Systems | Signed-off | HAMILTON AIR COMPANY, INC. | 08/10/2021 |
| DOB NOW | General Construction | Signed-off | SOCRATES COATING AND CON* | 07/29/2021 |
| DOB NOW | Plumbing | Signed-off | N.PAGANO P&H CONTR LTD | 07/28/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | NOVA CONSTRUCTION SERVICE | 06/08/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/17/2022 | — | — | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PUMY-P60NKMU1 5 tons · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/26/2026 | Complete | METROPOLITAN ELEC OF NY I | General Wiring |
| 12/16/2025 | Complete | GLENDALE ELECTL CONTNG IN | — |
| 04/07/2025 | Permit Issued | ACCURATE ELEC'L CORP. | General Wiring |
| 02/14/2025 | Complete | BERGER QUALITY ELEC'L CON | General Wiring |
| 10/31/2024 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 08/31/2024 | Complete | S.E. ELECTL CONTNG CORP | General Wiring |
| 08/23/2024 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 05/23/2024 | Complete | METROPOLITAN ELEC OF NY I | General Wiring |
| 02/01/2024 | Complete | BIG CITY ELECL SOLUTIONS | General Wiring |
| 04/21/2023 | Permit Issued | GMC ELECTRICAL INC | General Wiring, Lighting |
| 04/18/2023 | Complete | RND ELECTRIC CORP | General Wiring |
| 01/17/2023 | Complete | MCCLEARY ELEC CONT INC | General Wiring |
| 11/08/2022 | Complete | LENS ELECTRIC, INC | General Wiring |
| 07/17/2022 | Complete | EPC ELECTRICAL CORP. | General Wiring |
| 01/14/2022 | Complete | SNB ELECTRICAL CONTNG COR | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2020 | Permit Issued | NOVA CONSTRUCTION SERVICE | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/13/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/13/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/20/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/20/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/31/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/31/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/13/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/11/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/11/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/10/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/03/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/06/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/02/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/27/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/21/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/01/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/14/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/26/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/06/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/18/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/05/2026 | Masonry | Martin Griggs | special |
| 05/04/2026 | Tenant Protection Plan Compliance | KHALID ALGENDE | special |
| 05/04/2026 | Final | Martin Griggs | progress |
| 12/12/2025 | Final | Robert Leslie | progress |
| 12/12/2025 | Tenant Protection Plan Compliance | EUGENE BIFULCO | special |
| 12/12/2025 | Lighting controls | EUGENE BIFULCO | energy_progress |
| 12/12/2025 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 10/10/2025 | Tenant Protection Plan Compliance | — | special |
| 10/08/2025 | Final | Robert Leslie | progress |
| 10/08/2025 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 10/08/2025 | Lighting controls | EUGENE BIFULCO | energy_progress |
| 12/10/2024 | Final | Martin Griggs | progress |
| 11/19/2024 | Final | Martin Griggs | progress |
| 10/28/2024 | Final | Michael Zenreich | progress |
| 10/28/2024 | Fire-Resistant Penetrations and Joints | Michael Zenreich | special |
| 10/28/2024 | Post-installed Anchors | Michael Zenreich | special |
| 10/28/2024 | Fire-Resistance Rated Construction | Michael Zenreich | progress |
| 06/10/2024 | Tenant Protection Plan Compliance | MICHAEL SCORRANO | special |
| 06/10/2024 | Maintenance information | MICHAEL SCORRANO | energy_progress |
| 06/10/2024 | HVAC-R and service water heating equipment | MICHAEL SCORRANO | energy_progress |
| 06/10/2024 | HVAC-R and service water piping design and insulation | MICHAEL SCORRANO | energy_progress |
| 06/10/2024 | HVAC-R and service water heating system controls | MICHAEL SCORRANO | energy_progress |
| 06/10/2024 | Final | MICHAEL SCORRANO | progress |
| 06/10/2024 | Energy Code Compliance Inspections | MICHAEL SCORRANO | progress |
| 06/10/2024 | Fire-Resistant Penetrations and Joints | MICHAEL SCORRANO | special |