← Back
Over six families without stores
Reid Park Rock
190 TAPSCOTT STREET · BIN 3081472
💬 Discuss this project
1930Year Built
4Stories
C1Building Class
R6Zoning
17,494 sfGross Floor Area
27Units
Rent Stabilized18 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: NYC PACT PRESERVATION PARTNERS LLC · 4,942 sf lot · 3.54 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Roof4p · 3 filings · 20 docs
Floor 18p · 3 filings · 20 docs
Cellar11p · 5 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW YORK CITY HOUSING AUTHORITY707/08/2026
PARSONS CONSTRUCTION407/08/2026
ACE GROUP NY407/08/2026
OWNER OF PREMISES103/22/2026
NYCHA NY HOUSING AUTHORITY203/21/2026
NYC PACT PRESERVATION PARTNERS203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
METROPOLIS GROUP INC2003/21/2026
CONVERSANO ASSOCIATES, INC.103/21/2026
GREEN STUDIO203/21/2026
BARNWELL CONSULTANTS103/21/2026
KD DESIGNS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FSC D&C LLCGeneral Contractor407/08/2026
DUAL FUEL PLUBING & HTINGPlumbing407/08/2026
LET IT GROW, INCORPORATEDGeneral Contractor204/09/2026
DUAL FUEL COMPANY LLCGeneral Contractor207/08/2026
HENRY SIMON INCElectrical103/21/2026
ACE GROUP NY CORPGeneral Contractor107/08/2026
CATANZARO, PETERElectrical103/21/2026
LIBERTY NY RESTORATION INGeneral Contractor107/08/2026
PARSONS CONSTRUCTION INCGeneral Contractor107/08/2026
PYRAMID ETC COMPANIES, LLGeneral Contractor104/09/2026
A & E PLUMBING CORPPlumbing107/08/2026
ARSENAL SCAFFOLD INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
METRIC CONSULTING AND INS18031207/08/2026
Building Lifecycle
All (123)Filed (16)Permit Issued (17)Signed Off (8)Violation (41)Inspection (7)Objection (4)Special Inspection (30)
07/13/2026
Signed off — Alteration
WORK SHALL INCLUDE DIRECT REPLACEMENT OF FINISHES DIRECT REPLACEMENT OF APARTMENT KITCHEN, BATHROOMS, DOORS AND WINDOW SASHES. ADDITIONAL GROUND LEVEL HARDSCAPE REPAIRS AND IMPROVEMENTS AS NEEDED PER PLANS.
B00918356-I1
07/10/2026
Signed off — Alteration
B00931036-I1
07/08/2026
Filed — Alteration
WORK SHALL INCLUDE DIRECT REPLACEMENT OF FINISHES DIRECT REPLACEMENT OF APARTMENT KITCHEN, BATHROOMS, DOORS AND WINDOW SASHES. ADDITIONAL GROUND LEVEL HARDSCAPE REPAIRS AND IMPROVEMENTS AS NEEDED PER PLANS.
B00918356-P2
07/08/2026
Special inspection requirement — Final
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Exterior lighting power
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Vestibules
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Air barrier - visual inspection
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Interior lighting power
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Lighting controls
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Lighting in dwelling units
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Fenestration air leakage
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Energy Code Compliance Inspections
SAMI HAJJAR P.E
07/08/2026
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
05/27/2026
Signed off — Alteration
MECHANICAL WORK INCLUDES INSTALLATION OF NEW GAS VENT DUCT IN BOILER ROOM EXISTING CHIMNEY
B00926271-I1
05/19/2026
Signed off — Alteration
SCOPE OF WORK INCLUDES THE REPLACEMENT OF GAS BOILERS AND ASSOCIATED PIPING AND DUCTWORK.
B01022433-I1
05/04/2026
Signed off — Alteration
Installation of plumbing fixtures along with related piping.
B00925874-I1
04/24/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/20/2026
Signed off — Alteration
Scope of work includes the repair and/or replacement of ventilation components and heating elements in bathroom/kitchen of existing apartments, as needed.
B00923692-I1
03/18/2026
Permit issued — General Construction
B00918356-I1-GC
03/11/2026
Signed off — Alteration
Installation of plumbing fixtures along with related piping.
B00946280-I1
03/02/2026
Signed off — Alteration
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01263126-I1
12/29/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/23/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
12/12/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SAMI HAJJAR P.E
12/12/2025
Special inspection requirement — HVAC-R and service water heating system controls
SAMI HAJJAR P.E
12/12/2025
Special inspection requirement — HVAC-R and service water heating equipment
SAMI HAJJAR P.E
12/12/2025
Special inspection requirement — Maintenance information
SAMI HAJJAR P.E
12/12/2025
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
12/12/2025
Special inspection requirement — Heating Systems
SAMI HAJJAR P.E
12/11/2025
Filed — Alteration
SCOPE OF WORK INCLUDES THE REPLACEMENT OF GAS BOILERS AND ASSOCIATED PIPING AND DUCTWORK.
B01022433-P1
11/21/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/13/2025
Violation issued (HPD, closed)
C
10/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SAMI HAJJAR P.E
10/24/2025
Special inspection requirement — HVAC-R and service water heating system controls
SAMI HAJJAR P.E
10/24/2025
Special inspection requirement — HVAC-R and service water heating equipment
SAMI HAJJAR P.E
10/24/2025
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
10/24/2025
Special inspection requirement — Maintenance information
SAMI HAJJAR P.E
10/24/2025
Special inspection requirement — Electrical motors and elevators
SAMI HAJJAR P.E
10/22/2025
Filed — Alteration
Installation of plumbing fixtures along with related piping.
B00925874-P1
10/15/2025
Violation issued (HPD, open)
B
10/15/2025
Violation issued (HPD, open)
B
10/15/2025
Violation issued (HPD, open)
A
10/15/2025
Violation issued (HPD, closed)
C
10/15/2025
Violation issued (HPD, open)
A
08/26/2025
Permit issued — Supported Scaffold
B01277233-I1-SF
08/25/2025
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLDING PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01277233-I1
08/21/2025
Permit issued — General Construction
B00931036-I1-GC
07/31/2025
Permit issued — Sidewalk Shed
B01263126-I1-SH
07/30/2025
Filed — Alteration
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01263126-I1
07/02/2025
Permit issued — Plumbing
B00925874-I1-PL
07/01/2025
Permit issued — Mechanical Systems
B00926271-I1-MS
06/25/2025
Permit issued — General Construction
B01184984-I1-GC-CX
06/25/2025
Violation issued (HPD, open)
C
06/25/2025
Violation issued (HPD, open)
B
04/28/2025
Permit issued — General Construction
B00918356-I1-GC
04/15/2025
Permit issued — General Construction
B01184984-I1-GC-CX
04/07/2025
Filed — Alteration
GENERAL LANDSCAPING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01184984-I1
04/02/2025
Filed — Alteration
WORK SHALL INCLUDE DIRECT REPLACEMENT OF FINISHES DIRECT REPLACEMENT OF APARTMENT KITCHEN, BATHROOMS, DOORS AND WINDOW SASHES. ADDITIONAL GROUND LEVEL HARDSCAPE REPAIRS AND IMPROVEMENTS AS NEEDED PER PLANS.
B00918356-P1
Latest 60 of 123 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC03/18/2026
DOB NOWSupported ScaffoldPermit IssuedACE GROUP NY CORP08/26/2025
DOB NOWGeneral ConstructionSigned-offLIBERTY NY RESTORATION IN08/21/2025
DOB NOWSidewalk ShedSigned-offARSENAL SCAFFOLD INC07/31/2025
DOB NOWPlumbingSigned-offDUAL FUEL PLUBING & HTING07/02/2025
DOB NOWMechanical SystemsSigned-offDUAL FUEL COMPANY LLC07/01/2025
DOB NOWGeneral ConstructionSigned-offLET IT GROW, INCORPORATED06/25/2025
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC04/28/2025
DOB NOWGeneral ConstructionSigned-offLET IT GROW, INCORPORATED04/15/2025
DOB NOWPlumbingSigned-offA & E PLUMBING CORP08/13/2024
DOB NOWMechanical SystemsSigned-offPYRAMID ETC COMPANIES, LL08/12/2024
DOB NOWPlumbingSigned-offDUAL FUEL PLUBING & HTING07/15/2024
DOB NOWMechanical SystemsSigned-offDUAL FUEL COMPANY LLC06/05/2024
DOB NOWBoiler EquipmentSigned-offDUAL FUEL PLUBING & HTING06/05/2024
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC04/30/2024
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC11/09/2023
DOB NOWSidewalk ShedPermit IssuedPARSONS CONSTRUCTION INC10/12/2019
BISBLISSUEDACE CONTRACTING, INC09/19/2013
BISPLISSUEDACE CONTRACTING, INC09/19/2013
BISEQISSUEDNAVTECH CONSTRUCTION CORP03/19/2010
BISEQISSUEDPARADISE CONST CO06/09/1997
3 projects · most recent 09/09/2025
General Wiring Boiler Controls
FiledStatusContractorScope
09/09/2025CompleteATLAS-ACON ELEC. SERVICEGeneral Wiring
12/02/2019Permit IssuedN.Y.C. HOUSING AUTHORITYBoiler Controls
10/05/2019Permit IssuedRICHARD NEU—
2 projects · most recent 04/07/2025
Steel
FiledStatusContractorScope
04/07/2025Signed-offLET IT GROW, INCORPORATED1 scope_items
09/04/2023——Steel
1 project · most recent 08/25/2025
Scaffold
FiledStatusContractorScope
08/25/2025Permit IssuedACE GROUP NY CORPScaffold
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
04/24/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/29/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/23/2025Pass-Final Boiler Equipment InspectionPassView ↗
11/21/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/12/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/30/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/16/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 56
DateRequirementInspectorRole
07/08/2026FinalSAMI HAJJAR P.Eprogress
07/08/2026Exterior lighting powerSAMI HAJJAR P.Eenergy_progress
07/08/2026VestibulesSAMI HAJJAR P.Eenergy_progress
07/08/2026Air barrier - visual inspectionSAMI HAJJAR P.Eenergy_progress
07/08/2026Interior lighting powerSAMI HAJJAR P.Eenergy_progress
07/08/2026Lighting controlsSAMI HAJJAR P.Eenergy_progress
07/08/2026Lighting in dwelling unitsSAMI HAJJAR P.Eenergy_progress
07/08/2026Fenestration and door U-factor and product ratingsSAMI HAJJAR P.Eenergy_progress
07/08/2026Fenestration air leakageSAMI HAJJAR P.Eenergy_progress
07/08/2026Energy Code Compliance InspectionsSAMI HAJJAR P.Eprogress
07/08/2026Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
12/12/2025HVAC-R and service water piping design and insulationSAMI HAJJAR P.Eenergy_progress
12/12/2025HVAC-R and service water heating system controlsSAMI HAJJAR P.Eenergy_progress
12/12/2025HVAC-R and service water heating equipmentSAMI HAJJAR P.Eenergy_progress
12/12/2025Maintenance informationSAMI HAJJAR P.Eenergy_progress
12/12/2025Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
12/12/2025Heating SystemsSAMI HAJJAR P.Especial
10/24/2025HVAC-R and service water piping design and insulationSAMI HAJJAR P.Eenergy_progress
10/24/2025HVAC-R and service water heating system controlsSAMI HAJJAR P.Eenergy_progress
10/24/2025HVAC-R and service water heating equipmentSAMI HAJJAR P.Eenergy_progress
10/24/2025Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
10/24/2025Maintenance informationSAMI HAJJAR P.Eenergy_progress
10/24/2025Electrical motors and elevatorsSAMI HAJJAR P.Eenergy_progress
03/31/2025Lighting controlsSAMI HAJJAR P.Eenergy_progress
03/31/2025Fenestration and door U-factor and product ratingsSAMI HAJJAR P.Eenergy_progress
Latest 25 of 56.
▾Documents — 106 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch13
08/25/2026B00931036-I1Request digital key ↗
08/25/2026B00926271-I1Request digital key ↗
08/24/2026B00923692-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00241017-I1Request digital key ↗
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION3
09/27/2013320874416Open ↗
03/22/2010320113854Open ↗
12/30/2009320113854Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION3
09/17/2013320874416Open ↗
04/06/2010320113854Open ↗
12/29/2009320113854Open ↗
▸Seals & Professional Certifications45
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/25/2026B00931036-I1Open ↗
08/25/2026B00926271-I1Open ↗
08/22/2026B00918356-P2Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/23/2026B01022433-I1Open ↗
09/01/2026B00923692-I1Open ↗
09/01/2026B00923692-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
09/23/2026B01022433-I1Open ↗
09/23/2026B01022433-I1Open ↗
09/01/2026B00923692-I1Open ↗
Showing 3 of 11 on file for this type
▸BISProfessional and Owner Certification (POC3)3
09/17/2013320874416Open ↗
09/17/2013320874416Open ↗
09/17/2013320874416Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
09/17/2013320874416Open ↗
12/29/2009320113854Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
12/29/2009320113854Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY-CERTIFICATION1
09/17/2013320874416Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
09/17/2013320874416Open ↗
▸Safety & Tenant Protection1
▸DOB NOWTenant Protection Plan1
08/13/2026B00241017-I1Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/25/2026B00931036-I1Open ↗
08/25/2026B00926271-I1Open ↗
08/22/2026B00918356-P2Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
12/29/2009320113854Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
09/17/2013320874416Open ↗
▸Energy Compliance2
▸BISTR8: Energy Code Progress Inspections1
09/17/2013320874416Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/19/2026B01022433-I1Open ↗
▸Approvals, Objections & Sign-offs18
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter13
08/25/2026B00931036-I1Open ↗
08/25/2026B00926271-I1Open ↗
08/22/2026B00918356-P2Open ↗
Showing 3 of 13 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
11/07/2011320113854Open ↗
11/02/2011320113854Open ↗
05/23/2011320113854Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
12/29/2009320113854Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/17/2013320874416Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
09/17/2013320874416Open ↗
▸Filing & Intake Forms4
▸BISEFILING COVER SHEET2
09/17/2013320874416Open ↗
12/29/2009320113854Open ↗
▸BISADDITIONAL INFORMATION2
04/08/2010320113854Open ↗
04/06/2010320113854Open ↗
▸Other Documents1
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll1
08/13/2026B01184984-I1Open ↗