← Back
Condo, commercial tower (mixed-use) [derived]
200 LAFAYETTE STREET
MANHATTAN · BIN 1007223
💬 Discuss this project
1900Year Built
7Stories
RCBuilding Class
M1-5/R7DZoning
81,696 sfGross Floor Area
2Units
LL97 Covered2 Open Violations ▸FISP: SAFEFDNY Report ↗
Condo, commercial tower (mixed-use) [derived] · 13,945 sf lot · 5.86 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction39p · 10 filings · 20 docs
Floor 7Under Construction45p · 4 filings · 20 docs
Floor 6Under Construction48p · 5 filings · 20 docs
Floor 513p · 5 filings · 20 docs
Floor 4Under Construction28p · 5 filings · 20 docs
Floor 3Under Construction27p · 5 filings · 20 docs
Floor 245p · 10 filings · 20 docs
Floor 144p · 12 filings · 20 docs
Cellar53p · 15 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SIGNEXPO1307/08/2026
GENERAL GROWTH PROPERTIES INC2107/08/2026
TRM CONTRACTING503/22/2026
1 R S103/22/2026
TOO HUNDRED LAFAYETTE LLC103/22/2026
420 BROOME ST OWNERS1403/22/2026
200 LAFAYETTE STREET1703/22/2026
JLL703/22/2026
GGP INC URBAN PROPERTIES303/22/2026
200 LAFAYETTE4203/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RIZZO GROUP6003/21/2026
JAM CONSULTANTS, INC.203/21/2026
LOUIS STRIAR1203/21/2026
A1 EXPEDITING SERVICE203/21/2026
AGOUTI CONSTRUCTION CONSULTING1203/21/2026
RETHY ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
K.J. REMODELING OF NY CO*General Contractor1207/08/2026
STRUCTURE TONE, LLCGeneral Contractor1207/08/2026
JT MAGEN & COMPANY INCGeneral Contractor909/26/2026
NICON BUILD LLCGeneral Contractor907/08/2026
CJS INDUSTRIES INCGeneral Contractor707/08/2026
A + SPRINKLER CORPFire Protection607/08/2026
FEDER, IRVINGElectrical503/21/2026
VIVIANO, PAULElectrical503/21/2026
FM95 NYScaffold407/08/2026
P & D MECHANICAL CORPFire Protection307/08/2026
NORLIN ELECL CONTRS INCElectrical303/22/2026
WHALEN CONSTRUCTION, INCGeneral Contractor307/08/2026
FM95NY LLCGeneral Contractor207/08/2026
HOLT CONSTRUCTION CORPGeneral Contractor203/21/2026
SPEZIALE, JOSEPHElectrical203/21/2026
CM PLUMBING INCPlumbing207/08/2026
PAR PLUMBING CO., INCPlumbing207/08/2026
SOH PAR SPRINKLER LLCFire Protection207/08/2026
ELYSIUM CONSTRUCTION INCGeneral Contractor203/21/2026
COMMERICAL PLBG SVCES LLCPlumbing107/08/2026
HYDRONIC CONCEPTS NY P&HPlumbing107/08/2026
HYDRONIC CONCEPTS NY PLBGPlumbing107/08/2026
M&T PLBG AND HTG CO., INCPlumbing107/08/2026
ABCO-PEERLESS SPRKLR CORPFire Protection107/08/2026
PETER AMABILEElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JACK GREEN ASSOCIATES422106/10/2026
CODEGREEN510903/12/2026
MEP INSPECTIONS, INC1102312/22/2025
ATLAS ATC ENGINEERING INC80112010/31/2023
SKYLINE ENGINEERING, PLLC267604/21/2023
ROSINI ENGINEERING, PC3282111/08/2022
AK ENGINEERING PC678411/07/2022
AVCON ENGINEERING PC548111/02/2022
PROJECT TACTICAL SOLUTION5859410/13/2022
Building Lifecycle
All (300)Filed (72)Permit Issued (58)Signed Off (38)Violation (8)Inspection (36)Objection (58)Special Inspection (30)
09/25/2026
Permit issued — General Construction
M01319575-I1-GC
09/25/2026
Permit issued — Mechanical Systems
M01319575-S1-MS
09/25/2026
Permit issued — Structural
M01319575-S4-ST
09/03/2026
Filed — Alteration
Plumbing modifications taking place on the roof as indicated on the drawings.
M01383935-I1
08/12/2026
Signed off — Alteration
Remove existing and Install new AC units and associated components, as per plans filed herewith. No change to use. egress or occupancy.
M01410205-I1
08/11/2026
Inspection — Under Review Boiler Equipment Inspection
Under Review
View inspection ↗
08/04/2026
Signed off — Alteration
Mechanical modifications taking place on the 6th & 7th floors as indicated on the drawings.
M01289928-S4
08/04/2026
Signed off — Alteration
Mechanical modifications taking place on the 6th & 7th floors as indicated on the drawings.
M01289928-S3
07/16/2026
Objection raised — Other
07/16/2026
Objection raised — Scope
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/16/2026
Objection resolved — Resolved
07/01/2026
Signed off — Alteration
Mechanical modifications taking place on the 6th & 7th floors as indicated on the drawings.
M01289928-S1
06/30/2026
Signed off — Alteration
Mechanical modifications taking place on the 6th & 7th floors as indicated on the drawings.
M01289928-I1
06/16/2026
Permit issued — Mechanical Systems
M01410205-I1-MS
06/10/2026
Filed — Alteration
Remove existing and Install new AC units and associated components, as per plans filed herewith. No change to use. egress or occupancy.
M01410205-I1
06/10/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/09/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
LAWRENCE GREEN
06/09/2026
Special inspection requirement — Maintenance information
LAWRENCE GREEN
06/09/2026
Special inspection requirement — HVAC-R and service water heating equipment
LAWRENCE GREEN
06/09/2026
Special inspection requirement — HVAC-R and service water heating system controls
LAWRENCE GREEN
06/09/2026
Special inspection requirement — Duct leakage testing, insulation and design
LAWRENCE GREEN
06/08/2026
Objection raised — Fire_Protection
06/08/2026
Objection raised — Accessibility
06/08/2026
Objection raised — Fire_Protection
06/08/2026
Objection raised — Fire_Protection
06/08/2026
Objection raised — Structural
06/08/2026
Objection raised — Structural
06/08/2026
Objection raised — Cost
06/08/2026
Objection raised — Structural
06/08/2026
Objection raised — Fire_Protection
06/08/2026
Objection raised — Inspections
06/08/2026
Objection raised — Fire_Protection
06/03/2026
Filed — No Work
M01364118-I1
06/01/2026
Special inspection requirement — Final
LAWRENCE GREEN
06/01/2026
Special inspection requirement — Mechanical Systems
LAWRENCE GREEN
05/14/2026
Permit issued — Sprinklers
M01289928-S4-EW-SP
04/30/2026
Filed — Alteration CO
Creation of a Public Assembly on the 6th floor & roof resulting in a change of use and occupancy. General construction modifications taking place on this application.
M01358560-I1
04/30/2026
Special inspection requirement — Lighting controls
04/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/30/2026
Special inspection requirement — Exterior lighting power
04/28/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/07/2026
Special inspection requirement — Final
04/07/2026
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
04/02/2026
Permit issued — Plumbing
M01319575-S2-PL
04/02/2026
Permit issued — Sprinklers
M01319575-S3-EW-SP
03/19/2026
Permit issued — Mechanical Systems
M01319575-S5-MS
03/12/2026
Filed — Alteration
Sprinkler modifications taking place on the 6th & 7th floors as indicated on the drawings.
M01319575-S5
03/11/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/10/2026
Signed off — Alteration
Modification of plumbing and sprinkler systems on the 3rd and 4th floors, as per plans filed herewith. No change in use, egress or occupancy.
M00766826-S6
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedJT MAGEN & COMPANY INC09/25/2026
DOB NOWMechanical SystemsPermit IssuedJT MAGEN & COMPANY INC09/25/2026
DOB NOWStructuralPermit IssuedJT MAGEN & COMPANY INC09/25/2026
DOB NOWMechanical SystemsSigned-offWHALEN CONSTRUCTION, INC06/16/2026
DOB NOWSprinklersSigned-offP & D MECHANICAL CORP05/14/2026
DOB NOWPlumbingPermit IssuedCM PLUMBING INC04/02/2026
DOB NOWSprinklersPermit IssuedP & D MECHANICAL CORP04/02/2026
DOB NOWMechanical SystemsPermit IssuedJT MAGEN & COMPANY INC03/19/2026
DOB NOWStructuralPermit IssuedJT MAGEN & COMPANY INC03/03/2026
DOB NOWGeneral ConstructionPermit IssuedJT MAGEN & COMPANY INC03/02/2026
DOB NOWMechanical SystemsPermit IssuedJT MAGEN & COMPANY INC03/02/2026
DOB NOWPlumbingSigned-offHYDRONIC CONCEPTS NY PLBG02/18/2026
DOB NOWPlumbingSigned-offHYDRONIC CONCEPTS NY P&H01/14/2026
DOB NOWMechanical SystemsSigned-offWHALEN CONSTRUCTION, INC12/29/2025
DOB NOWGeneral ConstructionSigned-offWHALEN CONSTRUCTION, INC12/29/2025
DOB NOWSprinklersSigned-offP & D MECHANICAL CORP11/06/2025
DOB NOWGeneral ConstructionSigned-offJT MAGEN & COMPANY INC11/05/2025
DOB NOWPlumbingSigned-offCM PLUMBING INC11/05/2025
DOB NOWMechanical SystemsSigned-offJT MAGEN & COMPANY INC11/03/2025
DOB NOWGeneral ConstructionPermit IssuedSTRUCTURE TONE, LLC04/08/2025
DOB NOWSprinklersSigned-offA + SPRINKLER CORP11/28/2023
DOB NOWSprinklersPermit IssuedA + SPRINKLER CORP11/28/2023
DOB NOWSprinklersSigned-offSOH PAR SPRINKLER LLC09/16/2023
DOB NOWGeneral ConstructionSigned-offFM95NY LLC08/08/2023
DOB NOWGeneral ConstructionSigned-offFM95NY LLC08/08/2023
DOB NOWSignSigned-offRED HOOK SIGN AND ELECT07/19/2023
DOB NOWSignSigned-offRED HOOK SIGN AND ELECT07/19/2023
DOB NOWSignSigned-offRED HOOK SIGN AND ELECT07/19/2023
DOB NOWSignSigned-offRED HOOK SIGN AND ELECT07/19/2023
DOB NOWProtection and Mechanical MethodsSigned-offSAFWAY ATLANTIC, LLC06/14/2023
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC05/08/2023
DOB NOWStructuralPermit IssuedSTRUCTURE TONE, LLC04/26/2023
DOB NOWMechanical SystemsSigned-offSTRUCTURE TONE, LLC04/20/2023
DOB NOWStructuralSigned-offSTRUCTURE TONE, LLC04/14/2023
DOB NOWMechanical SystemsSigned-offSTRUCTURE TONE, LLC04/14/2023
DOB NOWPlumbingSigned-offA & M WARSHAW PLBG & HTG04/02/2023
DOB NOWSprinklersSigned-offABCO-PEERLESS SPRKLR CORP03/29/2023
DOB NOWGeneral ConstructionPermit IssuedSTRUCTURE TONE, LLC03/29/2023
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC03/16/2023
DOB NOWPlumbingSigned-offA + SPRINKLER CORP03/10/2023
+ 60 more permits on file
2 projects · most recent 06/10/2026
Air Conditioning Systems Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/10/2026Signed-offWHALEN CONSTRUCTION, INCAir Conditioning Systems
Cooling
Gree CAS12HP230V1R32AH 12,000 BTU · Ahu ×3
MUL24HP230V1R32A0 24,000 BTU · Condensing Unit ×1
10/13/2022Permit IssuedNICON BUILD LLCAir Conditioning Systems, Heating and Air Conditioning Systems
Cooling
Stulz ATS-OHS-18 750 CFM · Crac Unit ×1
Heat / Cool
3 projects · most recent 03/12/2026
FiledStatusContractorScope
03/12/2026Permit IssuedCMP PIPING INC312 heads
10/28/2025Signed-offCMP PIPING INC280 heads
10/13/2022Signed-offA + SPRINKLER CORP—
4 projects · most recent 09/03/2026
Water/Sanitary
FiledStatusContractorScope
09/03/2026——Water/Sanitary
03/12/2026Permit IssuedCM PLUMBING INC—
12/22/2025Signed-offHYDRONIC CONCEPTS NY PLBGWater/Sanitary
10/28/2025Signed-offCM PLUMBING INCWater/Sanitary
14 projects · most recent 09/04/2026
General Wiring Lighting
FiledStatusContractorScope
09/04/2026Permit IssuedM.C. ELECTRICAL NY INCGeneral Wiring
01/02/2026Permit IssuedM.C. ELECTRICAL NY INCGeneral Wiring
12/05/2025CompleteUNITED ELEC & LIGHTING COGeneral Wiring
02/18/2025Permit IssuedNORLIN ELECL CONTRS INCGeneral Wiring
09/08/2023CompleteDAL ELECTRICAL CORP.1 meters, 1 new_meters
09/01/2023CompleteRAINBOW ELECTRIC CO., INC—
09/01/2023CompleteRAINBOW ELECTRIC CO., INC—
08/07/2023CompleteDAL ELECTRICAL CORP.General Wiring
03/27/2023CompleteUNI-LITE ELECTRIC, LLCGeneral Wiring
03/13/2023CompleteEMPIRE STATE ELEC MAINT &General Wiring, Lighting
11/14/2022CompleteALBA ELECTRIC CORPGeneral Wiring
03/28/2022CompleteGRAMERCY ELECTRIC INC—
10/11/2018CompleteNORLIN ELECL CONTRS INCGeneral Wiring, Lighting
04/19/2018Permit IssuedLIPPOLIS ELECTRIC, INC.General Wiring
1 project · most recent 10/28/2025
FiledStatusContractorScope
10/28/2025Signed-offCMP PIPING INC1 scope_items
▾Field Inspections (DOB CAP) — 36
DateTypeResultReport
08/11/2026Under Review Boiler Equipment InspectionUnder ReviewView ↗
06/10/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/28/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/11/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/20/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/31/2025Fail-Final CND-Occupancy InspectionFailView ↗
06/11/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/06/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/27/2024Pass-Final CND-Occupancy InspectionPassView ↗
05/09/2024Fail-Final CND-Occupancy InspectionFailView ↗
02/06/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/02/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/28/2023Pass-Final CND-Occupancy InspectionPassView ↗
11/21/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/20/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/27/2023Fail-Final CND-Occupancy InspectionFailView ↗
10/16/2023Pass-Final CND-Occupancy InspectionPassView ↗
10/04/2023Fail-Final SP - Up to 3 Requested FloorsFailView ↗
09/25/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/20/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/20/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/29/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/28/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/22/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/22/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
Latest 25 of 36.
▾Special Inspection Requirements (DOB NOW) — 144
DateRequirementInspectorRole
06/09/2026HVAC-R and service water piping design and insulationLAWRENCE GREENenergy_progress
06/09/2026HVAC-R and service water heating system controlsLAWRENCE GREENenergy_progress
06/09/2026Duct leakage testing, insulation and designLAWRENCE GREENenergy_progress
06/09/2026Maintenance informationLAWRENCE GREENenergy_progress
06/09/2026HVAC-R and service water heating equipmentLAWRENCE GREENenergy_progress
06/01/2026Mechanical SystemsLAWRENCE GREENspecial
06/01/2026FinalLAWRENCE GREENprogress
04/30/2026Fire-Resistant Penetrations and Joints—special
04/30/2026Exterior lighting power—energy_progress
04/30/2026Lighting controls—energy_progress
04/07/2026Fire-Resistant Penetrations and Joints—special
04/07/2026Mastic and Intumescent Fire-resistant Coatings—special
04/07/2026Final—progress
02/25/2026Public Assembly Emergency LightingJames Sullivan Jrprogress
02/11/2026Mastic and Intumescent Fire-resistant Coatings—special
02/10/2026FinalThomas Lanzelottiprogress
02/05/2026Mechanical SystemsHATIM ELSAIDspecial
02/05/2026Exhaust and Vent Systems in Plenums and DuctsHATIM ELSAIDspecial
02/05/2026FinalHATIM ELSAIDprogress
01/28/2026FinalHATIM ELSAIDprogress
01/28/2026Mechanical SystemsHATIM ELSAIDspecial
12/09/2025FinalHATIM ELSAIDprogress
12/09/2025Exhaust and Vent Systems in Plenums and DuctsHATIM ELSAIDspecial
12/09/2025FinalThomas Lanzelottiprogress
12/09/2025Mechanical SystemsHATIM ELSAIDspecial
Latest 25 of 144.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Andreessen HorowitzOfficeFloors 6, 7, Roof
Project M01358560 Alteration CO · Plan Examiner Review · 04/30/2026
Project M01319575 Alteration · Permit Entire · 02/13/2026
Project M01289928 Alteration · LOC Issued · 10/28/2025
EatalyRestaurant / Food ServiceCellar, Floor 1
Project M01174830 Alteration · Permit Entire · 03/20/2025
Project M00996021 No Work · Objections · 01/26/2024
ChobaniOfficeFloors 5–7
Project M00615275 Alteration · LOC Issued · 11/02/2022
a16zOfficeFloors 3, 4
Project M00766826 Alteration · LOC Issued · 08/26/2022
Project M00695246 Alteration · LOC Issued · 03/18/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 1,899 on file (BIS + DOB NOW)
▸Plans & Drawings80
▸DOB NOWPlans/Sketch75
09/15/2026M01383935-I1Request digital key ↗
09/15/2026M01383935-S1Request digital key ↗
09/06/2026M00002460-I1Request digital key ↗
Showing 3 of 75 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
08/29/2026M00902715-I1Request digital key ↗
Showing 1 of 2 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly2
08/28/2026M00996021-I1Request digital key ↗
Showing 1 of 2 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Applications & Permits400
▸BISPLAN / WORK APPROVAL APPLICATION181
01/13/2025123717013Open ↗
12/26/2023121056445Open ↗
07/19/2023121056445Open ↗
Showing 3 of 181 on file for this type
▸BISWORK PERMIT APPLICATION148
04/13/2022122675694Open ↗
04/04/2022122675694Open ↗
09/10/2020140942853Open ↗
Showing 3 of 148 on file for this type
▸DOB NOWLPC Approval/Permit66
09/15/2026M01383935-S1Open ↗
09/15/2026M01383935-I1Open ↗
09/02/2026M00701844-I1Open ↗
Showing 3 of 66 on file for this type
▸BISPLACE OF ASSEMBLY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records2
▸BISZONING RESOLUTION DETERMINATION2
04/20/2018121056445Open ↗
Showing 1 of 2 on file for this type
▸Seals & Professional Certifications489
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION193
08/16/2019123717013Open ↗
07/01/2019123717013Open ↗
06/20/2019122799445Open ↗
Showing 3 of 193 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature80
09/15/2026M01383935-I1Open ↗
09/15/2026M01383935-S1Open ↗
09/06/2026M00002460-I1Open ↗
Showing 3 of 80 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature74
09/23/2026M01319575-S3Open ↗
09/23/2026M01289928-S4Open ↗
09/01/2026M00830662-I1Open ↗
Showing 3 of 74 on file for this type
▸DOB NOWProgress Inspector Seal & Signature49
09/29/2026M00706754-I1Open ↗
09/29/2026M00706754-I1Open ↗
09/19/2026M08052442-P2Open ↗
Showing 3 of 49 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST41
06/22/2018123550932Open ↗
04/13/2018123442989Open ↗
Showing 2 of 41 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT26
09/09/2020140942853Open ↗
06/22/2018123550932Open ↗
04/13/2018123442989Open ↗
Showing 3 of 26 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment127
▸BISSCHEDULE B - PLUMBING30
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 30 on file for this type
▸BISSELF-CERT PLUMBING NOTICE25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISEQUIPMENT USE PERMITS23
05/31/2018122794976Open ↗
Showing 1 of 23 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE21
06/14/2018122675694Open ↗
06/14/2018123191170Open ↗
04/13/2018123442989Open ↗
Showing 3 of 21 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA13
11/03/2025123391837Open ↗
03/21/2018122987704Open ↗
Showing 2 of 13 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT10
05/31/2018122794976Open ↗
Showing 1 of 10 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSTANDPIPE INSP REPORT : FP-841
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection8
▸DOB NOWStreet Tree Checklist4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos155
▸DOB NOWDEP ACP-5: Asbestos Assessment Report74
09/15/2026M01383935-I1Open ↗
09/15/2026M01383935-S1Open ↗
09/02/2026M00701844-I1Open ↗
Showing 3 of 74 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)45
09/09/2020140942853Open ↗
07/01/2019123717013Open ↗
06/22/2018123550932Open ↗
Showing 3 of 45 on file for this type
▸BISTHIS IS NOT AN ASBESTOS PROJECT26
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 26 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸Energy Compliance64
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS36
02/19/2019122479120Open ↗
02/07/2019122479120Open ↗
02/07/2019122479120Open ↗
Showing 3 of 36 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS14
02/19/2019122479120Open ↗
02/07/2019122479120Open ↗
Showing 2 of 14 on file for this type
▸BISTR8: Energy Code Progress Inspections9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISTECHNICAL REPORT: ENERGY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Inspections & Test Reports24
▸BISTECHNICAL REPORT: RESPONSIBILITY7
08/31/2022122675694Open ↗
02/28/2022123442989Open ↗
12/08/2021122675694Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER7
08/16/2019123717013Open ↗
Showing 1 of 7 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
08/16/2019123717013Open ↗
Showing 1 of 4 on file for this type
▸BISCONCRETE DESIGN MIX (TR-3) 27-6052
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
08/31/2022122675694Open ↗
02/25/2022123442989Open ↗
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION2
08/20/2018121056445Open ↗
Showing 1 of 2 on file for this type
▸Approvals, Objections & Sign-offs199
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST79
09/01/2022122675694Open ↗
02/28/2022123442989Open ↗
12/10/2020140942853Open ↗
Showing 3 of 79 on file for this type
▸BISLANDMARKS APPROVAL37
09/09/2020140942853Open ↗
06/27/2018123550932Open ↗
04/13/2018123442989Open ↗
Showing 3 of 37 on file for this type
▸BISADMINISTRATIVE OBJECTIONS28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION22
04/13/2022122675694Open ↗
02/19/2019122479120Open ↗
05/31/2018122794976Open ↗
Showing 3 of 22 on file for this type
▸BISSUPERSEDING LETTER9
11/18/2019122675694Open ↗
10/31/2019122675694Open ↗
Showing 2 of 9 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE7
10/21/2022121056445Open ↗
05/18/2018121056445Open ↗
Showing 2 of 7 on file for this type
▸BISLANDMARKS SIGNOFF4
09/01/2022122675694Open ↗
02/25/2022123442989Open ↗
12/10/2020140942853Open ↗
Showing 3 of 4 on file for this type
▸BISFINAL2
08/31/2022122675694Open ↗
02/25/2022123442989Open ↗
▸BISSHED LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership123
▸BISCOST AFFIDAVIT120
02/25/2022123442989Open ↗
02/25/2022123442989Open ↗
12/10/2020140942853Open ↗
Showing 3 of 120 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
08/31/2022122675694Open ↗
02/28/2022123442989Open ↗
▸BISProperty Owner Sign Affidavit (SIG-1)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Filing & Intake Forms170
▸BISEFILING COVER SHEET78
07/01/2019123717013Open ↗
06/22/2018123550932Open ↗
04/13/2018123442989Open ↗
Showing 3 of 78 on file for this type
▸BISADDITIONAL INFORMATION66
11/13/2023121056445Open ↗
03/26/2023121056445Open ↗
04/04/2022122675694Open ↗
Showing 3 of 66 on file for this type
▸BISBOROUGH INTAKE FORM26
01/30/2020121056445Open ↗
10/03/2019121056445Open ↗
09/16/2019121056445Open ↗
Showing 3 of 26 on file for this type
▸Other Documents44
▸DOB NOWProof of Historic Building32
09/02/2026M00701844-I1Open ↗
08/29/2026M00830662-I1Open ↗
Showing 2 of 32 on file for this type
▸BISOP-129 INTERNAL (SECONDARY) BACKFLOW PREVENTION DEVICE TEST REPORT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWProperty Ownership Certification4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSupporting Document: Fee Deferment1
08/16/2023121056445Open ↗