Two family converted from one family
2052 63 STREET
BROOKLYN · BIN 3133275
💬 Discuss this project
1915Year Built
2Stories
B3Building Class
R5Zoning
3,551 sfGross Floor Area
2Units
4 Open Violations ▸FDNY Report ↗
Two family converted from one family · 3,138 sf lot · 1.13 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof23p · 5 filings · 20 docs
Floor 320p · 2 filings · 20 docs
Floor 221p · 2 filings · 20 docs
Floor 119p · 2 filings · 20 docs
Cellar19p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
J G CONSTRUCTION SRVCS607/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/27/2022$1.2M—ROSEMARIE E. RICHARD TRUST → Private party$341/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CHUN ENGINEERING CONSULTANT PLLC1302/12/2025
CAVALRY ASSOCIATES504/17/2024
AG ENGINEERING PLLC107/18/2023
MOHAMMAD AHEAD, PE107/13/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CAVALRY2003/21/2026
CAVALRY MANAGEMENT1003/21/2026
ARSENAL BUILDING CONSULTANTS LLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CLASSIC BUILDERS CORPGeneral Contractor707/08/2026
WIZ FIRE SPRINKLERS LLCFire Protection307/08/2026
ORBIT PLBG & HTG INCPlumbing207/08/2026
B.P. ELECTRIC CORPElectrical103/22/2026
J & G CONSTRUCTION SVCSGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. INT'L ENGINEERING PLLC3129902/12/2025
DAL H CHUN ENGINEER PC1972511/22/2024
CHUN ENGINEERING CONSULTA9605202/14/2023
Building Lifecycle
All (85)Filed (19)Permit Issued (12)Signed Off (8)Violation (4)Inspection (10)Objection (2)Special Inspection (30)
05/06/2025
Signed off — Alteration
B00661635-I1
02/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JAMES CHUN
02/20/2025
Special inspection requirement — Fenestration areas
JAMES CHUN
02/20/2025
Special inspection requirement — Maintenance information
JAMES CHUN
02/20/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
JAMES CHUN
02/20/2025
Special inspection requirement — Fenestration air leakage
JAMES CHUN
02/20/2025
Special inspection requirement — Fire-Resistance Rated Construction
JAMES CHUN
02/20/2025
Special inspection requirement — Insulation placement and R values
JAMES CHUN
02/20/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
JAMES CHUN
02/20/2025
Special inspection requirement — Energy Code Compliance Inspections
JAMES CHUN
02/20/2025
Special inspection requirement — Air barrier — testing
JAMES CHUN
02/20/2025
Special inspection requirement — Air barrier - visual inspection
JAMES CHUN
02/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
JAMES CHUN
02/20/2025
Special inspection requirement — Interior lighting power
JAMES CHUN
02/20/2025
Special inspection requirement — Permanent certificate
JAMES CHUN
02/20/2025
Special inspection requirement — Metering
JAMES CHUN
02/20/2025
Special inspection requirement — Lighting in dwelling units
JAMES CHUN
02/20/2025
Special inspection requirement — Electric vehicle service equipment requirements
JAMES CHUN
02/12/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
B00660801-P4
02/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NANIK MASSAND
02/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
02/12/2025
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
02/12/2025
Special inspection requirement — Metering
NANIK MASSAND
02/12/2025
Special inspection requirement — Maintenance information
NANIK MASSAND
02/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
02/12/2025
Special inspection requirement — Air barrier - visual inspection
NANIK MASSAND
02/12/2025
Special inspection requirement — Permanent certificate
NANIK MASSAND
02/12/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
NANIK MASSAND
02/12/2025
Special inspection requirement — Air barrier — testing
NANIK MASSAND
02/12/2025
Special inspection requirement — Electric vehicle service equipment requirements
NANIK MASSAND
02/12/2025
Special inspection requirement — Insulation placement and R values
NANIK MASSAND
02/12/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
NANIK MASSAND
02/06/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/10/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
12/17/2024
Signed off — Alteration
Plumbing filed in conjunction with ALT I B00660801
B00661658-I1
12/04/2024
Signed off — Alteration
Filed herein in conjunction with alt I B00660801-I1
B00854874-I1
11/26/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
B00660801-P3
11/22/2024
Filed — Alteration
Filed herein in conjunction with alt I B00660801-I1
B00854874-P1
10/30/2024
Filed — Alteration
Plumbing filed in conjunction with ALT I B00660801
B00661658-P3
10/07/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/03/2024
Signed off — Alteration
B00765212-I1
10/01/2024
Signed off — Alteration
TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT I APPLICATION B00660801
B00661656-I1
09/10/2024
Signed off — Alteration
SOE FILING IN CONJUNCTION WITH DOB APPLICATION B00660801.NO CHANGE IN USE, EXITS OR OCCUPANCY.
B00765217-I1
09/05/2024
Permit issued — Support of Excavation
B00765217-I1-SE
09/04/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
B00660801-P2
08/27/2024
Permit issued — Plumbing
B00661658-I1-PL
08/26/2024
Filed — Alteration
Plumbing filed in conjunction with ALT I B00660801
B00661658-P2
07/30/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/25/2024
Permit issued — Sprinklers
B00854874-I1-EW-SP
07/25/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/19/2024
Signed off — Alteration
B00906149-I1
05/09/2024
Permit issued — Sprinklers
B00854874-I1-EW-SP
04/17/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
B00660801-P1
02/26/2024
Permit issued — Mechanical Systems
B00661635-I1-MS
12/14/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/16/2023
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
11/16/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/04/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/15/2023
Permit issued — Sprinklers
B00854874-I1-EW-SP
09/01/2023
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
Latest 60 of 85 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupport of ExcavationSigned-offCLASSIC BUILDERS CORP09/05/2024
DOB NOWPlumbingSigned-offORBIT PLBG & HTG INC08/27/2024
DOB NOWSprinklersSigned-offWIZ FIRE SPRINKLERS LLC07/25/2024
DOB NOWSprinklersSigned-offWIZ FIRE SPRINKLERS LLC05/09/2024
DOB NOWMechanical SystemsSigned-offCLASSIC BUILDERS CORP02/26/2024
DOB NOWSprinklersSigned-offWIZ FIRE SPRINKLERS LLC09/15/2023
DOB NOWPlumbingSigned-offORBIT PLBG & HTG INC07/28/2023
DOB NOWProtection and Mechanical MethodsSigned-offJ & G CONSTRUCTION SVCS07/19/2023
DOB NOWGeneral ConstructionPermit IssuedCLASSIC BUILDERS CORP07/13/2023
DOB NOWFoundationSigned-offCLASSIC BUILDERS CORP05/04/2023
DOB NOWStructuralSigned-offCLASSIC BUILDERS CORP05/03/2023
DOB NOWConstruction FenceSigned-offCLASSIC BUILDERS CORP03/29/2023
BISOTISSUEDMILRO SERVICES,INC08/08/2020
BISPLISSUEDJ G BATTISTA PLUMBING & HEAT05/14/1999
BISOTISSUEDDBA-PRIMO GNRL CONTR03/30/1999
2 projects · most recent 11/13/2024
General Wiring
FiledStatusContractorScope
11/13/2024CompleteB.P. ELECTRIC CORPGeneral Wiring
08/14/2020CompleteMCDOUGALL ELECTRIC, INC.General Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
02/06/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/10/2025Fail-Final CND-Occupancy InspectionFailView ↗
10/07/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/30/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/25/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/14/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/16/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
11/16/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/04/2023Pass-Final CND-Occupancy InspectionPassView ↗
09/01/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 84
DateRequirementInspectorRole
02/20/2025Structural Stability – Alterations of existing buildingsJAMES CHUNspecial
02/20/2025Maintenance informationJAMES CHUNenergy_progress
02/20/2025Fenestration and door U-factor and product ratingsJAMES CHUNenergy_progress
02/20/2025Fenestration areasJAMES CHUNenergy_progress
02/20/2025Electric vehicle service equipment requirementsJAMES CHUNenergy_progress
02/20/2025Insulation placement and R valuesJAMES CHUNenergy_progress
02/20/2025Air barrier - visual inspectionJAMES CHUNenergy_progress
02/20/2025Interior lighting powerJAMES CHUNenergy_progress
02/20/2025Lighting in dwelling unitsJAMES CHUNenergy_progress
02/20/2025MeteringJAMES CHUNenergy_progress
02/20/2025Air barrier — testing JAMES CHUNenergy_progress
02/20/2025Fenestration air leakageJAMES CHUNenergy_progress
02/20/2025Permanent certificateJAMES CHUNenergy_progress
02/20/2025Fire-Resistance Rated ConstructionJAMES CHUNprogress
02/20/2025Energy Code Compliance InspectionsJAMES CHUNprogress
02/20/2025Exterior Insulation and Finish Systems (EIFS)JAMES CHUNspecial
02/20/2025Fire-Resistant Penetrations and JointsJAMES CHUNspecial
02/12/2025Lighting in dwelling unitsNANIK MASSANDenergy_progress
02/12/2025Exterior Insulation and Finish Systems (EIFS)NANIK MASSANDspecial
02/12/2025Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
02/12/2025Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
02/12/2025Energy Code Compliance InspectionsNANIK MASSANDprogress
02/12/2025Fire-Resistance Rated ConstructionNANIK MASSANDprogress
02/12/2025Permanent certificateNANIK MASSANDenergy_progress
02/12/2025Fenestration areasNANIK MASSANDenergy_progress
Latest 25 of 84.
▾Documents — 196 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch18
08/29/2026B00765207-I1Request digital key ↗
08/27/2026B00661656-I1Request digital key ↗
08/27/2026B00661658-I1Request digital key ↗
Showing 3 of 18 on file for this type
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION3
02/26/2024340876449Open ↗
07/16/2020340724238Open ↗
04/15/2020340724238Open ↗
▸BISWORK PERMIT APPLICATION1
08/08/2020340724238Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
01/30/2024340876449Open ↗
▸BISBPP-DOT: SIDEWALK/CURB/ROAD WORK PERMITS1
04/17/2025340876449Open ↗
▸Zoning, Tax Lot & Property Records13
▸DOB NOWZD1: DOB Zoning Diagram5
08/13/2026B00660801-P1Open ↗
08/13/2026B00660801-P3Open ↗
08/13/2026B00660801-P4Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/13/2026B00660801-I1Open ↗
08/13/2026B00660801-P2Open ↗
08/13/2026B00660801-P3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWRestrictive Declaration/Easement 12
08/13/2026B00660801-I1Open ↗
08/13/2026B00660801-P4Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00660801-I1Open ↗
▸Seals & Professional Certifications80
▸DOB NOWProgress Inspector Seal & Signature38
09/30/2026B00661658-P3Open ↗
09/30/2026B00661658-P3Open ↗
08/28/2026B00660801-P4Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature21
09/30/2026B00661658-P3Open ↗
09/30/2026B00661658-P3Open ↗
09/02/2026B00765217-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature18
08/29/2026B00765217-I1Open ↗
08/27/2026B00661658-P3Open ↗
08/27/2026B00661658-P2Open ↗
Showing 3 of 18 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
01/30/2024340876449Open ↗
04/15/2020340724238Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/26/2024340876449Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/13/2026B00660801-P2Open ↗
08/13/2026B00660801-P1Open ↗
08/13/2026B00660801-I1Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection8
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
04/03/2024340876449Open ↗
▸BISBPP: STREET TREES SITE PLAN1
04/03/2024340876449Open ↗
▸BISSTREET TREE CHECKLIST1
01/30/2024340876449Open ↗
▸BISSTREET TREE SIGNOFF1
04/17/2025340876449Open ↗
▸BISSTREET TREES SITE PLAN1
04/17/2025340876449Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00660801-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00660801-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00660801-I1Open ↗
▸Environmental & Asbestos17
▸DOB NOWDEP ACP-5: Asbestos Assessment Report15
08/27/2026B00661658-P3Open ↗
08/27/2026B00661658-P2Open ↗
08/27/2026B00661658-P1Open ↗
Showing 3 of 15 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
07/23/2020340724238Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/26/2024340876449Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
12/17/2021340724238Open ↗
12/13/2021340724238Open ↗
08/08/2020340724238Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
12/13/2021340724238Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026B00660801-I1Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY5
12/17/2021340724238Open ↗
12/13/2021340724238Open ↗
08/08/2020340724238Open ↗
Showing 3 of 5 on file for this type
▸BISBPP: FIELD INSPECTION1
04/17/2025340876449Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/20/2021340724238Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
04/17/2025340876449Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT2
08/04/2020340724238Open ↗
07/16/2020340724238Open ↗
▸BISBPP-11 - Affidavit as to Roadway Pavement And/Or Sidewalk and Curb Construction1
04/28/2025340876449Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
12/13/2021340724238Open ↗
▸BISBPP: ENGINEERS AFFIDAVIT1
05/12/2025340876449Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION3
08/04/2020340724238Open ↗
07/30/2020340724238Open ↗
07/23/2020340724238Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
02/26/2024340876449Open ↗
04/15/2020340724238Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/26/2024340876449Open ↗
▸Other Documents24
▸DOB NOWSite Survey: Initial5
08/13/2026B00660801-I1Open ↗
08/13/2026B00660801-P1Open ↗
08/13/2026B00660801-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/13/2026B00660801-P2Open ↗
08/13/2026B00660801-P3Open ↗
08/13/2026B00660801-P4Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/23/2026B00660801-P3Open ↗
08/23/2026B00660801-P2Open ↗
08/23/2026B00660801-P1Open ↗
Showing 3 of 5 on file for this type
▸BISBPP: FINAL AS-BUILT PHOTOGRAPHS1
04/17/2025340876449Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
04/03/2024340876449Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
04/03/2024340876449Open ↗
▸BISBPP: AS-BUILT SIDEWALK SURVEY1
04/17/2025340876449Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
04/28/2025340876449Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
04/03/2024340876449Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00660801-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/15/2026B00765217-I1Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026B00660801-I1Open ↗