| Owner | Filings | Most Recent |
|---|---|---|
| XTREME HOMECARE SERVICES LLC | 8 | 07/08/2026 |
| AXIUM CONSTRUCTION | 35 | 07/08/2026 |
| IMMANUEL INC | 5 | 03/22/2026 |
| NB PLAZA PROPERTY LLC | 2 | 03/22/2026 |
| TO THE OWNER OF 213-03 NO | 1 | 03/22/2026 |
| INNO ASSET CORP | 1 | 03/22/2026 |
| OXFORD FINE PROPERTIES | 68 | 03/21/2026 |
| ALLIED PROPERTIES | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/17/2023 | $13.6M | — | 21311 NORTHERN BLVD LLC → NB PLAZA PROPERTY LLC | $347/sf building |
| 10/22/2018 | $5.6M | — | E&H BAYSIDE LLC → 21311 NORTHERN BLVD LLC | $143/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BASIC GROUPS CORP | 7 | 05/21/2024 |
| NA | 5 | 03/21/2024 |
| PROSPECT ENGINEERING P.C | 1 | 01/22/2024 |
| ALL CITY ENGINEERING, P.C. | 1 | 12/20/2023 |
| JUNG H. CHOI, ARCHITECT, PC | 2 | 07/06/2023 |
| LUCID BUILDING ENGINEERING P.C. | 1 | 04/24/2023 |
| MARTIN A. PASSANTE ARCHITECT | 3 | 04/21/2023 |
| DIMENSIONS ENGINEER SERVICE | 1 | 03/24/2022 |
| LILKER ASSOCIATES CONSULTING ENGINE | 4 | 03/10/2020 |
| HC ARCHITECT, PC | 2 | 12/10/2019 |
| ALLEN SHINFELD, P.E. PLLC | 1 | 01/28/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| BASIC GROUPS | 14 | 03/21/2026 |
| BUILD TEAM | 10 | 03/21/2026 |
| AXIUM CONSTRUCTION | 6 | 03/21/2026 |
| BMB BUILDING CONSULTING | 2 | 03/21/2026 |
| JP EXPEDITE | 4 | 03/21/2026 |
| BURNHAM NATIONWIDE INC | 4 | 03/21/2026 |
| YOUN DESIGN CORP | 2 | 03/21/2026 |
| DOMANI CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PIPESTYLISTS, INC | Plumbing | 6 | 07/08/2026 |
| AXIUM CONSTRUCTION CORP | General Contractor | 4 | 03/21/2026 |
| STEEL TONE CONSTRUCTION | General Contractor | 4 | 07/08/2026 |
| ALMONTE HOME IMPROVEMENTS | General Contractor | 3 | 03/21/2026 |
| CITY STONE WORLD INC | General Contractor | 2 | 03/21/2026 |
| WESTERN HOUSE CONSTRUCT | General Contractor | 2 | 03/21/2026 |
| DIMEX GROUP INC | General Contractor | 2 | 03/21/2026 |
| SIGNS CAD | Scaffold | 2 | 07/08/2026 |
| UNITECH DESIGN | Scaffold | 1 | 07/08/2026 |
| AHEARN-HOLTZMAN, INC | General Contractor | 1 | 03/22/2026 |
| CAPITAL BUILDERS GROUP INC | General Contractor | 1 | 07/08/2026 |
| INTEGRA PLUMBING OF N.Y | Plumbing | 1 | 07/08/2026 |
| RITE WAY HEATING CORP | Plumbing | 1 | 07/08/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| R G M SIGNS | Scaffold | 1 | 07/08/2026 |
| ALLSTATE SPRINKLER LLC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ANDREW GOODRICH, P.E., PL | 965 | 7 | 05/21/2024 |
| HSU & ASSOCIATES | 8025 | 5 | 03/21/2024 |
| ALL CITY ENGINEERING PC | 7115 | 1 | 12/20/2023 |
| JUNG H CHOI ARCHITECT | 3020 | 2 | 07/06/2023 |
| LILKER ASSOCIATES CONSULT | 816 | 4 | 03/10/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | ALMONTE HOME IMPROVEMENTS | 01/24/2024 |
| DOB NOW | Sign | Signed-off | UNITECH DESIGN INC | 01/24/2024 |
| DOB NOW | Plumbing | Signed-off | T & T PLUMBING INC | 12/18/2023 |
| DOB NOW | General Construction | Signed-off | CITY STONE WORLD | 12/15/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CAPITAL BUILDERS GROUP IN | 07/29/2023 |
| DOB NOW | General Construction | Signed-off | STEEL TONE CONSTRUCTION | 07/13/2023 |
| DOB NOW | General Construction | Permit Issued | AXIUM CONSTRUCTION | 06/12/2023 |
| DOB NOW | Sign | Signed-off | R.G.M. SIGNS INC | 06/01/2023 |
| DOB NOW | Plumbing | Signed-off | T & T PLUMBING INC | 05/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | STEEL TONE CONSTRUCTION | 05/08/2023 |
| DOB NOW | Plumbing | Signed-off | LS PLUMBING CORP | 04/26/2023 |
| DOB NOW | General Construction | Permit Issued | WESTERN HOUSE CONSTRUCT | 04/10/2023 |
| DOB NOW | Plumbing | Permit Issued | T & T PLUMBING INC | 04/05/2023 |
| DOB NOW | General Construction | Signed-off | DIMEX GROUP INC | 03/29/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | STEEL TONE CONSTRUCTION | 03/23/2023 |
| DOB NOW | General Construction | Permit Issued | AXIUM CONSTRUCTION | 06/13/2022 |
| DOB NOW | Sprinklers | Signed-off | ALLSTATE SPRINKLER LLC | 12/31/2019 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 12/12/2019 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 12/11/2019 |
| DOB NOW | Plumbing | Permit Issued | INTEGRA PLUMBING OF N.Y | 11/08/2019 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 04/08/2019 |
| BIS | OT | ISSUED | KENAN SIGN & AWNING CORP | 06/28/2020 |
| BIS | OT | ISSUED | CAPITAL BUILDERS GROUP INC | 10/21/2019 |
| BIS | OT | ISSUED | AXIUM CONSTRUCTION CORP | 08/01/2019 |
| BIS | FP | ISSUED | METFLOW FIRE CONTROL LLC | 05/29/2019 |
| BIS | MH | ISSUED | KENAN SIGN & AWNING CORP | 05/13/2019 |
| BIS | OT | ISSUED | AXIUM CONSTRUCTION CORP | 07/19/2018 |
| BIS | PL | ISSUED | EP PLUMBING INC | 05/25/2018 |
| BIS | OT | ISSUED | AXIUM CONSTRUCTION CORP | 04/27/2018 |
| BIS | OT | ISSUED | ALL AIR SYSTEMS INC | 02/26/2018 |
| BIS | — | ISSUED | UNITECH DESIGN INC | 12/04/2012 |
| BIS | — | ISSUED | A.M.A HOLDINGS INC | 10/24/2012 |
| BIS | SP | ISSUED | DC BUILDING SERVICES INC | 10/11/2011 |
| BIS | PL | ISSUED | DC BUILDING SERVICES INC | 10/11/2011 |
| BIS | MH | ISSUED | LEE & COMPANY OF NY, INC | 09/29/2011 |
| BIS | — | ISSUED | BOLD & BOLT VISUAL, CORP | 02/08/2011 |
| BIS | SP | ISSUED | PLUMBING & HTG DOCTOR INC | 10/28/2010 |
| BIS | PL | ISSUED | PLUMBING & HTG DOCTOR INC | 10/28/2010 |
| BIS | OT | ISSUED | NUGEN CONSTRUCTION CORP | 10/13/2010 |
| BIS | OT | ISSUED | NUGEN CONSTRUCTION CORP | 09/21/2010 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2019 | Permit Issued | INTEGRA PLUMBING OF N.Y | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/23/2024 | Complete | ATMOS ELECTRIC SVCE CORP | — |
| 12/05/2023 | Complete | ERIC & NG ELEC'L, INC. | General Wiring |
| 06/20/2023 | Complete | KJK ELECTRIC INC | General Wiring |
| 05/03/2023 | Complete | A ELECTRICAL MAIN SVC INC | — |
| 12/19/2019 | Complete | AMPERE ELECL SERVICES COR | — |
| 12/19/2019 | Complete | AMPERE ELECL SERVICES COR | — |
| 10/28/2019 | Complete | AMP-RITE ELEC. INC. | General Wiring |
| 10/28/2019 | Complete | AMP-RITE ELEC. INC. | 1 meters |
| 05/03/2019 | Complete | R.J.ELECTRICAL CONTRACTOR | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/19/2024 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 04/01/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/25/2024 | Fail-Final Sign Permit Inspection | Fail | View ↗ |
| 03/21/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/20/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/29/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/17/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/21/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/25/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/22/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/21/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/25/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/25/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/22/2024 | Mechanical Systems | ANDREW GOODRICH | special |
| 05/22/2024 | Fire-Resistant Penetrations and Joints | ANDREW GOODRICH | special |
| 05/22/2024 | Maintenance information | ANDREW GOODRICH | energy_progress |
| 05/22/2024 | HVAC-R and service water heating system controls | ANDREW GOODRICH | energy_progress |
| 05/22/2024 | Duct leakage testing, insulation and design | ANDREW GOODRICH | energy_progress |
| 05/22/2024 | HVAC-R and service water heating equipment | ANDREW GOODRICH | energy_progress |
| 05/22/2024 | HVAC-R and service water piping design and insulation | ANDREW GOODRICH | energy_progress |
| 05/22/2024 | Fire-Resistance Rated Construction | ANDREW GOODRICH | progress |
| 05/22/2024 | Energy Code Compliance Inspections | ANDREW GOODRICH | progress |
| 05/22/2024 | Final | ANDREW GOODRICH | progress |
| 03/20/2024 | Energy Code Compliance Inspections | Chih Hsu | progress |
| 03/20/2024 | Fire-Resistance Rated Construction | Chih Hsu | progress |
| 03/20/2024 | Structural Steel - Details | Chih Hsu | special |
| 03/20/2024 | Final | Chih Hsu | progress |
| 03/20/2024 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 03/20/2024 | Structural Cold-Formed Steel | Chih Hsu | special |
| 03/14/2024 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 03/07/2024 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 02/07/2024 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 01/09/2024 | Final | JUSTIN KIM | progress |
| 12/19/2023 | HVAC-R and service water piping design and insulation | Liangkai Xia | energy_progress |
| 12/19/2023 | HVAC-R and service water heating system controls | Liangkai Xia | energy_progress |
| 12/19/2023 | HVAC-R and service water heating equipment | Liangkai Xia | energy_progress |
| 12/19/2023 | Maintenance information | Liangkai Xia | energy_progress |
| 12/13/2023 | Final | Liangkai Xia | progress |