← Back
Office, 20+ stories, with or without commercial
2 World Financial Center
225 LIBERTY STREET · BIN 1000058
💬 Discuss this project
1987Year Built
44Stories
O4Building Class
BPCZoning
2,267,925 sfGross Floor Area
1Units
LL97 Covered0 Open ViolationsFISP: SWARMPFDNY Report ↗
Office, 20+ stories, with or without commercial · Owner of record: WFP TOWER B CO LP · 199,346 sf lot · 11.38 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction12p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 19 docs
Penthouse2p · 2 filings · 20 docs
Floor 447p · 4 filings · 20 docs
Floor 4331p · 9 filings · 20 docs
Floor 4238p · 18 filings · 20 docs
Floor 4113p · 11 filings · 20 docs
Floor 4018p · 10 filings · 20 docs
Floor 3915p · 7 filings · 20 docs
Floor 3815p · 8 filings · 20 docs
Floor 378p · 4 filings · 20 docs
Floor 368p · 5 filings · 20 docs
Floor 35Under Construction43p · 4 filings · 20 docs
Floor 341p · 1 filing · 10 docs
Floor 33Under Construction13p · 1 filing · 17 docs
Floor 32Under Construction17p · 2 filings · 20 docs
Floor 31Under Construction15p · 2 filings · 20 docs
Floor 306p · 3 filings · 20 docs
Floor 29Under Construction36p · 6 filings · 20 docs
Floor 287p · 4 filings · 20 docs
Floor 27Under Construction10p · 4 filings · 20 docs
Floor 26Under Construction9p · 3 filings · 20 docs
Floor 251p · 2 filings · 9 docs
Floor 24
Floor 2312p · 3 filings · 20 docs
Floor 227p · 3 filings · 20 docs
Floor 21Under Construction31p · 1 filing · 15 docs
Floor 204p · 2 filings · 20 docs
Floor 19Under Construction38p · 2 filings · 20 docs
Floor 18Under Construction39p · 3 filings · 20 docs
Floor 17Under Construction37p · 2 filings · 20 docs
Floor 16Under Construction31p · 1 filing · 15 docs
Floor 151p · 1 filing · 1 doc
Floor 14
Floor 13
Floor 1210p · 9 filings · 20 docs
Floor 11Under Construction69p · 4 filings · 20 docs
Floor 10Under Construction85p · 12 filings · 20 docs
Floor 9Under Construction81p · 5 filings · 20 docs
Floor 8Under Construction82p · 4 filings · 20 docs
Floor 7Under Construction61p · 3 filings · 20 docs
Floor 6Under Construction65p · 6 filings · 20 docs
Floor 5Under Construction35p · 3 filings · 20 docs
Floor 4Under Construction36p · 5 filings · 20 docs
Floor 311p · 6 filings · 20 docs
Floor 2111p · 20 filings · 20 docs
Floor 1124p · 21 filings · 20 docs
CellarUnder Construction37p · 7 filings · 20 docs
Sub-Cellar9p · 6 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BROOKFIELD PROPERTIES OPERATED BY C27409/13/2026
BROOKFIELD PROPERTIES MG LLC82407/08/2026
COMMERZ BANK507/08/2026
PLATINUM SERVICES NY807/08/2026
WFP TOWER B CO L P54903/22/2026
WFP TOWER B CO LP WFP TOW203/22/2026
WFP TOWER BCO LP 3 WORLD103/22/2026
WKP TOWER B CO LP103/22/2026
WFP TOWERS B CO LP303/22/2026
WFP TOWER B CO.L.P.503/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
WILLIAM VITACCO ASSOCIATES29803/21/2026
MUNICIPAL BUILDING CONSULTANTS5703/21/2026
DVA Advisors3603/21/2026
LOUIS STRIAR1403/21/2026
AGOUTI CONSTRUCTION CONSULTING403/21/2026
OUTSOURCE CONSULTANTS, INC.703/21/2026
A1 EXPEDITING SERVICE CORP.6403/21/2026
PLATINUM SERVICES NY403/21/2026
ARUP303/21/2026
PINNACLE BUILDING CON203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUMMIT INTERIORS, INCGeneral Contractor9007/08/2026
WINICK PRODUCTIONS, LLCGeneral Contractor3207/08/2026
TURNER CONSTRUCTION COMPANYGeneral Contractor2207/08/2026
JRM CONSTRUCTION MGMT LLCGeneral Contractor2207/08/2026
ABCO-PEERLESS SPRKLR CORPFire Protection2107/08/2026
TULLA CONTRACTING CORPGeneral Contractor2007/08/2026
CLUNE CONSTRUCTION CO LPGeneral Contractor1707/08/2026
SIRINA FIRE PROT CORPFire Protection1607/08/2026
MAC FELDER INCPlumbing1607/08/2026
PAR FIRE PROTECTION LLCFire Protection1407/08/2026
GLOBAL FACILITY MANAGEMENTGeneral Contractor1307/08/2026
JOHN GALLIN & SON, INCGeneral Contractor1007/08/2026
PAR PLUMBING CO., INCPlumbing1007/08/2026
AGGRESSIVE FIRE PROT LLCFire Protection907/08/2026
ICON INTERIORS INCGeneral Contractor807/08/2026
QUEST BUILDERS GROUP INCGeneral Contractor803/21/2026
EVERGREEN MECHANICAL CORPPlumbing807/08/2026
SHAWMUT WOODWORKING & SUPPLYGeneral Contractor707/08/2026
M&T PLBG AND HTG CO., INCPlumbing707/08/2026
LAB PLBG & HTG CO INCPlumbing607/08/2026
BENJAMIN GROUP ENTERPRISGeneral Contractor507/08/2026
TRU-ART SIGNScaffold507/08/2026
ASHLAR MECHANICAL CORPFire Protection507/08/2026
BNF CONTRACTORS INCGeneral Contractor403/21/2026
BENCHMARK BUILDERS LLCGeneral Contractor407/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PROJECT TACTICAL SOLUTION58591508/20/2026
ALAN MARGOLIN & ASSOC4232508/06/2026
JS BUILDING CONSULTING4959306/11/2026
DKA CONSULTING PC3150206/11/2026
OUTSOURCE SPECIAL INSPECT28277504/27/2026
ROSINI ENGINEERING, PC3282201/09/2026
BIG APPLE GROUP NY A RMA9168110/16/2025
CHARLES G MICHEL ENGINEER2871310/06/2025
AK ENGINEERING PC6781509/25/2025
WB ENGINEERING533507/03/2025
Building Lifecycle
All (300)Filed (64)Permit Issued (77)Signed Off (38)Inspection (60)Objection (31)Special Inspection (30)
09/10/2026
Signed off — Alteration
Relocation of Fire Department valve cabinet.
M01337713-S3
08/24/2026
Special inspection requirement — Post-installed Anchors
Max Lee
08/24/2026
Special inspection requirement — HVAC-R and service water heating system controls
Max Lee
08/24/2026
Special inspection requirement — Lighting controls
Max Lee
08/24/2026
Special inspection requirement — Final
Max Lee
08/24/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Max Lee
08/24/2026
Special inspection requirement — Mechanical Systems
Max Lee
08/24/2026
Special inspection requirement — Duct leakage testing, insulation and design
Max Lee
08/24/2026
Special inspection requirement — Interior lighting power
Max Lee
08/24/2026
Special inspection requirement — HVAC-R and service water heating equipment
Max Lee
08/21/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/21/2026
Objection resolved — Resolved
08/20/2026
Filed — Alteration
Relocation of Fire Department valve cabinet.
M01337713-P1
08/18/2026
Signed off — Alteration
Relocation of Fire Department valve cabinet.
M01337713-S2
08/18/2026
Signed off — Alteration
Interior demo of 1st floor existing mechanical equipment associated controls, ductwork and piping. No change in use, egress or occupancy.
M01261578-S1
08/18/2026
Signed off — Alteration
Interior demo of 1st floor existing mechanical equipment associated controls, ductwork and piping. No change in use, egress or occupancy.
M01261578-S3
08/18/2026
Signed off — Alteration
Interior demo of 1st floor existing mechanical equipment associated controls, ductwork and piping. No change in use, egress or occupancy.
M01261578-S2
08/17/2026
Signed off — Alteration
M01350534-I1
08/12/2026
Filed — No Work
M01427146-I1
08/12/2026
Filed — No Work
M01427149-I1
08/12/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/12/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/12/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
08/07/2026
Permit issued — Sign
M01422060-I1-SG
08/07/2026
Special inspection requirement — Sprinkler Systems
Max Lee
08/07/2026
Special inspection requirement — Post-installed Anchors
Max Lee
08/07/2026
Special inspection requirement — Standpipe Systems
Young Suh
08/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
08/07/2026
Special inspection requirement — Post-installed Anchors
Young Suh
08/06/2026
Signed off — Alteration
HEAVY DUTY SIDEWALK SHED DURING GENERAL CONSTRUCTION WORK FILED SEPARATELY UNDER APPLICATION # M01066237. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M01328642-S1
08/06/2026
Signed off — Alteration
HEAVY DUTY SIDEWALK SHED DURING GENERAL CONSTRUCTION WORK FILED SEPARATELY UNDER APPLICATION # M01066237. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M01328642-I1
08/06/2026
Filed — Alteration
Mechanical work as shown on plans for Space 127. No change in use, egress or occupancy.
M01292279-P1
08/06/2026
Special inspection requirement — Sprinkler Systems
Young Suh
08/06/2026
Special inspection requirement — Post-installed Anchors
Young Suh
08/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
08/05/2026
Filed — Alteration
Mechanical work as shown on plans for Space 127. No change in use, egress or occupancy.
M01292279-P4
08/05/2026
Filed — Alteration
REPLACE 2 ILLUMINATED ACCESSORY BUSINESS WALL SIGNS FOR OMEGA.
M01422060-I1
08/04/2026
Filed — Alteration
Mechanical work as shown on plans for Space 127. No change in use, egress or occupancy.
M01292279-P5
07/30/2026
Signed off — Alteration
Interior demo of 1st floor existing mechanical equipment associated controls, ductwork and piping. No change in use, egress or occupancy.
M01261578-I1
07/29/2026
Signed off — Alteration
M01324246-I1
07/27/2026
Filed — Alteration
Relocation of Fire Department valve cabinet.
M01337713-P2
07/21/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/16/2026
Permit issued — Sign
M01426217-I1-SG
07/16/2026
Objection raised — Scope
07/16/2026
Objection raised — Scope
07/16/2026
Objection raised — Fire_Protection
07/16/2026
Objection raised — Scope
07/16/2026
Objection raised — Scope
07/16/2026
Objection raised — Fire_Protection
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSignPermit IssuedNATIONAL MAINTENANCE, INC08/07/2026
DOB NOWSignSigned-offACTIVE SIGNS INC07/16/2026
DOB NOWConstruction FencePermit IssuedAURORA CONTRACTORS INC07/02/2026
DOB NOWSprinklersPermit IssuedPAR FIRE PROTECTION LLC06/23/2026
DOB NOWGeneral ConstructionPermit IssuedCREATIVE INSTALLATIONS IN06/17/2026
DOB NOWMechanical SystemsPermit IssuedCREATIVE INSTALLATIONS IN06/15/2026
DOB NOWPlumbingPermit IssuedMAC FELDER INC05/15/2026
DOB NOWPlumbingPermit IssuedMAC FELDER INC05/15/2026
DOB NOWStandpipePermit IssuedARCHER CONSULTANTS GROUP05/14/2026
DOB NOWSprinklersPermit IssuedARCHER CONSULTANTS GROUP05/14/2026
DOB NOWSprinklersPermit IssuedARCHER CONSULTANTS GROUP05/14/2026
DOB NOWGeneral ConstructionPermit IssuedTURNER CONSTRUCTION COMPANY04/24/2026
DOB NOWStructuralPermit IssuedTURNER CONSTRUCTION COMPANY04/21/2026
DOB NOWGeneral ConstructionPermit IssuedTURNER CONSTRUCTION COMPANY04/16/2026
DOB NOWMechanical SystemsPermit IssuedTURNER CONSTRUCTION COMPANY04/16/2026
DOB NOWStructuralPermit IssuedTURNER CONSTRUCTION COMPANY04/16/2026
DOB NOWGeneral ConstructionPermit IssuedSUMMIT INTERIORS, INC04/15/2026
DOB NOWPlumbingSigned-offMAC FELDER INC04/06/2026
DOB NOWPlumbingPermit IssuedMAC FELDER INC04/02/2026
DOB NOWMechanical SystemsPermit IssuedTURNER CONSTRUCTION COMPANY03/23/2026
DOB NOWMechanical SystemsPermit IssuedTURNER CONSTRUCTION COMPANY03/12/2026
DOB NOWGeneral ConstructionSigned-offTURNER CONSTRUCTION COMPANY03/12/2026
DOB NOWGeneral ConstructionSigned-offTURNER CONSTRUCTION COMPANY03/12/2026
DOB NOWMechanical SystemsPermit IssuedCONSTRUCTION MANAGEMENT &03/04/2026
DOB NOWSprinklersPermit IssuedSEAN COAKLEY P & H INC03/03/2026
DOB NOWStandpipeSigned-offABCO-PEERLESS SPRKLR CORP02/27/2026
DOB NOWSprinklersSigned-offABCO-PEERLESS SPRKLR CORP02/27/2026
DOB NOWSprinklersSigned-offABCO-PEERLESS SPRKLR CORP02/27/2026
DOB NOWPlumbingPermit IssuedSEAN COAKLEY P & H INC02/26/2026
DOB NOWSprinklersSigned-offABCO-PEERLESS SPRKLR CORP02/25/2026
DOB NOWStandpipeSigned-offABCO-PEERLESS SPRKLR CORP02/25/2026
DOB NOWStructuralSigned-offICON INTERIORS INC02/09/2026
DOB NOWStandpipeSigned-offAGGRESSIVE FIRE PROT LLC01/29/2026
DOB NOWPlumbingSigned-offPAR PLUMBING CO., INC01/28/2026
DOB NOWSprinklersSigned-offAGGRESSIVE FIRE PROT LLC01/28/2026
DOB NOWGeneral ConstructionPermit IssuedCONSTRUCTION MANAGEMENT &01/27/2026
DOB NOWMechanical SystemsPermit IssuedICON INTERIORS INC01/16/2026
DOB NOWSprinklersSigned-offASHLAR MECHANICAL CORP01/12/2026
DOB NOWGeneral ConstructionSigned-offICON INTERIORS INC01/09/2026
DOB NOWGeneral ConstructionSigned-offTULLA CONTRACTING CORP01/08/2026
+ 60 more permits on file
5 projects · most recent 08/06/2026
Heating and Air Conditioning Systems Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/06/2026Permit IssuedSHAWMUT WOODWORKING & SUPHeating and Air Conditioning Systems
Heat / Cool
Above Air MCC-011X1-1-0000-EC-00-UF2-XS 1,474 CFM · Crac Unit ×2
02/09/2026Signed-offTURNER CONSTRUCTION COMPAHeating and Air Conditioning Systems
Heat / Cool
Superior Rex RAHC-A-06 13,826 BTU · Fan Coil Indoor ×9
RAHC-A-12 25,383 BTU · Fan Coil Indoor ×4
SBVD08 11,500 BTU · Fan Coil Indoor ×4
RAHC-A-16 292,000 BTU · Fan Coil Indoor ×1
RAHC06 13,826 BTU · Fan Coil Indoor ×1
SBVD12 20,543 BTU ×1
SBVD20 45,909 BTU · Fan Coil Indoor ×1
SDVD12 25,043 BTU · Fan Coil Indoor ×1
07/03/2025Permit IssuedJOHN GALLIN & SON, INCAir Conditioning Systems
Cooling
Vertiv MMD40C3AR0D2S693 23,400 BTU · Crac Unit ×4
03/14/2025Signed-offWOLF CONSTRUCTION CORP 20Air Conditioning Systems
Cooling
12/21/2024Permit IssuedTIMBIL MECHANICAL, LLCHeating Systems, Ventilation Systems—
12 projects · most recent 08/20/2026
Sprinkler System
FiledStatusContractorScope
08/20/2026Signed-offAGGRESSIVE FIRE PROT LLCSprinkler System
08/06/2026Signed-offCMA PLUMBING & HEATING INSprinkler System
06/11/2026Permit IssuedPAR FIRE PROTECTION LLC20 heads
04/27/2026Permit IssuedARCHER CONSULTANTS GROUP885 heads
02/09/2026Signed-offABCO-PEERLESS SPRKLR CORPSprinkler System
01/09/2026Permit IssuedSEAN COAKLEY P & H INC57 heads
01/07/2026Signed-offASHLAR MECHANICAL CORPSprinkler System
11/21/2025Signed-offABCO-PEERLESS SPRKLR CORPSprinkler System
10/15/2025Permit IssuedCMA PLUMBING & HEATING INSprinkler System
07/03/2025Permit IssuedSIRINA FIRE PROT CORPSprinkler System
03/14/2025Signed-offDENKO MECHANICAL INCSprinkler System
03/22/2023Permit IssuedM&T PLBG AND HTG CO., INC3 heads
16 projects · most recent 08/20/2026
Water/Sanitary Gas
FiledStatusContractorScope
08/20/2026Signed-offPAR PLUMBING CO., INCWater/Sanitary
08/06/2026Permit IssuedDONATO PLUMBING, INCWater/Sanitary
04/27/2026Permit IssuedMAC FELDER INCWater/Sanitary
02/09/2026Signed-offMAC FELDER INCWater/Sanitary
01/09/2026Permit IssuedSEAN COAKLEY P & H INCWater/Sanitary
01/07/2026———
12/23/2025Permit IssuedMAC FELDER INCWater/Sanitary
11/21/2025Signed-offPAR PLUMBING CO., INCWater/Sanitary
10/24/2025Signed-offPAR PLUMBING CO., INCWater/Sanitary
10/15/2025Signed-offDONATO PLUMBING, INCWater/Sanitary
07/03/2025Signed-offS.B.A. PLUMBING CORPWater/Sanitary
03/14/2025Signed-offLAB PLBG & HTG CO INCWater/Sanitary
02/05/2025Permit IssuedSKINNER PLUMBING & HEATINGas, Water/Sanitary
03/22/2023——Water/Sanitary
02/24/2023Permit IssuedWILLIAM C. GERAKARIS P&HGas, Water/Sanitary
25 projects · most recent 07/16/2026
General Wiring
FiledStatusContractorScope
07/16/2026Permit IssuedBIG ANT ELECTRIC, INCGeneral Wiring
05/11/2026Permit IssuedALLRAN ELECTRIC OF NY LLCGeneral Wiring
05/07/2026Permit IssuedFOREST ELECTRIC CORP.General Wiring
03/04/2026Permit IssuedNOVA ELECTRIC LLC—
01/12/2026CompleteCAMPBELL & DAWES LTD ELECGeneral Wiring
12/15/2025Permit IssuedNORCAL ELECTRIC LLCGeneral Wiring
12/11/2025Permit IssuedPREMIER ELECTRIC, INCGeneral Wiring
12/03/2025Permit IssuedCORPORATE ELEC. GROUP INC—
11/06/2025CompleteMER ELECTRIC, INCGeneral Wiring
10/22/2025CompleteALLRAN ELECTRIC OF NY LLC—
07/18/2025CompleteALLSTATE ELECTRIC CORPGeneral Wiring
07/01/2025Permit IssuedP.E. STONE INCGeneral Wiring
05/05/2025CompleteZEREM ELECTRIC CORP.General Wiring
04/30/2025CompleteFOREST ELECTRIC CORP.General Wiring
04/30/2025CompleteFOREST ELECTRIC CORP.General Wiring
5 projects · most recent 08/06/2026
Steel Concrete
FiledStatusContractorScope
08/06/2026Permit IssuedSHAWMUT WOODWORKING & SUPSteel, Concrete
04/27/2026Permit IssuedMAC FELDER INCSteel, Concrete
03/17/2026Permit IssuedSUMMIT INTERIORS, INC1 scope_items
02/09/2026Signed-offMAC FELDER INCSteel, Concrete
12/23/2025Permit IssuedMAC FELDER INCSteel
2 projects · most recent 06/23/2026
Fence Sidewalk Shed
FiledStatusContractorScope
06/23/2026Permit IssuedYABOO FENCE CO INCFence
12/12/2025Permit IssuedSAFWAY ATLANTIC, LLCFence, Sidewalk Shed
▾Field Inspections (DOB CAP) — 251
DateTypeResultReport
08/21/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/12/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/12/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/12/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/21/2026Pass-Final CND-Occupancy InspectionPassView ↗
07/13/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/10/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/09/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/09/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/06/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/02/2026Pass-Final CND-Occupancy InspectionPassView ↗
06/12/2026Certified Sprinkler (PL) - SP - RoughingCertifiedView ↗
06/04/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/29/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/27/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/27/2026Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
05/22/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/21/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
05/21/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/19/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/06/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/06/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/06/2026Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
05/01/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/28/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
Latest 25 of 251.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
08/24/2026Duct leakage testing, insulation and designMax Leeenergy_progress
08/24/2026HVAC-R and service water heating system controlsMax Leeenergy_progress
08/24/2026Interior lighting powerMax Leeenergy_progress
08/24/2026Post-installed AnchorsMax Leespecial
08/24/2026FinalMax Leeprogress
08/24/2026Mechanical SystemsMax Leespecial
08/24/2026HVAC-R and service water piping design and insulationMax Leeenergy_progress
08/24/2026HVAC-R and service water heating equipmentMax Leeenergy_progress
08/24/2026Lighting controlsMax Leeenergy_progress
08/07/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
08/07/2026Post-installed AnchorsYoung Suhspecial
08/07/2026Sprinkler SystemsMax Leespecial
08/07/2026Post-installed AnchorsMax Leespecial
08/07/2026Standpipe SystemsYoung Suhspecial
08/06/2026Sprinkler SystemsYoung Suhspecial
08/06/2026Post-installed AnchorsYoung Suhspecial
08/06/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
07/09/2026FinalLEON SKVIRSKYprogress
07/07/2026Standpipe SystemsYoung Suhspecial
07/07/2026Fire-Resistant Penetrations and JointsYoung Suhspecial
07/07/2026Post-installed AnchorsYoung Suhspecial
07/07/2026Public Assembly Emergency LightingJONAR MADRIAGAprogress
07/07/2026Public Assembly Emergency LightingJONAR MADRIAGAprogress
07/01/2026FinalJERE MURDOCHprogress
06/10/2026Shutoff dampersDamon Amadioenergy_progress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Saks GlobalOfficeFloor 27
Project M01411676 Alteration · Permit Entire · 06/11/2026
MeredithOfficeFloor 4
Project M01399351 Alteration CO · Objections · 06/08/2026
Project M00521678 Alteration CO · Permit Entire · 06/03/2021
Project M00511472 Alteration · LOC Issued · 05/25/2021
Bottega VenetaRetail—
Project M01369968 Alteration · Permit Entire · 03/17/2026
Davidoff of GenevaRetailFloor 1
Project M01324908 Alteration · Permit Entire · 01/09/2026
Syneos HealthOfficeFloor 29
Project M01314093 Alteration · Permit Entire · 11/20/2025
Project M01295739 Alteration · Permit Entire · 10/14/2025
Neko HealthMedical / HealthcareFloor 1
Project M01292279 Alteration · Permit Entire · 10/21/2025
Tablet Works PharmacyRetailFloor 2
Project M01222448 Alteration · LOC Issued · 06/18/2025
CommerzbankOfficeFloor 32
Project M01205653 Alteration · LOC Issued · 04/22/2025
Project M00377291 Alteration · LOC Issued · 08/05/2020
College BoardEducationFloor 27
Project M01186659 Alteration CO · Permit Entire · 04/08/2025
Project M01186591 Alteration · LOC Issued · 04/07/2025
Project M01186645 No Work · PA Certificate of Operation Issued · 04/07/2025
InvescoOfficeFloors 10–13, 15
Project M01100414 Alteration · LOC Issued · 02/04/2025
Project M00871800 Alteration · LOC Issued · 06/08/2023
Project M00695712 Alteration · LOC Issued · 04/22/2022
Daily ProvisionsRestaurant / Food ServiceFloor 2
Project M01105207 Alteration · LOC Issued · 09/25/2024
Carrot ExpressRestaurant / Food ServiceFloor 2
Project M01071844 Alteration · LOC Issued · 07/15/2024
Antico Vinaio Sandwich ShopRestaurant / Food ServiceFloor 2
Project M01041061 Alteration · Permit Entire · 05/15/2024
Brookfield Oaktree Wealth SolutionsOfficeFloor 34
Project M00890385 Alteration · LOC Issued · 07/27/2023
Project M00890947 Alteration · LOC Issued · 07/27/2023
Oakfield Oaktree Wealth SolutionsOfficeFloor 34
Project M00887385 Alteration · LOC Issued · 07/18/2023
American Heart Association Wall Street Run & Heart WalkOther—
Project M00866210 No Work · TA Certificate of Operation Issued · 05/01/2023
TartineryRestaurant / Food Service—
Project M00847877 No Work · TA Certificate of Operation Issued · 03/22/2023
The Rink at Brookfield PlaceFitness / Recreation—
Project M08026618 No Work · TA Certificate of Operation Issued · 10/31/2022
Project M00614083 Alteration · Permit Entire · 10/21/2021
Simon Kucher PartnersOfficeFloor 40
Project M00781299 Alteration · LOC Issued · 08/25/2022
Project M00773998 Alteration · LOC Issued · 08/16/2022
Project M00774006 Alteration · LOC Issued · 08/16/2022
Project M00774116 Alteration · LOC Issued · 08/16/2022
Project M00774831 Alteration · LOC Issued · 08/16/2022
Dotdash MeredithRetailFloor 1
Project M00755676 Alteration · LOC Issued · 06/20/2022
Mah-Ze-Dahr BakeryUnknown—
Project M00725720 Alteration · Permit Entire · 06/02/2022
DRW HoldingsOfficeFloor 42
Project M00728654 Alteration · LOC Issued · 06/01/2022
Saks Photo StudioOfficeFloor 26
Project M00704488 Alteration · LOC Issued · 04/08/2022
MasterworksOfficeFloors 28, 29
Project M00635550 Alteration · LOC Issued · 11/24/2021
Louis VuittonRetailFloor 1
Project M00587456 Alteration · Permit Entire · 10/12/2021
Project M00322521 Alteration · LOC Issued · 03/03/2020
Project M00322557 Alteration · LOC Issued · 03/03/2020
Project M00322744 Alteration · LOC Issued · 03/03/2020
EquiLendOfficeFloors 9, 10
Project M00592785 Alteration · LOC Issued · 09/27/2021
Sauce PizzeriaRestaurant / Food ServiceFloor 2
Project M00551903 Alteration · LOC Issued · 09/09/2021
Ani RamenRestaurant / Food ServiceSub-cellar, Floor 2
Project M00564383 Alteration · LOC Issued · 09/03/2021
Project M00564393 Alteration · LOC Issued · 09/03/2021
Adam Grooming AtelierRetailFloor 2
Project M00296087 Alteration · LOC Issued · 02/07/2020
OmegaRetailFloor 1
Project M00198988 Alteration · LOC Issued · 08/29/2019
Project M00199056 Alteration · LOC Issued · 08/13/2019
ConveneOfficeFloor 2
Project M00204289 No Work · PA Certificate of Operation Issued · 08/14/2019
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 14,702 on file (BIS + DOB NOW)
▸Plans & Drawings449
▸DOB NOWPlans/Sketch307
09/06/2026M00033213-I1Request digital key ↗
09/06/2026M00077188-I1Request digital key ↗
09/06/2026M00077201-I1Request digital key ↗
Showing 3 of 307 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly51
09/05/2026M00112183-I1Request digital key ↗
09/05/2026M00128298-I1Request digital key ↗
09/05/2026M00132934-I1Request digital key ↗
Showing 3 of 51 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler24
09/05/2026M00199164-I1Request digital key ↗
09/05/2026M00230091-I1Request digital key ↗
09/05/2026M00281983-I1Request digital key ↗
Showing 3 of 24 on file for this type
▸DOB NOWPlans/Sketch - Plumbing17
09/05/2026M00199056-I1Request digital key ↗
09/05/2026M00230090-I1Request digital key ↗
09/05/2026M00281982-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems16
09/05/2026M00198988-I1Request digital key ↗
09/05/2026M00230089-I1Request digital key ↗
09/05/2026M00281654-I1Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Standpipe10
09/05/2026M00230092-I1Request digital key ↗
Showing 1 of 10 on file for this type
▸DOB NOWPlans/Sketch - Structural9
09/05/2026M00199088-I1Request digital key ↗
09/05/2026M00199088-P1Request digital key ↗
Showing 2 of 9 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly9
09/05/2026M00204283-I1Request digital key ↗
09/05/2026M00204289-I1Request digital key ↗
09/05/2026M00204272-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - General Construction4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sign2
09/05/2026M00226139-I1Request digital key ↗
09/05/2026M00224560-I1Request digital key ↗
▸Applications & Permits2,574
▸BISPLAN / WORK APPROVAL APPLICATION1,517
10/23/2025120638122Open ↗
10/21/2025120638122Open ↗
03/19/2025140926121Open ↗
Showing 3 of 1,517 on file for this type
▸BISWORK PERMIT APPLICATION987
11/29/2022122669371Open ↗
10/14/2022123073654Open ↗
Showing 2 of 987 on file for this type
▸BISPLACE OF ASSEMBLY70
11/28/2022120847995Open ↗
09/27/2022123201114Open ↗
09/26/2022123201114Open ↗
Showing 3 of 70 on file for this type
▸Zoning, Tax Lot & Property Records32
▸BISFLOOD ZONE DESIGN CERTIFICATION32
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 32 on file for this type
▸Seals & Professional Certifications4,018
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1,800
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1,800 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature445
09/06/2026M00077188-I1Open ↗
09/06/2026M00077201-I1Open ↗
09/06/2026M00077164-I1Open ↗
Showing 3 of 445 on file for this type
▸DOB NOWProgress Inspector Seal & Signature422
09/30/2026M07996403-I1Open ↗
09/30/2026M07996403-I1Open ↗
09/30/2026M07996403-I1Open ↗
Showing 3 of 422 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT411
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 411 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST386
11/16/2022140448932Open ↗
Showing 1 of 386 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature349
09/30/2026M07996403-I1Open ↗
09/29/2026M00230091-I1Open ↗
09/28/2026M01121344-S3Open ↗
Showing 3 of 349 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM132
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 132 on file for this type
▸BISPC FULL REPORT22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISAPPLICANT OWNER SIGNATURE11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸Trade Schedules & Equipment1,193
▸BISSELF-CERT PLUMBING NOTICE404
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 404 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE330
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 330 on file for this type
▸BISSCHEDULE B - PLUMBING195
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 195 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA158
08/08/2023121957356Open ↗
08/08/2023122237837Open ↗
08/08/2023103433063Open ↗
Showing 3 of 158 on file for this type
▸BISSPRINKLER INSP REPORT : FP-8553
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 53 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISEQUIPMENT USE PERMITS16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISSTANDPIPE INSP REPORT : FP-8412
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸Safety & Tenant Protection17
▸BISSTREET TREE CHECKLIST11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸DOB NOWStreet Tree Checklist3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWStreet Trees Site Plan1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWStreet Tree Sign Off1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos1,013
▸BISASBESTOS: CERTIFICATION (DEP ACP5)493
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 493 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report341
09/06/2026M00077188-I1Open ↗
09/06/2026M00077201-I1Open ↗
09/06/2026M00077164-I1Open ↗
Showing 3 of 341 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'128
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 128 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸Energy Compliance658
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS368
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 368 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS146
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 146 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY42
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 42 on file for this type
▸BISTR8: Energy Code Progress Inspections34
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 34 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)17
02/06/2025140926121Open ↗
01/10/2024122979107Open ↗
11/01/2022123066500Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: ENERGY11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports237
▸BISTECHNICAL REPORT: RESPONSIBILITY178
02/06/2025123671945Open ↗
02/06/2025140938975Open ↗
02/03/2025140938975Open ↗
Showing 3 of 178 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER24
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 24 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸Approvals, Objections & Sign-offs1,264
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST623
03/19/2025140926121Open ↗
02/18/2025123671945Open ↗
02/13/2025140938975Open ↗
Showing 3 of 623 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION197
02/03/2025123671945Open ↗
02/03/2025140938975Open ↗
11/16/2023103336472Open ↗
Showing 3 of 197 on file for this type
▸BISADMINISTRATIVE OBJECTIONS148
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 148 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE89
10/23/2025120638122Open ↗
10/21/2025120638122Open ↗
10/07/2024120638122Open ↗
Showing 3 of 89 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)81
09/05/2026M00199088-I1Open ↗
09/05/2026M00230091-I1Open ↗
09/05/2026M00230090-I1Open ↗
Showing 3 of 81 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)51
09/05/2026M00230091-I1Open ↗
09/05/2026M00230090-I1Open ↗
09/05/2026M00281654-I1Open ↗
Showing 3 of 51 on file for this type
▸BISSUPERSEDING LETTER23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISFINAL21
02/12/2025123671945Open ↗
02/11/2025140938975Open ↗
02/06/2025140926121Open ↗
Showing 3 of 21 on file for this type
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDCLA Approval of Artwork1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership1,295
▸BISCOST AFFIDAVIT1,261
10/31/2023103433063Open ↗
08/08/2023121957356Open ↗
08/08/2023121957347Open ↗
Showing 3 of 1,261 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW334
02/11/2025140938975Open ↗
02/11/2025123671945Open ↗
02/06/2025140926121Open ↗
Showing 3 of 34 on file for this type
▸Filing & Intake Forms1,567
▸BISEFILING COVER SHEET724
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 724 on file for this type
▸BISADDITIONAL INFORMATION567
12/15/2025120638122Open ↗
12/15/2025120638122Open ↗
03/14/2025120638122Open ↗
Showing 3 of 567 on file for this type
▸BISBOROUGH INTAKE FORM233
10/14/2022123073654Open ↗
Showing 1 of 233 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET43
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 43 on file for this type
▸Other Documents205
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION133
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 133 on file for this type
▸BISSupporting Document: Fee Exempt16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISSUBSTANTIAL IMPROVEMENT CALCULATIONS9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸DOB NOWAlternate Plan 17
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWAlternate Plan 26
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWAlternate Plan 35
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWAlternate Plan 44
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAlternate Plan 64
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAlternate Plan 54
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProperty Ownership Certification3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWAlternate Plan 73
09/05/2026M00204289-I1Open ↗
09/05/2026M00204272-I1Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWAlternate Plan 82
09/05/2026M00204283-I1Open ↗
09/05/2026M00204289-I1Open ↗
▸DOB NOWAlternate Plan 91
09/05/2026M00204289-I1Open ↗
▸DOB NOWAlternate Plan 151
09/05/2026M00204289-I1Open ↗
▸DOB NOWAlternate Plan 111
09/05/2026M00204289-I1Open ↗
▸DOB NOWSupporting Document1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWAlternate Plan 101
09/05/2026M00204289-I1Open ↗
▸DOB NOWAlternate Plan 121
09/05/2026M00204289-I1Open ↗
▸DOB NOWAlternate Plan 141
09/05/2026M00204289-I1Open ↗
▸DOB NOWAlternate Plan 131
09/05/2026M00204289-I1Open ↗
▸DOB NOWFlood Hazard Area Substantial Improvement Calculation1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type