| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01314093 ↗ | 225 LIBERTY STREET MANHATTAN | Alteration | Permit Issued | 11/20/2025 | 11/25/2025 | Design MG ENGINEERING D.P.C. Contractor OMARA ORGANIZATION INC | INTERIOR SPRINKLER MODIFICATIONS ON 29TH FLOOR RELATED TO INTERIOR OFFICE RENOVATION. NO CHANGE OF USE, EGRESS OR OCCUPANCY. NO EXTERIOR WOR… |
| M01295739 ↗ | 225 LIBERTY STREET MANHATTAN | Alteration | Permit Issued | 10/14/2025 | 11/14/2025 | Design MG ENGINEERING D.P.C. Contractor OMARA ORGANIZATION INC | INTERIOR DEMO OF PLUBMING FIXTURES ON 29TH FLOOR AS INDICATED ON PLANS FILED HEREWITH. |
| M00821122 ↗ | 200 VESEY STREET MANHATTAN | Alteration | Signed-off | 02/17/2023 | 02/22/2023 | Design MMOSER ASSOCIATES Owner CBRE Contractor OMARA ORGANIZATION INC | General construction work as shown on plans (Syneos Health). Floor 38 (Construction)/39 (Marketing). |
| Name | Projects together | Most recent |
|---|---|---|
| MMOSER ASSOCIATES | 3 | 11/21/2025 |
| MG ENGINEERING D.P.C. | 2 | 11/21/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| OMARA ORGANIZATION INC | 3 | 11/21/2025 |
| PAR PLUMBING CO., INC | 2 | 11/21/2025 |
| ABCO-PEERLESS SPRKLR CORP | 1 | 11/21/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| BROOKFIELD PROPERTIES OPERATED BY C | 2 | 11/21/2025 |
| CBRE | 1 | 02/17/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| OUTSOURCE CONSULTANTS, INC. | 2 | 11/21/2025 |
| WILLIAM VITACCO ASSOCIATES | 1 | 02/17/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01314093 ↗ | 225 LIBERTY STREET MANHATTAN | Alteration | Permit Issued | 11/20/2025 | 11/25/2025 | Design MG ENGINEERING D.P.C. Contractor OMARA ORGANIZATION INC | INTERIOR SPRINKLER MODIFICATIONS ON 29TH FLOOR RELATED TO INTERIOR OFFICE RENOVATION. NO CHANGE OF USE, EGRESS OR OCCUPANCY. NO EXTERIOR WOR… |
| M01295739 ↗ | 225 LIBERTY STREET MANHATTAN | Alteration | Permit Issued | 10/14/2025 | 11/14/2025 | Design MG ENGINEERING D.P.C. Contractor OMARA ORGANIZATION INC | INTERIOR DEMO OF PLUBMING FIXTURES ON 29TH FLOOR AS INDICATED ON PLANS FILED HEREWITH. |
| M00821122 ↗ | 200 VESEY STREET MANHATTAN | Alteration | Signed-off | 02/17/2023 | 02/22/2023 | Design MMOSER ASSOCIATES Owner CBRE Contractor OMARA ORGANIZATION INC | General construction work as shown on plans (Syneos Health). Floor 38 (Construction)/39 (Marketing). |
| Building | Filings | Most Recent |
|---|---|---|
| 225 LIBERTY STREET ↗ | 2 | 11/21/2025 |
| 200 VESEY STREET ↗ | 1 | 02/17/2023 |