DOB12/01/2024FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
ECB05/02/2024FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #904611. REMEDY: SUBMIT ACCEPTABLE REQU$1K due
DOB12/01/2023FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
DOB02/22/2023FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023
DOB12/01/2022FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
DOB12/01/2021FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
DOB04/29/2021FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
ECB03/30/202127-929.1 AC27-929.1,FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OFAUTOMATIC SPRINKLERS&FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BLDG 100' OR MORE IN HY IN EXISTENCE O$84 due
ECB12/23/2019AC279291-FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY JULY 1,2019,IN AN OFFICE BUILDING 100 FEE$6K due
DOB09/03/2019FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019
DOB03/31/2008V-DOB VIOLATION - ACTIVE
ECB06/17/2024A. C. 27-929.1, FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORNothing owed — awaiting certificate of correction
ECB04/21/202327-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HENothing owed — awaiting certificate of correction
ECB04/21/2020SEC. 27-929.1 AC 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/19,IN AN OFFICE BLDGNothing owed — awaiting certificate of correction
ECB01/28/2020FAILURE TO MAINTAIN EXT BLDG FACADE & APPURTENANCES.AS NOTED EXPOSURE1SEVERAL LOCATIONS W/SPALLED BRICKS,VERTICAL CRACK IN BRICKS ABOVE 1ST FL.EXP:4-SPALLED MASONRY IN SEVERAL LOCATIONS,EXPOSED REBAR SPALLING CNothing owed — awaiting certificate of correction
ECB08/02/2010FAILURE TO FILE AN ARCHITECT / ENGINEER REPORT CERTIFYING EXIT / DIRECTIONAL SIGNAL SIGNS ARE CONNECTED TO EMERGENCY POWER SOURCE / STORAGE BATTERY EQUIPMENT. REMEDY: FILE ARCHITECT / ENGINEER REPORT.Nothing owed — awaiting certificate of correction
ECB02/09/201044H9.44H11.52H11.42B10.100H11.42 REPLACE WORN CONTACTS ON P RELAY AND RELAY AND REPLACE SHUT WIRE ON SFS RELAY 100 REPLACE WORN SADDLE ON LOBBY HALL DOORNothing owed — awaiting certificate of correction