LL97 Covered1 Active Violation 0 unresolved · 1 paperwork only 3 likely answered ▸
Factory, industrial, miscellaneous · Owner of record: PPF Industrial 27-11 49th Avenue · 107,640 sf lot · 2 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofMana Products13p · 3 filings · 17 docs
Penthouse27-11 49th Ave Realty, LLC12p · 3 filings · 20 docs
Floor 3Metropolitan Realty Associates LLC1p · 1 filing · 9 docs
Floor 2Mana Products19p · 4 filings · 20 docs
Floor 1Metropolitan Realty Associates LLC10p · 3 filings · 20 docs
CellarMetropolitan Realty Associates LLC1p · 1 filing · 15 docs
Site & exteriorMetropolitan Realty Associates LLC13p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
27-11 49 Avenue Realty6007/08/2026
Metropolitan Realty2907/08/2026
Mana Products1203/21/2026
27-11 49th Avenue203/21/2026
PPF Industrial 27-11 49th Avenue103/22/2026
32-02 Queens BLVD103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/03/2022$105.5M—— → —$491/sf building
08/31/2020$75.0M—— → —$349/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Design 2147203/21/2026
A1 Expediting Service403/21/2026
KM Associates of New York503/21/2026
JMV Associates803/21/2026
Rigid Structural Design203/21/2026
Tarek M. Zeid, P.E203/21/2026
K & M Associates503/21/2026
Tarek M Zeid P E203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Cook & KrupaGeneral Contractor404/09/2026
JC Contracting ManagementGeneral Contractor303/21/2026
Crystal ComfortGeneral Contractor203/21/2026
Rockledge ScaffoldScaffold207/08/2026
Champ Plumbing & HeatingPlumbing207/08/2026
T.N.T. Plumbing & HeatingFire Protection107/08/2026
Nations Roof Eastspecialty_contractor107/08/2026
Andamio ScaffoldingScaffold107/08/2026
CNH ElectricalElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Benazzi Engineering5603103/27/2025
Crosscheck Inspection Services544408/07/2024
Charles G Michel Engineering2871604/13/2021
KV Lambiris Architect3401110/16/2019
Building Lifecycle
All (154)Filed (15)Permit Issued (13)Signed Off (12)Violation (48)Inspection (2)Objection (34)Special Inspection (30)
08/18/2026
Signed off — Alteration
Repair to existing piles/pile encasements as per plans herewith. No change to use, egress, or occupancy.
Q01010077-I1
09/25/2025
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q01226411-I1
09/10/2025
Signed off — Alteration
TEMPORARY SCAFFOLD STAIR TOWER AS PER DRAWINGS. SCAFFOLD STAIR TOWER SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01079758-S1
09/10/2025
Signed off — Alteration
TEMPORARY SCAFFOLD STAIR TOWER AS PER DRAWINGS. SCAFFOLD STAIR TOWER SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01079758-I1
09/05/2025
Signed off — Alteration
FILING HEREWITH STRUCTURAL REPAIRS AS PER PLANS.
Q01198258-I1
06/13/2025
Permit issued — Structural
Q01010077-I1-ST
06/12/2025
Permit issued — Foundation
Q01010077-S1-FO
05/20/2025
Permit issued — Sidewalk Shed
Q01226411-I1-SH
05/19/2025
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q01226411-I1
04/08/2025
Permit issued — Structural
Q01198258-I1-ST
03/27/2025
Filed — Alteration
FILING HEREWITH STRUCTURAL REPAIRS AS PER PLANS.
Q01198258-I1
03/21/2025
Special inspection requirement — Post-installed Anchors
Gregory Benazzi
03/21/2025
Special inspection requirement — Masonry
Gregory Benazzi
03/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Gregory Benazzi
03/20/2025
Special inspection requirement — Final
Gregory Benazzi
01/17/2025
Signed off — Alteration
Roof recovery system installation with minor patching and associated masonry for perimeter flashing installation as per plans herewith. No work proposed outside of roof areas. No change to use, egress, or occupancy.
Q01050247-I1
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/12/2024
Permit issued — General Construction
Q01050247-I1-GC
08/07/2024
Filed — Alteration
Repair to existing piles/pile encasements as per plans herewith. No change to use, egress, or occupancy.
Q01010077-S1
07/31/2024
Objection resolved — Addressed
07/31/2024
Objection resolved — Addressed
07/31/2024
Objection resolved — Addressed
07/31/2024
Objection resolved — Addressed
07/26/2024
Objection resolved — Addressed
07/23/2024
Filed — Alteration
TEMPORARY SCAFFOLD STAIR TOWER AS PER DRAWINGS. SCAFFOLD STAIR TOWER SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01079758-S1
07/23/2024
Permit issued — Supported Scaffold
Q01079758-S1-SF
07/15/2024
Filed — Alteration
TEMPORARY SCAFFOLD STAIR TOWER AS PER DRAWINGS. SCAFFOLD STAIR TOWER SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Q01079758-I1
07/15/2024
Permit issued — Sidewalk Shed
Q01079758-I1-SH
07/08/2024
Objection raised — Admin
07/08/2024
Objection raised — Admin
07/08/2024
Objection raised — Energy
07/08/2024
Objection raised — Admin
06/25/2024
Objection resolved — Addressed
06/24/2024
Filed — Alteration
Roof recovery system installation with minor patching and associated masonry for perimeter flashing installation as per plans herewith. No work proposed outside of roof areas. No change to use, egress, or occupancy.
Q01050247-I1
06/21/2024
Objection raised — Other
06/21/2024
Objection raised — Other
06/17/2024
Filed — Alteration
Repair to existing piles/pile encasements as per plans herewith. No change to use, egress, or occupancy.
Q01010077-I1
05/14/2024
Special inspection requirement — Final
EUGENE BIFULCO
05/14/2024
Special inspection requirement — Masonry
EUGENE BIFULCO
05/13/2024
Special inspection requirement — Concrete - Cast-In-Place
EUGENE BIFULCO
05/13/2024
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
GREGORY BIESIADECKI
05/13/2024
Special inspection requirement — Structural Steel - Details
EUGENE BIFULCO
05/13/2024
Special inspection requirement — Structural Steel - Welding
EUGENE BIFULCO
05/13/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
EUGENE BIFULCO
02/23/2024
Special inspection requirement — Footing and Foundation
EUGENE BIFULCO
02/23/2024
Special inspection requirement — Final
GREGORY BIESIADECKI
02/23/2024
Special inspection requirement — Final
EUGENE BIFULCO
12/15/2023
Signed off — Alteration
Filing for the Masonry wall replacement at Stairs, exterior Masonry wall repairs and removal of concrete Canopy.
Q08048299-I1
04/20/2023
Permit issued — Structural
Q08048299-I1-ST
02/10/2023
Filed — Alteration
Filing for the Masonry wall replacement at Stairs, exterior Masonry wall repairs and removal of concrete Canopy.
Q08048299-P1
02/10/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
EUGENE BIFULCO
02/10/2023
Special inspection requirement — Structural Steel - High Strength Bolting
02/10/2023
Special inspection requirement — Post-installed Anchors
EUGENE BIFULCO
02/10/2023
Special inspection requirement — Structural Steel - Details
EUGENE BIFULCO
02/10/2023
Special inspection requirement — Structural Steel - High Strength Bolting
EUGENE BIFULCO
02/10/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
EUGENE BIFULCO
02/10/2023
Special inspection requirement — Masonry
EUGENE BIFULCO
02/10/2023
Special inspection requirement — Structural Steel - Welding
EUGENE BIFULCO
Latest 60 of 154 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offCook & Krupa06/13/2025
DOB NOWFoundationPermit IssuedCook & Krupa06/12/2025
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding05/20/2025
DOB NOWStructuralSigned-offJC Contracting Management04/08/2025
DOB NOWGeneral ConstructionSigned-offNations Roof East09/12/2024
DOB NOWSupported ScaffoldSigned-offRockledge Scaffold07/23/2024
DOB NOWSidewalk ShedSigned-offRockledge Scaffold07/15/2024
DOB NOWStructuralSigned-offCook & Krupa04/20/2023
DOB NOWPlumbingSigned-offChamp Plumbing & Heating06/11/2021
DOB NOWBoiler EquipmentSigned-offChamp Plumbing & Heating11/18/2020
DOB NOWMechanical SystemsSigned-offChampion Combustion11/12/2020
DOB NOWSprinklersSigned-offT.N.T. Plumbing & Heating12/12/2019
DOB NOWMechanical SystemsSigned-offCrystal Comfort12/06/2019
BISOTISSUEDCyprus Painting11/25/2019
BISOTISSUEDCyprus Painting05/21/2019
BISSPISSUEDT.N.T. Plumbing & Heating03/14/2019
BISPLISSUEDWard Plumbing07/05/2018
BISMHISSUEDCrystal Comfort02/06/2018
BISOTISSUEDCyprus Painting01/29/2018
BISOTISSUEDCyprus Painting01/29/2018
BISSPISSUEDT.N.T. Plumbing & Heating01/29/2018
BISOTISSUEDCyprus Painting01/23/2018
BISOTISSUEDCyprus Painting01/23/2018
BISMHISSUEDCyprus Painting01/23/2018
BISMHISSUEDCrystal Comfort01/18/2018
BISSPISSUEDT.N.T. Plumbing & Heating01/10/2018
BISMHISSUEDCyprus Painting01/09/2018
BISMHISSUEDRP Cooling07/20/2011
BISPLISSUEDEP Plumbing Co04/24/2009
BISMHISSUEDRP Cooling04/24/2009
BISOTISSUEDPromax Home Imprve03/13/2009
BISPLISSUEDEP Plumbing Co01/28/2009
BISBLISSUEDE P Plumbing Co01/15/2008
BISPLISSUEDE P Plumbing Co01/15/2008
BIS—ISSUEDMana Product11/19/2007
BISMHISSUEDMana Products11/19/2007
BISMHISSUEDMana Products10/24/2006
BISOTISSUEDMana Products10/24/2006
BIS—ISSUEDMana Product10/24/2006
BISOTISSUEDMana Products10/24/2006
+ 23 more permits on file
6 projects · most recent 05/21/2025
FiledStatusContractorScope
05/21/2025CompleteBorowide Elect'l Contractors—
07/03/2024CompleteAnthony G Ferry—
01/28/2020Permit IssuedCNH Electrical—
10/03/2019Permit IssuedStar Electrical Contractors—
04/29/2019Permit IssuedStar Electrical Contractors—
03/11/2019Permit IssuedCNH Electrical1 meters, 1 new_meters
1 project · most recent 08/07/2024
Concrete
FiledStatusContractorScope
08/07/2024Signed-offCook & KrupaConcrete
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
07/22/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/23/2021No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
▾Special Inspection Requirements (DOB NOW) — 51
DateRequirementInspectorRole
03/21/2025Post-installed AnchorsGregory Benazzispecial
03/21/2025MasonryGregory Benazzispecial
03/20/2025Structural Stability – Alterations of existing buildingsGregory Benazzispecial
03/20/2025FinalGregory Benazziprogress
05/14/2024FinalEUGENE BIFULCOprogress
05/14/2024MasonryEUGENE BIFULCOspecial
05/13/2024Concrete - Cast-In-PlaceEUGENE BIFULCOspecial
05/13/2024Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)GREGORY BIESIADECKIspecial
05/13/2024Structural Steel - DetailsEUGENE BIFULCOspecial
05/13/2024Structural Steel - WeldingEUGENE BIFULCOspecial
05/13/2024Structural Stability – Alterations of existing buildingsEUGENE BIFULCOspecial
02/23/2024Footing and FoundationEUGENE BIFULCOprogress
02/23/2024FinalGREGORY BIESIADECKIprogress
02/23/2024FinalEUGENE BIFULCOprogress
02/10/2023Structural Stability – Alterations of existing buildingsEUGENE BIFULCOspecial
02/10/2023Structural Steel - High Strength Bolting—special
02/10/2023Post-installed AnchorsEUGENE BIFULCOspecial
02/10/2023Structural Steel - DetailsEUGENE BIFULCOspecial
02/10/2023Structural Steel - High Strength BoltingEUGENE BIFULCOspecial
02/10/2023Construction Operations Influencing Adjacent StructuresEUGENE BIFULCOspecial
02/10/2023MasonryEUGENE BIFULCOspecial
02/10/2023Structural Steel - WeldingEUGENE BIFULCOspecial
02/10/2023FinalEUGENE BIFULCOprogress
02/09/2023Structural Steel - WeldingEUGENE BIFULCOspecial
02/09/2023FinalEUGENE BIFULCOprogress
Latest 25 of 51.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Mana ProductsOfficeFloor 2, Roof
Project Q00239216 Alteration · LOC Issued · 10/16/2019
Project Q00239230 Alteration · LOC Issued · 10/16/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 324 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch8
08/25/2026Q08048299-I1Request digital key ↗
08/25/2026Q08048299-P1Request digital key ↗
08/21/2026Q01079758-S1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/15/2026Q00239230-I1Request digital key ↗
08/15/2026Q00348030-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
08/27/2026Q00348015-P1Request digital key ↗
08/15/2026Q00348015-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment1
08/15/2026Q00347992-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
08/28/2026Q00239216-I1Request digital key ↗
▸Applications & Permits47
▸BISPLAN / WORK APPROVAL APPLICATION26
10/28/2020421585412Open ↗
10/07/2020421585412Open ↗
09/09/2020421585412Open ↗
Showing 3 of 26 on file for this type
▸BISWORK PERMIT APPLICATION20
12/05/2019421797247Open ↗
06/04/2019421726984Open ↗
03/20/2019421380874Open ↗
Showing 3 of 20 on file for this type
▸BISPLACE OF ASSEMBLY1
02/05/2015401962015Open ↗
▸Seals & Professional Certifications100
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION35
10/28/2020421585412Open ↗
01/16/2020421585635Open ↗
12/05/2019421797247Open ↗
Showing 3 of 35 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature21
09/23/2026Q00347992-I1Open ↗
09/23/2026Q00347992-I1Open ↗
09/02/2026Q01010077-S1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWProgress Inspector Seal & Signature20
09/23/2026Q00347992-I1Open ↗
09/23/2026Q00347992-I1Open ↗
09/23/2026Q00347992-I1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/28/2026Q00239216-I1Open ↗
08/27/2026Q00348015-I1Open ↗
08/27/2026Q00348015-P1Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT6
06/28/2018421646106Open ↗
12/20/2017421585635Open ↗
12/20/2017421585403Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
06/28/2018421646106Open ↗
12/20/2017421585635Open ↗
12/20/2017421585403Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment20
▸BISSELF-CERT PLUMBING NOTICE5
06/23/2010420006326Open ↗
Showing 1 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT5
10/15/2020421585412Open ↗
08/19/2011420368088Open ↗
08/19/2011420368088Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE PERMITS4
12/17/2020421585412Open ↗
10/15/2020421585412Open ↗
08/19/2011420368088Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE4
12/08/2018421380874Open ↗
06/28/2018421646106Open ↗
12/20/2017421585635Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
06/23/2010420006326Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos38
▸DOB NOWOER: Notice to Proceed8
08/28/2026Q00239216-I1Open ↗
08/13/2026Q01010077-S1Open ↗
08/13/2026Q01050247-I1Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)7
09/03/2019421797247Open ↗
05/02/2019421726984Open ↗
07/12/2018421646106Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWOER: Notice of Satisfaction7
08/28/2026Q00239216-I1Open ↗
08/13/2026Q08048299-I1Open ↗
08/13/2026Q01010077-S1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/28/2026Q00239216-I1Open ↗
08/25/2026Q08048299-P1Open ↗
08/25/2026Q08048299-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
06/20/2011420368088Open ↗
06/20/2011420368088Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/15/2026Q00348015-I1Open ↗
08/13/2026Q00348030-I1Open ↗
08/13/2026Q00347992-I1Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION1
12/09/2020421797247Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
10/16/2019421797247Open ↗
▸Energy Compliance19
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
10/22/2019421585403Open ↗
09/20/2019421726984Open ↗
09/20/2019421726984Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
12/09/2020421797247Open ↗
10/15/2020421585412Open ↗
10/22/2019421585403Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
08/19/2011420368088Open ↗
07/22/2011420368088Open ↗
▸DOB NOWPreliminary Commissioning Report Certification2
08/13/2026Q00347992-I1Open ↗
08/13/2026Q00348030-I1Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
10/15/2020421585412Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
12/09/2020421797247Open ↗
10/15/2020421585412Open ↗
10/15/2020421585412Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs22
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
12/09/2020421797247Open ↗
10/15/2020421585412Open ↗
01/23/2020421585635Open ↗
Showing 3 of 13 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
10/21/2019421797247Open ↗
01/19/2018421585403Open ↗
08/26/2010420006326Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
10/27/2017421380874Open ↗
06/17/2011420368088Open ↗
Showing 2 of 4 on file for this type
▸Cost, Insurance & Ownership22
▸BISCOST AFFIDAVIT22
12/09/2020421797247Open ↗
10/15/2020421585412Open ↗
11/01/2019421585635Open ↗
Showing 3 of 22 on file for this type
▸Filing & Intake Forms33
▸BISADDITIONAL INFORMATION15
10/28/2020421585412Open ↗
10/07/2020421585412Open ↗
10/02/2020421585412Open ↗
Showing 3 of 15 on file for this type
▸BISEFILING COVER SHEET14
09/03/2019421797247Open ↗
05/02/2019421726984Open ↗
06/28/2018421646106Open ↗
Showing 3 of 14 on file for this type
▸BISBOROUGH INTAKE FORM4
01/09/2019421585412Open ↗
12/29/2018421585412Open ↗
12/08/2018421380874Open ↗
Showing 3 of 4 on file for this type
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
08/26/2020421585412Open ↗
07/11/2020421585412Open ↗