| Owner | Filings | Most Recent |
|---|---|---|
| National Grid | 258 | 10/17/2026 |
| Brooklyn Union Gas Co | 11 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Michael Gerasopoulos | 2 | 08/21/2026 |
| National Grid | 1 | 06/18/2026 |
| BL Companies | 24 | 06/17/2026 |
| PS&S | 1 | 03/31/2026 |
| WB Engineers & Consultants | 1 | 03/09/2026 |
| Harold Downing | 1 | 02/25/2026 |
| Antonio Leo Architect | 2 | 02/06/2026 |
| Goldman Copeland Associates | 22 | 11/13/2025 |
| HDR | 2 | 09/16/2025 |
| HDR Engineering | 1 | 09/16/2025 |
| William F. Collins Architects | 14 | 08/05/2025 |
| All City Engineering | 6 | 08/30/2024 |
| B-Cubed Engineering | 5 | 06/26/2024 |
| Gomez | 1 | 06/22/2023 |
| Vector Structural Engineering | 1 | 12/09/2022 |
| Joseph Wojnas | 1 | 08/02/2022 |
| Bga | 2 | 05/27/2022 |
| Urban Integrations | 1 | 04/07/2022 |
| Walter T. Gorman, P.E | 2 | 08/16/2021 |
| Grammas Consultants | 1 | 02/17/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| RPO | 66 | 03/21/2026 |
| K & M Associates | 35 | 03/21/2026 |
| KM Associates of New York | 30 | 03/21/2026 |
| Walter T Gorman PE | 4 | 03/21/2026 |
| Metropolis Group | 2 | 03/21/2026 |
| Codegreen | 2 | 03/21/2026 |
| Construction Permit Services | 2 | 03/21/2026 |
| Tower | 3 | 03/21/2026 |
| Preemptive Solutions & Consulting | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Bond Civil & Utility Cons | General Contractor | 53 | 08/04/2026 |
| H.M. Hughes Co | General Contractor | 30 | 07/08/2026 |
| Clune Construction Co | General Contractor | 16 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 11 | 07/08/2026 |
| Bancker Construction | General Contractor | 10 | 10/17/2026 |
| Spring Scaffolding | Scaffold | 8 | 07/08/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 5 | 07/08/2026 |
| Posillico Environmental I | General Contractor | 5 | 07/08/2026 |
| Matco Service | General Contractor | 5 | 08/12/2026 |
| Phoenix Plumbing & Mechanical | Fire Protection | 5 | 07/08/2026 |
| Village P & H NY | Plumbing | 4 | 07/08/2026 |
| John F Mize | Electrical | 4 | 03/21/2026 |
| Murray James | Electrical | 4 | 03/21/2026 |
| Brookside Environmetal | General Contractor | 4 | 03/21/2026 |
| Global Facility Management | General Contractor | 4 | 03/21/2026 |
| Abco-Peerless Sprinkler | Plumbing | 4 | 03/22/2026 |
| Clune Construction Co | Scaffold | 3 | 03/21/2026 |
| Fresh Meadow Mechanical Plumbing | Plumbing | 2 | 06/28/2026 |
| SJS Construction Co | General Contractor | 2 | 07/08/2026 |
| Avalon Electric | Electrical | 1 | 03/22/2026 |
| North American Dismantling | Scaffold | 1 | 07/08/2026 |
| Elmac Electric | Electrical | 1 | 03/21/2026 |
| JSP Electl CNTNG | Electrical | 1 | 03/21/2026 |
| Cross Check Mechanical | Plumbing | 1 | 07/08/2026 |
| Hydrokinetic Plumbing & Heating I | Plumbing | 1 | 07/08/2026 |
| Corporate Electric Group | Electrical | 1 | 03/21/2026 |
| Kevin Keaveny Electric Co | Electrical | 1 | 03/21/2026 |
| Thompson Michael | Electrical | 1 | 03/21/2026 |
| SRM Electrical Service | Electrical | 1 | 03/22/2026 |
| Upright Fire Protctn | Fire Protection | 1 | 08/26/2026 |
| Schlesinger Elect'l Contracting | Electrical | 1 | 03/22/2026 |
| Elemco Testing Co Inc Dba | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Grant Engineering | 2627 | 2 | 08/21/2026 |
| Alan Margolin & Associates | 423 | 30 | 05/08/2026 |
| WB Engineering | 533 | 1 | 03/09/2026 |
| Gza Geoenvironmental of N | 1179 | 6 | 01/06/2026 |
| Goldman Copeland Associates | 2826 | 3 | 11/13/2025 |
| All City Engineering | 7115 | 6 | 08/30/2024 |
| Crosscheck Inspection Services | 544 | 18 | 06/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Bancker Construction | 10/16/2026 |
| DOB NOW | General Construction | Permit Issued | Bancker Construction | 10/16/2026 |
| DOB NOW | General Construction | Permit Issued | Bancker Construction | 09/10/2026 |
| DOB NOW | Structural | Permit Issued | Matco Service | 08/11/2026 |
| DOB NOW | Foundation | Permit Issued | Bond Civil & Utility Cons | 08/03/2026 |
| DOB NOW | General Construction | Permit Issued | Bond Civil & Utility Cons | 07/31/2026 |
| DOB NOW | Support of Excavation | Permit Issued | Bond Civil & Utility Cons | 07/31/2026 |
| DOB NOW | Plumbing | Permit Issued | Fresh Meadow Mechanical Plumbing | 06/24/2026 |
| DOB NOW | General Construction | Permit Issued | Posillico Environmental I | 06/08/2026 |
| DOB NOW | Sprinklers | Permit Issued | Kit Renovation | 06/05/2026 |
| DOB NOW | Structural | Signed-off | Bond Civil & Utility Cons | 05/08/2026 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 05/05/2026 |
| DOB NOW | General Construction | Signed-off | HM Hughes Co | 04/10/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Matco Service | 03/18/2026 |
| DOB NOW | Foundation | Permit Issued | Bond Civil & Utility Cons | 03/10/2026 |
| DOB NOW | Support of Excavation | Permit Issued | Bond Civil & Utility Cons | 03/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Global Facility Management | 02/11/2026 |
| DOB NOW | General Construction | Permit Issued | Global Facility Management | 02/11/2026 |
| DOB NOW | Structural | Permit Issued | Bond Civil & Utility Cons | 01/29/2026 |
| DOB NOW | Sprinklers | Permit Issued | Abco-Peerless Sprinkler | 01/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | Abco-Peerless Sprinkler | 01/26/2026 |
| DOB NOW | Sprinklers | Signed-off | Abco-Peerless Sprinkler | 01/06/2026 |
| DOB NOW | Earth Work | Permit Issued | Bond Civil & Utility Cons | 11/06/2025 |
| DOB NOW | General Construction | Permit Issued | Bond Civil & Utility Cons | 11/06/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | Foundation | Permit Issued | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | Earth Work | Permit Issued | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | Foundation | Permit Issued | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | Structural | Permit Issued | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | Support of Excavation | Signed-off | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | Support of Excavation | Signed-off | Bond Civil & Utility Cons | 11/05/2025 |
| DOB NOW | General Construction | Permit Issued | Bancker Construction | 10/06/2025 |
| DOB NOW | Earth Work | Permit Issued | Bond Civil & Utility Cons | 10/06/2025 |
| DOB NOW | Foundation | Permit Issued | Bond Civil & Utility Cons | 10/03/2025 |
| DOB NOW | Support of Excavation | Signed-off | Bond Civil & Utility Cons | 07/09/2025 |
| DOB NOW | Support of Excavation | Signed-off | Bond Civil & Utility Cons | 07/08/2025 |
| DOB NOW | Structural | Permit Issued | Bond Civil & Utility Cons | 07/07/2025 |
| DOB NOW | Foundation | Permit Issued | Bond Civil & Utility Cons | 07/07/2025 |
| DOB NOW | Earth Work | Permit Issued | Bond Civil & Utility Cons | 07/07/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Bond Civil & Utility Cons | 07/07/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/09/2026 | Permit Issued | Matco Service | Air Conditioning Systems, Ventilation Systems | |
| 05/17/2024 | — | — | Generators | — |
| 05/17/2024 | — | — | Generators | — |
| 12/11/2020 | Permit Issued | SJS Construction Co | Air Conditioning Systems | Cooling Task TGU063CAV ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2026 | Permit Issued | Upright Fire Protctn | Sprinkler System |
| 01/31/2025 | Permit Issued | Abco-Peerless Sprinkler | 1,445 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2026 | Permit Issued | Fresh Meadow Mechanical Plumbing | Gas, Storm, Water/Sanitary |
| 05/17/2024 | — | — | Gas |
| 05/17/2024 | — | — | Gas |
| 11/01/2023 | Signed-off | Hydrokinetic Plumbing & Heating I | Gas |
| 01/08/2021 | Permit Issued | Village P & H NY | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/08/2026 | Permit Issued | E-J Electric Installation Co | General Wiring |
| 03/30/2026 | Complete | Tri-Power Electrical | General Wiring |
| 02/11/2026 | Permit Issued | Accurate Electrical Contractors | General Wiring |
| 03/10/2025 | Permit Issued | Accurate Electrical Contractors | General Wiring |
| 09/10/2024 | Complete | SRM Electrical Service | — |
| 06/26/2024 | Permit Issued | E-J Electric Installation Co | General Wiring |
| 11/01/2023 | Complete | AMC Electrical Services | General Wiring |
| 11/29/2022 | Complete | Schlesinger Elect'l Contracting | — |
| 10/06/2022 | Permit Issued | Avalon Electric | — |
| 04/26/2022 | Permit Issued | E-J Electric Installation Co | General Wiring |
| 04/08/2022 | Complete | Top Shelf Electric | — |
| 02/11/2021 | Permit Issued | Heso Electrical | General Wiring |
| 02/11/2021 | Permit Issued | Heso Electrical | General Wiring |
| 12/06/2019 | Permit Issued | Avalon Electric | — |
| 02/15/2019 | Complete | E-J Electric Installation Co | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Permit Issued | Matco Service | Steel, Concrete |
| 03/31/2026 | Signed-off | Bond Civil & Utility Cons | Steel |
| 09/16/2025 | Permit Issued | Bond Civil & Utility Cons | Steel, Concrete |
| 03/14/2025 | Permit Issued | Bond Civil & Utility Cons | 1 scope_items |
| 05/27/2022 | — | — | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2025 | Permit Issued | Bond Civil & Utility Cons | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/26/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/10/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/08/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/08/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/06/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/05/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/30/2025 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 10/27/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/15/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/09/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/09/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/08/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/04/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 11/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/06/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/03/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/12/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/26/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/05/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/25/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/19/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/11/2026 | Subgrade Inspections | Stephen Morse | special |
| 08/11/2026 | Concrete - Cast-In-Place | Stephen Morse | special |
| 08/11/2026 | Structural Stability – Alterations of existing buildings | Stephen Morse | special |
| 08/11/2026 | Structural Steel - Details | Stephen Morse | special |
| 08/11/2026 | Structural Steel - High Strength Bolting | Stephen Morse | special |
| 08/11/2026 | Structural Steel - Welding | Stephen Morse | special |
| 08/11/2026 | Final | Stephen Morse | progress |
| 06/10/2026 | Final | ROBERT KARPOWICZ | progress |
| 06/04/2026 | Sprinkler Systems | Young Suh | special |
| 06/04/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 05/19/2026 | Heating Systems | — | special |
| 04/29/2026 | Sprinkler Systems | Young Suh | special |
| 04/29/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 03/09/2026 | HVAC-R and service water piping design and insulation | David Bonifacic | energy_progress |
| 03/09/2026 | HVAC-R and service water heating system controls | David Bonifacic | energy_progress |
| 03/09/2026 | Duct leakage testing, insulation and design | David Bonifacic | energy_progress |
| 03/09/2026 | Maintenance information | David Bonifacic | energy_progress |
| 03/09/2026 | Shutoff dampers | David Bonifacic | energy_progress |
| 03/09/2026 | HVAC-R and service water heating equipment | David Bonifacic | energy_progress |
| 03/05/2026 | Final | Young Suh | progress |
| 03/05/2026 | Structural Stability – Alterations of existing buildings | Young Suh | special |
| 03/05/2026 | Concrete - Cast-In-Place | — | special |
| 03/05/2026 | Structural Steel - Details | Young Suh | special |
| 02/09/2026 | Mechanical Systems | David Bonifacic | special |
| 02/09/2026 | Final | David Bonifacic | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| National Grid | Office | Cellar, Floors 1, 2, Roof | Project B01415104 Project B01346625 Project B01334654 Project B01311652 Project B01270996 Project B01170423 Project B01170499 Project B01151026 Project B01122387 Project B01033670 Project B00830963 Project B00830967 |