| Owner | Filings | Most Recent |
|---|---|---|
| 305 East 24th Owners | 160 | 07/08/2026 |
| Baybridge Condo III | 5 | 07/08/2026 |
| SS Bridging Construction | 5 | 03/21/2026 |
| 305 East 24th | 5 | 03/21/2026 |
| Parman | 3 | 03/21/2026 |
| Nardoni Realty | 2 | 03/21/2026 |
| RSP Companies | 1 | 03/22/2026 |
| Tower | 1 | 03/21/2026 |
| Phoenix | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Fsi Architecture | 2 | 08/20/2026 |
| Studio NÖW | 2 | 07/23/2026 |
| Li Architecture Studio | 1 | 06/25/2026 |
| Rigid Structural Design | 1 | 05/08/2026 |
| Lawrence V. McDonald, Jr. Architect | 3 | 07/14/2025 |
| Arquitectura Varela | 1 | 08/28/2024 |
| KMB Design Group | 2 | 08/08/2023 |
| Gaby Tchilinguirian R.A | 1 | 05/24/2023 |
| GMH Architecture | 4 | 10/20/2022 |
| EN-Power Group | 1 | 05/31/2022 |
| Connolly Engineering | 1 | 03/18/2022 |
| Sullivan | 1 | 03/15/2022 |
| Marcelo Barujel Architect | 2 | 02/28/2022 |
| Wong Architect | 2 | 11/05/2021 |
| Ndkazalas Architecture | 1 | 03/02/2020 |
| Baileys Engineering | 1 | 06/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Construction Permit Services | 2 | 03/21/2026 |
| Cornerstone Consulting | 2 | 03/21/2026 |
| Stark Expediting Group | 2 | 03/21/2026 |
| Synchron Expediting | 2 | 03/21/2026 |
| Ndkazalas Architecture | 1 | 03/21/2026 |
| M W Expediting | 2 | 03/21/2026 |
| J A Expediting | 2 | 03/21/2026 |
| AE Design Solution | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Skyline Restoration | specialty_contractor | 6 | 07/08/2026 |
| Bari Dejaynes | General Contractor | 5 | 08/18/2026 |
| Macintosh Electric | Electrical | 3 | 03/21/2026 |
| Titan Contracting | General Contractor | 3 | 03/21/2026 |
| J&D Maintenance | General Contractor | 3 | 03/21/2026 |
| Deluxe Electrical & Maintenance | Electrical | 2 | 03/21/2026 |
| Evs Electric | Electrical | 2 | 03/22/2026 |
| Renovation by MY Home | General Contractor | 2 | 03/21/2026 |
| Asaro Paul | Electrical | 2 | 03/21/2026 |
| R & L Construction & Painting | General Contractor | 2 | 03/21/2026 |
| Vilanova Electrical Conts | Electrical | 2 | 03/22/2026 |
| Macintosh Electric | Electrical | 2 | 03/22/2026 |
| Skyline Restoration | Scaffold | 2 | 07/08/2026 |
| Bell Construction of NY | General Contractor | 1 | 07/08/2026 |
| Crystal Comfort | General Contractor | 1 | 04/09/2026 |
| E. Castillo Construction | General Contractor | 1 | 07/08/2026 |
| Taurus Construction Group | General Contractor | 1 | 07/08/2026 |
| Zaf | General Contractor | 1 | 07/08/2026 |
| Intersystem Construction | Scaffold | 1 | 07/02/2026 |
| AMC Plumbing, Heating & CLNG | Plumbing | 1 | 07/08/2026 |
| American Build PLB & HT | Plumbing | 1 | 07/08/2026 |
| Crown Plumbing | Plumbing | 1 | 07/08/2026 |
| Metrotech Mechanical | Plumbing | 1 | 07/08/2026 |
| New York Park Plumbing & Heating Co | Plumbing | 1 | 07/08/2026 |
| TMS Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Berger Carlos | Electrical | 1 | 03/21/2026 |
| Fas Electric | Electrical | 1 | 03/22/2026 |
| Pappas & Fodera Elect'l | Electrical | 1 | 03/21/2026 |
| Gia Electrical | Electrical | 1 | 03/22/2026 |
| Gsa Electric | Electrical | 1 | 03/22/2026 |
| George Holness G.C | Electrical | 1 | 03/21/2026 |
| Jte Electrical Services | Electrical | 1 | 03/22/2026 |
| Jumper Electric | Electrical | 1 | 03/22/2026 |
| Momern Elect'l Contractors | Electrical | 1 | 03/21/2026 |
| Magic Electric | Electrical | 1 | 03/21/2026 |
| Spectrum Electric | Electrical | 1 | 03/21/2026 |
| A & E Construction of NY | General Contractor | 1 | 08/21/2026 |
| Agl Development | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Fsi Architecture | 354 | 2 | 08/20/2026 |
| Group-S | 5216 | 3 | 08/20/2026 |
| Broadway Inspections | 8735 | 1 | 06/25/2026 |
| Lawrence V McDonald Architects | 6039 | 3 | 07/14/2025 |
| KMB Design Group | 513 | 2 | 08/08/2023 |
| Gaby Tchilinguirian R.A | 2540 | 1 | 05/24/2023 |
| GM Huang Architecture PLL | 1398 | 3 | 10/19/2022 |
| Chen Engineering Services | 1826 | 1 | 03/18/2022 |
| Rimkus New York | 8123 | 1 | 03/15/2022 |
| Wong Architect | 1272 | 2 | 11/05/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | A & E Construction of NY | 08/20/2026 |
| DOB NOW | General Construction | Signed-off | Bari Dejaynes | 08/17/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Intersystem Construction | 05/11/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Crystal Comfort | 02/20/2026 |
| DOB NOW | General Construction | Signed-off | Bari Dejaynes | 11/18/2024 |
| DOB NOW | General Construction | Signed-off | Bell Construction of NY | 08/29/2024 |
| DOB NOW | General Construction | Signed-off | Bari Dejaynes | 02/06/2024 |
| DOB NOW | Plumbing | Signed-off | New York Park Plumbing & Heating Co | 10/06/2023 |
| DOB NOW | General Construction | Signed-off | Taurus Construction Group | 08/18/2023 |
| DOB NOW | General Construction | Signed-off | J&D Maintenance | 07/14/2023 |
| DOB NOW | Antenna | Signed-off | Agl Development | 06/09/2023 |
| DOB NOW | Plumbing | Signed-off | AMC Plumbing, Heating & CLNG | 03/01/2023 |
| DOB NOW | General Construction | Signed-off | Skyline Restoration | 12/16/2022 |
| DOB NOW | Structural | Signed-off | Skyline Restoration | 12/16/2022 |
| DOB NOW | General Construction | Signed-off | R L Construction Pain | 12/06/2022 |
| DOB NOW | General Construction | Signed-off | Skyline Restoration | 08/24/2022 |
| DOB NOW | Structural | Signed-off | Skyline Restoration | 08/23/2022 |
| DOB NOW | General Construction | Signed-off | Titan Contracting | 06/10/2022 |
| DOB NOW | Plumbing | Signed-off | Crown Plumbing | 04/29/2022 |
| DOB NOW | General Construction | Signed-off | E. Castillo Construction | 04/04/2022 |
| DOB NOW | Plumbing | Signed-off | TMS Plumbing & Heating | 01/31/2022 |
| DOB NOW | General Construction | Signed-off | Renovation by MY Home | 11/24/2021 |
| DOB NOW | Plumbing | Permit Issued | Metrotech Mechanical | 10/01/2021 |
| DOB NOW | General Construction | Signed-off | Zaf | 09/14/2021 |
| DOB NOW | Plumbing | Signed-off | American Build PLB & HT | 07/24/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Skyline Restoration | 08/01/2019 |
| DOB NOW | Supported Scaffold | Signed-off | Skyline Restoration | 06/13/2018 |
| BIS | OT | ISSUED | Minos Construction | 12/28/2020 |
| BIS | EQ | ISSUED | Phoenix Sutton STR | 08/31/2020 |
| BIS | OT | ISSUED | Minos Construction | 07/21/2020 |
| BIS | OT | ISSUED | Skyline Restoration | 06/17/2020 |
| BIS | OT | ISSUED | Skyline Restoration | 03/03/2020 |
| BIS | OT | ISSUED | Skyline Restoration | 02/28/2020 |
| BIS | PL | ISSUED | Aranda Plumbing & Heating | 05/23/2019 |
| BIS | OT | ISSUED | Skyline Restoration | 03/08/2019 |
| BIS | OT | ISSUED | Pina's Remodelers & Desig | 03/07/2019 |
| BIS | OT | ISSUED | Skyline Restoration | 03/01/2019 |
| BIS | OT | ISSUED | Intelligen Power Systems | 10/17/2018 |
| BIS | PL | ISSUED | F1 Mechanical | 10/09/2018 |
| BIS | OT | ISSUED | Dowd Interiors | 10/05/2018 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/20/2026 | Permit Issued | Crystal Comfort | Cooling Towers | Cooling Tower Marley Marley NC8403QLN1 6,595,400 BTU · Cooling Tower ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/22/2021 | Permit Issued | Metrotech Mechanical | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/19/2026 | Permit Issued | 876 Electrical | General Wiring |
| 07/31/2026 | Permit Issued | Go to Electrical | General Wiring |
| 07/01/2026 | Complete | IP2 Electric | General Wiring |
| 04/28/2026 | Complete | Glendale Electl Contng | General Wiring |
| 09/19/2025 | Complete | Input Electric | General Wiring |
| 07/30/2025 | Complete | Ikaros Electrical Enterprises | — |
| 07/21/2025 | Permit Issued | McCleary Electric Cont | General Wiring |
| 07/14/2025 | Complete | Empire Lic Electrical Contractors | General Wiring |
| 06/26/2025 | Complete | Macintosh Electric | General Wiring |
| 04/14/2025 | Complete | Macintosh Electric | General Wiring |
| 02/15/2025 | Permit Issued | Evs Electric | General Wiring |
| 11/20/2024 | Complete | Argon Electrical | General Wiring |
| 02/29/2024 | Permit Issued | Evs Electric | General Wiring |
| 02/20/2024 | Complete | M & M Control Wiring | — |
| 02/07/2024 | Complete | Evs Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2026 | Permit Issued | A & E Construction of NY | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2026 | Permit Issued | Intersystem Construction | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/10/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/08/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/18/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/14/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/10/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/06/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/26/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/19/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/19/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/19/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/02/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/10/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/05/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/01/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/18/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/20/2026 | Mechanical Systems | James Cicalo | special |
| 07/20/2026 | Final | James Cicalo | progress |
| 07/20/2026 | Energy Code Compliance Inspections | James Cicalo | progress |
| 07/20/2026 | Tenant Protection Plan Compliance | MICHAEL SCORRANO | special |
| 05/05/2026 | Final | ADAM WATSON | progress |
| 12/05/2025 | Tenant Protection Plan Compliance | MICHAEL SCORRANO | special |
| 07/22/2025 | Energy Code Compliance Inspections | Lawrence McDonald | progress |
| 07/22/2025 | Fire-Resistant Penetrations and Joints | Lawrence McDonald | special |
| 07/14/2025 | Energy Code Compliance Inspections | James Cicalo | progress |
| 07/09/2025 | Energy Code Compliance Inspections | Lawrence McDonald | progress |
| 07/09/2025 | Fire-Resistant Penetrations and Joints | Lawrence McDonald | special |
| 06/06/2025 | Mechanical Systems | James Cicalo | special |
| 06/06/2025 | Final | James Cicalo | progress |
| 08/20/2024 | Final | Vicente Varela | progress |
| 01/30/2024 | Final | ADAM WATSON | progress |
| 07/20/2023 | Fire-Resistant Penetrations and Joints | Lawrence McDonald | special |
| 07/20/2023 | Energy Code Compliance Inspections | Lawrence McDonald | progress |
| 07/20/2023 | Fire-Resistance Rated Construction | Lawrence McDonald | progress |
| 07/20/2023 | Interior lighting power | Lawrence McDonald | energy_progress |
| 07/20/2023 | Lighting in dwelling units | Lawrence McDonald | energy_progress |
| 06/06/2023 | Final | Lawrence McDonald | progress |
| 05/19/2023 | Final | GABY TCHILINGUIRIAN | progress |
| 05/19/2023 | Fire-Resistant Penetrations and Joints | GABY TCHILINGUIRIAN | special |
| 05/26/2022 | Structural Stability – Alterations of existing buildings | HENLIA CHEN | special |
| 05/19/2022 | Mechanical Systems | MICHAEL SCORRANO | special |