Whole building & multi-floor projectsGoldmanUnder Construction4 filings
General Construction facade work taking place on floors 001-086 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Mechanical modifications taking place on the Sub-Cellar (Construction)/Lower Level (Marketing), 1st through 46th, 2nd Floor, 5th Floor, 10th Floor, 73rd, 74th as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
INSTALLATION OF BASEMENT AND SHAFTWAY SYSTEM SCAFFOLD AS PER PLANS. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
RoofMMBC Major Market Broadcasting, Starbucks4p · 2 filings · 13 docs
ArchitectureMechanical
GENERAL CONSTRUCTION ON THE 81ST FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
MECHANICAL WORK IN THE SUBCELLAR, CELLAR, AND 1ST THROUGH 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
18 documents · 2 drawing sheets
Floor 90Empire State Building temporary exhibit1 filing · 7 docs
Architecture
Issued Permit Scope
General Construction
Install temp. inflatable on exterior of the Spire. No alteration to the existing structure for Empire State Building Spire Exhibit. Producer is responsible to monitor site safety & implement WAP. All production equipment removed upon event completion
On file for this project
7 documents
Floor 89
Floor 882p · 1 filing · 8 docs
Structural
STRUCTURAL WORK ON THE TOWER (88TH FL MARKETING) AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 2 drawing sheets
Floor 87Empire State Realty Trust1p · 1 filing · 5 docs
Mechanical
Issued Permit Scope
Mechanical Systems
Mechanical work on floors 81, 82, 85, 87 as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Floor 86Empire State Realty Trust1 filing · 5 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural
Structural modifications taking place to replace a small stair on the 86th floor as per plans filed herewith. No change in Use, Egress, or Occupancy.
On file for this project
5 documents
Floor 85McKay Brothers2p · 4 filings · 13 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Modifications to the existing HVAC System; Remove existing AC unit and install new units, install new intake and discharge louvers, exhaust fans, grilles and ductwork as per plans (Suites #7920, 8102b and 8516.) No change to use, egress or occupancy.
On file for this project
7 documents
Mechanical work on floors 81, 82, 85, 87 as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents
Mechanical modifications taking place on the 85th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 84
Floor 83
Floor 82Archdiocese1p · 2 filings · 10 docs
ArchitectureElectricalMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Mechanical work on floors 81, 82, 85, 87 as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents
GENERAL CONSTRUCTION ON THE 82ND FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
On file for this project
5 documents · 1 drawing sheet
Floor 81MMBC Major Market Broadcasting, National Weather ServiceUnder Construction6p · 9 filings · 13 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
Replacement of existing louver on the 81st floor in an existing window frame. No change to egress use or occupancy
On file for this project
13 documents · 1 drawing sheet
Modifications to the existing HVAC System; Remove existing AC unit and install new units, install new intake and discharge louvers, exhaust fans, grilles and ductwork as per plans (Suites #7920, 8102b and 8516.) No change to use, egress or occupancy.
On file for this project
7 documents
GENERAL CONSTRUCTION ON THE 81ST FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
Latest 3 of 9 filings on this floor.
Floor 80
Floor 79Kearney12p · 15 filings · 13 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL MODIFICATIONS TO THE 78TH AND 79TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
SPRINKLER AND STANDPIPE MODIFICATIONS TO THE 78TH AND 79TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
PLUMBING MODIFICATIONS TO THE 78TH AND 79TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 15 filings on this floor.
Floor 78Kearney11p · 11 filings · 13 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
STRUCTURAL MODIFICATIONS TO THE 78TH AND 79TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents
SPRINKLER AND STANDPIPE MODIFICATIONS TO THE 78TH AND 79TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
PLUMBING MODIFICATIONS TO THE 78TH AND 79TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 11 filings on this floor.
Floor 77Corridor restoration, multiple floors3p · 10 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on floors 31, 46 and 61 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 1 drawing sheet
Plumbing modifications taking place on the 77th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents
Sprinkler modifications taking place on the 77th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
3 documents
Latest 3 of 10 filings on this floor.
Floor 76Empire State Building suite refresh1p · 4 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
SPRINKLER MODIFICATIONS TAKING PLACE ON 76TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
PLUMBING MODIFICATIONS TAKING PLACE ON 76TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON 76TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 75Core Specialty, Nosten13p · 8 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents · 3 drawing sheets
General Construction Louver work taking place on the 75th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
Latest 3 of 8 filings on this floor.
Floor 74
Floor 73
Floor 72Astrazeneca Pharmaceuticals, Core Specialty6p · 12 filings · 13 docs
ArchitectureCivilFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
General Construction Louver work taking place on the 72nd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents
Structural modifications taking place on the 72nd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents
Sprinkler modifications taking place on the 72nd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 12 filings on this floor.
Floor 71Workday, Kaltex America +240p · 18 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Plumbing modifications taking place on the 71st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 1 drawing sheet
Sprinkler modifications taking place on the 71st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
3 documents · 1 drawing sheet
General Construction Louver work taking place on the 71st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 18 filings on this floor.
Floor 70Revman International2p · 2 filings · 11 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
GENERAL CONSTRUCTION TAKING PLACE ON THE 70TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
MECHANICAL WORK TAKING PLACE ON THE 70TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
Floor 69Core Specialty, Lutron Electronics Co9p · 10 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
Mechanical Modifications taking place on Floors 30, 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
12 documents
Latest 3 of 10 filings on this floor.
Floor 68Empire State Realty Trust45p · 10 filings · 13 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MECHANICAL WORK ON THE 68TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
Plumbing modifications taking place on the 68th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 1 drawing sheet
Sprinkler modifications taking place on the 68th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 10 filings on this floor.
Floor 67Core Specialty9p · 5 filings · 13 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
General Construction taking place on the 67th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents · 3 drawing sheets
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
Latest 3 of 5 filings on this floor.
Floor 66Booking Holdings5p · 5 filings · 13 docs
ArchitectureFire ProtectionGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
General Construction taking place on the 66th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
Mechanical modifications taking place on the 66th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 1 drawing sheet
Sprinkler modifications taking place on the 66th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 65Suite 6500 pre-built refresh5p · 4 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
General Construction taking place on the 65th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Mechanical modifications taking place on the 65th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
Plumbing modifications taking place on the 65th Floor as per plans filed herewith. No change in Use, Egress, or Occupancy.
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 64HNTBUnder Construction2p · 2 filings · 11 docs
ArchitectureFire ProtectionGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
General construction on the 64th floor as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
6 documents · 1 drawing sheet
Mechanical work on the 64th floor as plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Floor 63Hecker Fink, Kaplan Hecker & Fink13p · 10 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SPRINKLER MODIFICATIONS TO THE 62ND AND 63RD FLOOR AS PLANS FILED HEREWITH.NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
GENERAL CONSTRUCTION ON THE 62ND AND 63RD FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 4 drawing sheets
MECHANICAL WORK ON THE 62ND AND 63RD FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 10 filings on this floor.
Floor 62Hecker Fink17p · 6 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
SPRINKLER MODIFICATIONS TO THE 62ND AND 63RD FLOOR AS PLANS FILED HEREWITH.NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
PLUMBING WORK ON THE 62ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
GENERAL CONSTRUCTION ON THE 62ND AND 63RD FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 4 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 61Corridor restoration, multiple floors3 filings · 13 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Sprinkler modifications taking place on floors 31, 46 and 61 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents
General Construction taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Mechanical modifications taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Floor 60Goldman8p · 7 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
Mechanical Modifications taking place on Floors 30, 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
12 documents
Mechanical modifications taking place on the 60th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents
Latest 3 of 7 filings on this floor.
Floor 59Lutron Electronics Co9p · 12 filings · 13 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
SPRINKLER MODIFICATIONS TAKING PLACE ON 59TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
PLUMBING MODIFICATIONS TAKING PLACE ON THE 59TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
SPRINKLER MODIFICATIONS TAKING PLACE ON 59TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 12 filings on this floor.
Floor 58HNTBUnder Construction10p · 7 filings · 13 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING WORK FROM THE 56 TO THE 58TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 4 drawing sheets
General construction from the 56 thru the 58th floor as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
7 documents · 1 drawing sheet
Mechanical work from the 56th to the 58th floor as plans filed herewith. No change in use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 57HNTBUnder Construction7p · 7 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING WORK FROM THE 56 TO THE 58TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 4 drawing sheets
General construction from the 56 thru the 58th floor as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
7 documents
Mechanical work from the 56th to the 58th floor as plans filed herewith. No change in use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 56HNTBUnder Construction8p · 4 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING WORK FROM THE 56 TO THE 58TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 4 drawing sheets
General construction from the 56 thru the 58th floor as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
7 documents · 1 drawing sheet
Mechanical work from the 56th to the 58th floor as plans filed herewith. No change in use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 55Nosten5p · 6 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbingZ
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Project M50738171Signed-off · 03/29/2021
Sprinkler work taking place on the 55th floor as per plans filed herewith. No change in use, egress or occupancy.
Sprinkler work taking place on the 55th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents · 2 drawing sheets
Sprinkler work taking place on the 55th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
10 documents
Latest 3 of 6 filings on this floor.
Floor 54Corgan, Pio Plus19p · 16 filings · 13 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MECHANICAL WORK ON THE 54TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
PLUMBING MODIFICATIONS TO 54TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
SPRINKLER MODIFICATIONS TO THE 54TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 16 filings on this floor.
Floor 53
Floor 52Core Specialty3 filings · 13 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
Mechanical Modifications taking place on Floors 30, 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
12 documents
Floor 51ZS Associates5p · 6 filings · 8 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler work taking place on the 51st floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Plumbing work taking place on the 51st floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Mechanical work taking place on the 51st floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
7 documents · 3 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 50
Floor 49Workday3p · 3 filings · 13 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
General Construction taking place on the 49th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Plumbing modifications taking place on the 49th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
Sprinkler modifications taking place on the 49th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 1 drawing sheet
Floor 48Core Specialty10p · 3 filings · 13 docs
ArchitectureDMFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents · 3 drawing sheets
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents · 2 drawing sheets
Mechanical Modifications taking place on Floors 30, 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
12 documents · 5 drawing sheets
Floor 47Core Specialty2p · 11 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING MODIFICATIONS TAKING PLACE ON 47TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
Latest 3 of 11 filings on this floor.
Floor 46Empire State Realty Trust5p · 7 filings · 4 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on floors 31, 46 and 61 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 1 drawing sheet
General Construction taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Mechanical modifications taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 45Corridor restoration, multiple floors3 filings · 4 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Sprinkler modifications taking place on floors 31, 46 and 61 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents
General Construction taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Mechanical modifications taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Floor 44Starbucks5p · 12 filings
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING MODIFICATIONS TAKING PLACE ON 44TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
SPRINKLER MODIFICATIONS TAKING PLACE ON 44TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON 44TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents
Latest 3 of 12 filings on this floor.
Floor 43Lutron Electronics CoUnder Construction18p · 14 filings · 13 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on the 43rd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents · 1 drawing sheet
Plumbing modifications taking place on the 43rd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 3 drawing sheets
General Construction taking place on the 43rd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 6 drawing sheets
Latest 3 of 14 filings on this floor.
Floor 42Core Specialty11p · 8 filings
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler Modifications taking place on Floors 42, 47, 48, 52, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents · 2 drawing sheets
MECHANICAL WORK ON THE 42ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents
General Construction Modifications taking place on Floors 42, 47, 48, 52, 60, 67, 69, 71, 72, 75 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 41Corgan, Ti Funaro14p · 9 filings · 13 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on the 41st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 1 drawing sheet
Plumbing modifications taking place on the 41st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
Mechanical modifications taking place on the 41st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 40StarbucksUnder Construction46p · 14 filings · 13 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications taking place on the 40th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 1 drawing sheet
Plumbing modifications taking place on the 40th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents
Sprinkler modifications taking place on the 40th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 14 filings on this floor.
Floor 39Ti FunaroUnder Construction27p · 8 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Plumbing modifications taking place on the 39th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 3 drawing sheets
Sprinkler modifications taking place on the 39th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 3 drawing sheets
General Construction Louver work taking place on the 39th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 38Esrt_esbUnder Construction16p · 10 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Structural modifications taking place on the 38th and 39th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents
General Construction taking place on the 38th and 39th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents
Sprinkler modifications taking place on the 38th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 10 filings on this floor.
Floor 37Empire State Realty Trust31p · 11 filings
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL WORK ON 37TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
SPRINKLER WORK ON THE 37TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 2 drawing sheets
PLUMBING WORK ON THE 37TH FLOOR AS PLANS FILED HEREWITH, NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 3 drawing sheets
Latest 3 of 11 filings on this floor.
Floor 36
Floor 35Empire State Realty TrustUnder Construction9p · 5 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
GENERAL CONSTRUCTION FROM THE 33RD TO THE 35TH FLOORS AS PLANS FILED FOR HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
MECHANICAL WORK FROM THE 33RD TO THE 35TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 2 drawing sheets
PLUMBING WORK FROM THE 33RD TO THE 35TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 9 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 34Empire State Realty TrustUnder Construction9p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
GENERAL CONSTRUCTION FROM THE 33RD TO THE 35TH FLOORS AS PLANS FILED FOR HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
MECHANICAL WORK FROM THE 33RD TO THE 35TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 2 drawing sheets
GENERAL CONSTRUCTION FOR LOUVERS ON THE 34TH FL AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 33Empire State Realty TrustUnder Construction7p · 5 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
GENERAL CONSTRUCTION FROM THE 33RD TO THE 35TH FLOORS AS PLANS FILED FOR HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 3 drawing sheets
MECHANICAL WORK FROM THE 33RD TO THE 35TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 1 drawing sheet
PLUMBING WORK FROM THE 33RD TO THE 35TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 9 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 32Esrt_esb13p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe
STANDPIPE WORK ON THE 32ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
SPRINKLER WORK ON THE 32ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
10 documents · 2 drawing sheets
PLUMBING WORK ON THE 32ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
10 documents · 5 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 31Corridor restoration, multiple floors2p · 8 filings · 4 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Sprinkler modifications taking place on floors 31, 46 and 61 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents · 1 drawing sheet
Sprinkler modifications taking place on the 31st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
4 documents
General Construction taking place on floors 31, 45, 46, 61, 77 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Latest 3 of 8 filings on this floor.
Floor 30Empire State Realty Trust1p · 1 filing
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Mechanical work taking place on the 30th floor terrace as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Floor 29
Floor 28LinkedIn12p · 4 filings
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Sprinkler work taking place on the 28th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
10 documents · 4 drawing sheets
Mechanical work taking place on the 28th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents · 4 drawing sheets
Plumbing work taking place on the 28th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents · 3 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 27LinkedIn7p · 5 filings
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Sprinkler work taking place on the 27th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
13 documents · 2 drawing sheets
Plumbing work taking place on the 27th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents · 3 drawing sheets
Structural work taking place on the 27th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
13 documents
Latest 3 of 5 filings on this floor.
Floor 26
Floor 25
Floor 24Pontera17p · 17 filings · 14 docs
ArchitectureCivilDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING MODIFICATIONS TAKING PLACE ON 24TH FLOOR AS PER PLANS ATTACHED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
SPRINKLER MODIFICATIONS TAKING PLACE ON 24TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON 24TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 3 drawing sheets
Latest 3 of 17 filings on this floor.
Floor 2323rd Floor Louver and Window Work7p · 5 filings · 13 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
General Construction Louver work taking place on the 23rd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents · 2 drawing sheets
General Construction taking place on the 23rd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
8 documents · 7 drawing sheets
Mechanical modifications taking place on the 23rd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 22Booking Holdings17p · 7 filings · 7 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
SPRINKLER WORK ON THE 22ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
General Construction taking place on the 22nd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 1 drawing sheet
Mechanical modifications taking place on the 22nd Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 21
Floor 20Shutterstock7p · 4 filings · 13 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PLUMBING WORK ON THE 20TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents
SPRINKLER WORK ON THE 20TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
GENERAL CONSTRUCTION ON THE 20TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents · 7 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 19
Floor 18
Floor 17
Floor 16LinkedIn, Thornton Tomasetti31p · 9 filings · 13 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
SPRINKLER MODIFICATIONS TAKING PLACE ON 16TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
PLUMBING MODIFICATIONS TAKING PLACE ON 16TH FLOOR AS PER PLANS ATTACHED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
20 documents · 1 drawing sheet
GENERAL CONSTRUCTION TAKING PLACE ON 16TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
21 documents · 20 drawing sheets
Latest 3 of 9 filings on this floor.
Floor 15LinkedIn26p · 10 filings
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Mechanical work taking place on the 15th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents
Plumbing work taking place on the 15th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
12 documents
General construction work taking place on the 14th and 15th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
4 documents · 11 drawing sheets
Latest 3 of 10 filings on this floor.
Floor 14LinkedIn, Goldman21p · 11 filings
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
General construction work taking place on the 14th and 15th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
4 documents · 8 drawing sheets
Structural work taking place on the 14th and 15th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
13 documents · 1 drawing sheet
Sprinkler work taking place on the 14th and 15th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
7 documents · 4 drawing sheets
Latest 3 of 11 filings on this floor.
Floor 13Sprinkler system installation, 11th-13th floorsUnder Construction5p · 5 filings · 16 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on Floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
General Construction Louver work taking place on floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 1 drawing sheet
Mechanical modifications taking place on Floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Latest 3 of 5 filings on this floor.
Floor 12Sprinkler system installation, 11th-13th floorsUnder Construction5p · 5 filings · 16 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on Floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
General Construction Louver work taking place on floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 1 drawing sheet
Mechanical modifications taking place on Floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Latest 3 of 5 filings on this floor.
Floor 11STVUnder Construction21p · 16 filings · 16 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Sprinkler modifications taking place on Floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 2 drawing sheets
General Construction Louver work taking place on floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
5 documents · 1 drawing sheet
Mechanical modifications taking place on Floors 11, 12 and 13 as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Latest 3 of 16 filings on this floor.
Floor 10STV15p · 10 filings · 13 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
GENERAL CONSTRUCTION ON THE 10TH AND 11TH FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
12 documents · 6 drawing sheets
SPRINKLER WORK ON THE 10TH AND 11TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
STRUCTURAL WORK ON THE 10TH AND 11TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
14 documents · 1 drawing sheet
Latest 3 of 10 filings on this floor.
Floor 9
Floor 8
Floor 7GNY Insurance Companies19p · 13 filings
ArchitectureDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
General Construction Louver working taking place on the 7th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Structural modifications taking place on the 7th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents · 1 drawing sheet
Sprinkler modifications taking place on the 7th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
7 documents · 3 drawing sheets
Latest 3 of 13 filings on this floor.
Floor 6Starbucks, Centric Brands4p · 5 filings
ArchitectureDMFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
GENERAL CONSTRUCTION ON THE SUB, CEL, 1 THRU 2ND AND FROM 3RD TO 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
30 documents
STRUCTURAL WORK ON THE CELLAR AND 1ST THRU 2nd FLOORS AND 3RD TO 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
41 documents · 1 drawing sheet
MECHANICAL WORK IN THE SUBCELLAR, CELLAR, AND 1ST THROUGH 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
18 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 5Centric Brands, Starbucks +117p · 21 filings · 13 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers · Structural
Sprinkler modifications taking place on the 5th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
Mechanical modifications taking place on the 5th Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents
General Construction taking place on the 5th floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
14 documents · 5 drawing sheets
Latest 3 of 21 filings on this floor.
Floor 4Starbucks, Centric Brands +14p · 9 filings
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sign · Sprinklers · Structural
GENERAL CONSTRUCTION ON THE SUB, CEL, 1 THRU 2ND AND FROM 3RD TO 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
30 documents
STRUCTURAL WORK ON THE CELLAR AND 1ST THRU 2nd FLOORS AND 3RD TO 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
41 documents
MECHANICAL WORK IN THE SUBCELLAR, CELLAR, AND 1ST THROUGH 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
18 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 3LinkedIn, Starbucks +1Under Construction24p · 22 filings · 17 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers · Structural
SPRINKLER WORK ON THE 3RD FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
9 documents · 1 drawing sheet
PLUMBING WORK ON THE 3RD FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
GENERAL CONSTRUCTION ON THE 3rd FLOOR AS PLANS FILED FOR HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 7 drawing sheets
Latest 3 of 22 filings on this floor.
Floor 2Corgan, Starbucks +1Under Construction42p · 22 filings · 13 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers · Standpipe · Structural
PLUMBING WORK IN THE CELLAR (Concourse Marketing floor), 1ST AND 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
GENERAL CONSTRUCTION ON THE CELLAR (Concourse marketing floor), 1ST AND 2ND FLOORS AS PLANS FILED FOR HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 3 drawing sheets
MECHANICAL WORK IN THE CELLAR (Concourse marketing floor), 1ST AND 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 22 filings on this floor.
Floor 1FedExOffice, Alidoro +4Under Construction24p · 23 filings · 13 docs
ArchitectureDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sign · Sprinklers · Standpipe · Structural
INTERIOR ILLUMINATED NON-ADVERTISING ACCESSORY HANGING SIGN APPROVED UNDER NYC LANDMARK PRESERVATION COMMISSION PERMIT CNE# 26-11985 - IN PROPERTY LINES- FEDEX OFFICE. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Plumbing modifications taking place on the 1st Floor as per plans filed herewith. No change in Use, Egress or Occupancy.
On file for this project
6 documents
PLUMBING WORK IN THE CELLAR (Concourse Marketing floor), 1ST AND 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
Latest 3 of 23 filings on this floor.
MezzanineChipotle Mexican Grill, Starbucks3p · 13 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL WORK ON THE CELLAR AND 1ST THRU 2nd FLOORS AND 3RD TO 6TH FLOORS AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
41 documents · 1 drawing sheet
Mechanical work taking place in the cellar, mezzanine and 1st floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
GENERAL CONSTRUCTION WORK TAKING PLACE IN THE CELLAR, MEZZANINE AND 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 13 filings on this floor.
CellarCorgan, Empire State Building Amentities CenterUnder Construction25p · 24 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
PLUMBING WORK IN THE CELLAR (Concourse Marketing floor), 1ST AND 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
GENERAL CONSTRUCTION ON THE CELLAR (Concourse marketing floor), 1ST AND 2ND FLOORS AS PLANS FILED FOR HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
MECHANICAL WORK IN THE CELLAR (Concourse marketing floor), 1ST AND 2ND FLOOR AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 24 filings on this floor.
Sub-CellarCorgan, Empire State Building Amentities Center +219p · 17 filings · 14 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
MECHANICAL WORK ON THE 1ST, 2ND FLOOR, SUB CELLAR CONSTRUCTION (LOWER LEVEL MARKETING) AND CELLAR CONSTRUCTION FLOOR (CLUB LEVEL MARKETING FLOOR )AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
14 documents
MECHANICAL MODIFICATIONS TAKING PLACE AT SUB-CELLAR CONSTRUCTION (LOWER LEVEL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 3 drawing sheets
PLUMBING WORK IN THE SUB-CELLAR AND CELLAR CONSTRUCTION FLOOR (LOWER LEVEL AND CONCOURSE MARKETING FLOOR) AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
5 documents
Latest 3 of 17 filings on this floor.
Site & exteriorFedExOffice, Observatory +2Under Construction12 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Sign
ILLUMINATED NON-ADVERTISING ACCESSORY WALL SIGN APPROVED UNDER NYC LANDMARK PRESERVATION COMMISSION PERMIT CNE# 26-11985 - FEDEX OFFICE. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 2 drawing sheets
INSTALL EXTERIOR ILLUMINATED WALL SIGN (SUSHI BEAU)
On file for this project
4 documents · 1 drawing sheet
INSTALL EXTERIOR ILLUMINATED SIGN (OBSERVATORY TICKETS)
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 12 filings on this floor.
Filed — no permit issuedObservatory1 filing · 3 docs
Structural
INSTALL EXTERIOR ILLUMINATED SIGN (OBSERVATORY TICKETS)
On file for this project