| Owner | Filings | Most Recent |
|---|---|---|
| CPT 360 Lexington | 266 | 03/22/2026 |
| 59 Maiden Lane Associates | 183 | 10/15/2026 |
| Cassidy Turley | 99 | 03/21/2026 |
| Crown Properties | 7 | 03/21/2026 |
| 250 Park | 4 | 03/21/2026 |
| DTZ | 4 | 03/21/2026 |
| 360 Lexington Realty Assoicate | 3 | 03/21/2026 |
| 360 Lexington Avenue Properties Investment | 2 | 03/21/2026 |
| Amcap 360 | 1 | 03/22/2026 |
| Total Line Construction | 1 | 03/21/2026 |
| Meringoff Properties | 1 | 03/21/2026 |
| Winoker Realty Comp | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/14/2024 | $65.5M | — | 360 LEXINGTON AVENUE PROPERTY INVESTORS IV, LLC → AMCAP 360 LLC | $275/sf building |
| 08/19/2019 | $180.0M | — | — → — | $755/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Flushing | 3 | 10/20/2026 |
| Mdeas Architects | 15 | 10/13/2026 |
| MG Engineering | 63 | 10/06/2026 |
| Catapano Engineering | 2 | 09/25/2026 |
| Concessi Engineering | 3 | 08/17/2026 |
| Rimkus | 3 | 06/10/2026 |
| Raad | 1 | 06/08/2026 |
| GKV Architects | 1 | 03/02/2026 |
| Robert Derector Associates | 5 | 01/21/2026 |
| BXP | 1 | 10/23/2025 |
| Gilsanz Murray Steficek | 1 | 07/02/2025 |
| George J. Xerakias, PE | 1 | 05/23/2025 |
| Applied Design Initiative | 1 | 03/19/2025 |
| CFS Engineering | 6 | 11/03/2023 |
| Env Architects | 2 | 01/25/2023 |
| TPG Architecture | 8 | 11/29/2022 |
| HC Engineering | 1 | 05/19/2022 |
| Spector Group II | 2 | 10/19/2021 |
| Gace | 1 | 03/04/2021 |
| Ashraf | 2 | 05/28/2020 |
| Dooling & Company Architects | 1 | 04/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM Zoning | 63 | 03/21/2026 |
| Metropolis Group | 86 | 03/21/2026 |
| Green Light Expediting | 12 | 03/21/2026 |
| Empire City Consultants | 4 | 03/21/2026 |
| Kma Designs | 4 | 03/21/2026 |
| Codegreen | 6 | 03/21/2026 |
| Whidden Silver | 6 | 03/21/2026 |
| HS Design Studio | 2 | 03/21/2026 |
| JP Expedite | 2 | 03/21/2026 |
| AE Design Solution | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Savcon | General Contractor | 16 | 07/08/2026 |
| Plaza Construction | General Contractor | 15 | 07/08/2026 |
| Five Boro Associates | Fire Protection | 10 | 07/08/2026 |
| Affect Build | General Contractor | 8 | 07/08/2026 |
| Solution Mechanical Contng | Plumbing | 8 | 07/08/2026 |
| Vanquish Group | General Contractor | 7 | 07/08/2026 |
| Whalen Construction | General Contractor | 6 | 08/12/2026 |
| W5 Group | General Contractor | 5 | 05/15/2026 |
| Lawrence Exterior Restoration | Scaffold | 4 | 07/08/2026 |
| Armon Mechanical | Fire Protection | 4 | 07/08/2026 |
| Allertonfox Construction | General Contractor | 4 | 07/08/2026 |
| Armon Mechanical | Plumbing | 3 | 07/08/2026 |
| Everest Scaffolding | Scaffold | 3 | 07/08/2026 |
| Kings Group NY | Scaffold | 3 | 07/08/2026 |
| New Roc Contracting | General Contractor | 3 | 04/09/2026 |
| Advanced Plumbing, Mechanical & Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Hydronic Concepts NY Plumbing | Fire Protection | 2 | 07/08/2026 |
| American Standard P&H Cororp | Plumbing | 2 | 07/08/2026 |
| Signature Construction Group | General Contractor | 2 | 04/09/2026 |
| Bedrock Mechanical | Fire Protection | 1 | 09/29/2026 |
| Denko Mechanical | Fire Protection | 1 | 07/08/2026 |
| Enobrac Plumbing | Plumbing | 1 | 07/08/2026 |
| Enobrac Plumbing | Fire Protection | 1 | 07/08/2026 |
| Hydro Mechanical | Fire Protection | 1 | 10/09/2026 |
| Millennium Maintenance & Electrical | Electrical | 1 | 03/21/2026 |
| MCL NY Industries | Plumbing | 1 | 06/27/2026 |
| Metro Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Pace Plumbing | Plumbing | 1 | 07/08/2026 |
| Hydronic Concepts NY P&H | Plumbing | 1 | 07/08/2026 |
| Cedar Electrical Contractors | Electrical | 1 | 03/21/2026 |
| C.M. Richey Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Innovative Electrical Service | Electrical | 1 | 03/21/2026 |
| Executive Electl Services | Electrical | 1 | 03/22/2026 |
| Patriot Electric | Electrical | 1 | 03/21/2026 |
| Jimenez Luis | Electrical | 1 | 03/21/2026 |
| All City Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Katz Michael | Electrical | 1 | 03/21/2026 |
| L J Electrical Service | Electrical | 1 | 03/21/2026 |
| Metropolis Electric | Electrical | 1 | 03/22/2026 |
| A & M Electrical Service | Electrical | 1 | 03/21/2026 |
| Pugliese Frank | Electrical | 1 | 03/21/2026 |
| Rockmor Electric Enterprises | Electrical | 1 | 03/21/2026 |
| Savcon | Scaffold | 1 | 07/08/2026 |
| Signs Cad | Sign hanger | 1 | 07/08/2026 |
| A&A Plumbing | Plumbing | 1 | 09/24/2026 |
| Advanced Plumbing Mechanical | Plumbing | 1 | 07/08/2026 |
| American Standard Plumbing | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Flushing Engineering Service | 4373 | 3 | 10/20/2026 |
| Milrose Consultants | 2003 | 10 | 10/13/2026 |
| MG Engineering | 8546 | 32 | 10/06/2026 |
| Catapano Engineering & AR | 3235 | 2 | 09/25/2026 |
| C.M. Testing Laboratory | 1352 | 1 | 09/25/2026 |
| Concessi Engineering | 540 | 4 | 08/17/2026 |
| Raad | 7727 | 1 | 06/08/2026 |
| Gilsanz Murray Steficek | 240 | 4 | 12/09/2025 |
| George J. Xerakias, PE | 1658 | 1 | 05/23/2025 |
| MEP Inspections | 1102 | 8 | 11/03/2023 |
| Alan Margolin & Associates | 423 | 24 | 01/25/2023 |
| PSI Agency | 254 | 6 | 10/29/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | Hydro Mechanical | 10/08/2026 |
| DOB NOW | Sprinklers | Permit Issued | Bedrock Mechanical | 09/28/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 09/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Whalen Construction | 08/11/2026 |
| DOB NOW | Plumbing | Permit Issued | MCL NY Industries | 06/24/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Whalen Construction | 06/12/2026 |
| DOB NOW | Sprinklers | Permit Issued | Armon Mechanical | 05/29/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | Kings Group NY | 05/22/2026 |
| DOB NOW | General Construction | Permit Issued | W5 Group | 05/13/2026 |
| DOB NOW | Standpipe | Signed-off | American Standard P&H Cororp | 04/22/2026 |
| DOB NOW | Sprinklers | Signed-off | American Standard Plumbing | 03/27/2026 |
| DOB NOW | Plumbing | Signed-off | American Standard P&H Cororp | 03/27/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Signature Construction GR | 03/10/2026 |
| DOB NOW | General Construction | Signed-off | Signature Construction GR | 03/10/2026 |
| DOB NOW | Plumbing | Permit Issued | Armon Mechanical | 01/27/2026 |
| DOB NOW | Sprinklers | Permit Issued | Armon Mechanical | 01/27/2026 |
| DOB NOW | Plumbing | Permit Issued | Armon Mechanical | 01/25/2026 |
| DOB NOW | Sprinklers | Permit Issued | Armon Mechanical | 01/16/2026 |
| DOB NOW | Sprinklers | Permit Issued | Armon Mechanical | 01/16/2026 |
| DOB NOW | Plumbing | Permit Issued | Armon Mechanical | 01/16/2026 |
| DOB NOW | General Construction | Signed-off | Affect Build | 01/14/2026 |
| DOB NOW | General Construction | Signed-off | W5 Group | 01/14/2026 |
| DOB NOW | General Construction | Signed-off | Affect Build | 01/14/2026 |
| DOB NOW | General Construction | Signed-off | Affect Build | 01/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | W5 Group | 01/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Affect Build | 01/13/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Affect Build | 01/12/2026 |
| DOB NOW | Sprinklers | Permit Issued | Five Boro Associates | 01/09/2026 |
| DOB NOW | Plumbing | Signed-off | Solution Mechanical Contng | 01/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Affect Build | 01/09/2026 |
| DOB NOW | Structural | Permit Issued | New Roc Contracting | 01/08/2026 |
| DOB NOW | Sprinklers | Signed-off | Bent Mechanical | 01/06/2026 |
| DOB NOW | General Construction | Permit Issued | New Roc Contracting | 12/26/2025 |
| DOB NOW | Sprinklers | Signed-off | Bent Mechanical | 12/19/2025 |
| DOB NOW | Plumbing | Signed-off | Hydronic Concepts NY P&H | 12/19/2025 |
| DOB NOW | General Construction | Signed-off | Whalen Construction | 10/31/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Whalen Construction | 10/27/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Plaza Construction | 10/16/2025 |
| DOB NOW | Sprinklers | Signed-off | Five Boro Associates | 10/10/2025 |
| DOB NOW | General Construction | Signed-off | New Roc Contracting | 10/01/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/20/2026 | — | — | Heating and Air Conditioning Systems, Ventilation Systems | |
| 10/13/2026 | Permit Issued | W5 Group | Air Conditioning Systems, Heating Systems | |
| 06/08/2026 | Permit Issued | Whalen Construction | Air Conditioning Systems | Cooling Mitsubishi Electric PUY-AK18NL 18,000 BTU · Condensing Unit ×1 |
| 03/02/2026 | Signed-off | Signature Construction GR | Air Conditioning Systems, Heating Systems | |
| 01/21/2026 | Signed-off | Allertonfox Construction | Heating and Air Conditioning Systems | Heat / Cool |
| 01/07/2026 | Signed-off | Affect Build | Air Conditioning Systems, Heating Systems | |
| 01/02/2026 | Signed-off | Affect Build | Air Conditioning Systems | |
| 08/08/2025 | Signed-off | Plaza Construction | Air Conditioning Systems | Cooling Lg KUSAB121A 11,180 BTU · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/20/2026 | — | — | — |
| 10/13/2026 | Permit Issued | Bedrock Mechanical | Sprinkler System |
| 09/25/2026 | Permit Issued | Hydro Mechanical | 36 heads |
| 08/17/2026 | Signed-off | Bent Mechanical | — |
| 02/26/2026 | Signed-off | American Standard Plumbing | 94 heads, 1 outlets |
| 01/21/2026 | Signed-off | Five Boro Associates | Sprinkler System |
| 01/07/2026 | Permit Issued | Armon Mechanical | Sprinkler System |
| 01/02/2026 | Permit Issued | Armon Mechanical | Sprinkler System |
| 08/21/2025 | Signed-off | Five Boro Associates | 11 heads |
| 08/08/2025 | Signed-off | Metro Fire Protection | 24 heads |
| 01/25/2023 | — | — | 181 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/20/2026 | — | — | Water/Sanitary |
| 10/13/2026 | Permit Issued | A&A Plumbing | Water/Sanitary |
| 09/25/2026 | — | — | Water/Sanitary |
| 08/17/2026 | Signed-off | Hydronic Concepts NY P&H | Water/Sanitary |
| 03/02/2026 | Signed-off | American Standard P&H | Water/Sanitary |
| 01/21/2026 | Signed-off | Solution Mechanical Contng | Water/Sanitary |
| 01/07/2026 | Permit Issued | Armon Mechanical | Water/Sanitary |
| 01/02/2026 | Permit Issued | Armon Mechanical | Water/Sanitary |
| 08/21/2025 | — | — | — |
| 01/25/2023 | — | — | Water/Sanitary |
| 03/01/2021 | Signed-off | Pace Plumbing | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/16/2026 | Permit Issued | Five Borough Electric | 1 meters |
| 10/06/2026 | Permit Issued | Lion Electric | General Wiring |
| 07/06/2026 | Permit Issued | Jte Electrical Services | General Wiring |
| 03/31/2026 | Complete | Sunbird Electrical Contracting | General Wiring |
| 01/23/2026 | Permit Issued | Ennell Group Electric | General Wiring |
| 01/23/2026 | Permit Issued | Ennell Group Electric | General Wiring |
| 11/28/2025 | Complete | Modern Voltage NYC | General Wiring |
| 10/27/2025 | Permit Issued | Control Electrical Cont'g | General Wiring |
| 06/05/2025 | Permit Issued | High Quality Electric of NYC | — |
| 05/05/2025 | Complete | Executive Electl Services | General Wiring |
| 04/07/2025 | Complete | Mikoma Electric | General Wiring |
| 06/14/2022 | Complete | Metropolis Electric | General Wiring |
| 02/16/2022 | Complete | Metropolis Electric | General Wiring |
| 10/21/2021 | Complete | Freedom Electl & Data | General Wiring |
| 05/07/2021 | Complete | C.M. Richey Electrical Contracting | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/09/2025 | Permit Issued | MCL NY Industries | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | Signed-off | Kings Group NY | Scaffold, Sidewalk Shed |
| 04/10/2020 | Permit Issued | Lawrence Exterior Restoration | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/14/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/09/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/04/2026 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/02/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/02/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 05/08/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/08/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/04/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/22/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/05/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/02/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/29/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/29/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/24/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/17/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/15/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/15/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/24/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/21/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/06/2026 | Energy Code Compliance Inspections | KY FU | progress |
| 10/06/2026 | HVAC-R and service water heating equipment | KY FU | energy_progress |
| 10/06/2026 | HVAC-R and service water heating system controls | KY FU | energy_progress |
| 10/06/2026 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 10/06/2026 | Duct leakage testing, insulation and design | KY FU | energy_progress |
| 10/06/2026 | Shutoff dampers | KY FU | energy_progress |
| 10/06/2026 | Post-installed Anchors | KY FU | special |
| 10/05/2026 | HVAC-R and service water heating system controls | Peter Gerazounis | energy_progress |
| 10/05/2026 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 10/05/2026 | Final | Michael Zaborski | progress |
| 10/05/2026 | Energy Code Compliance Inspections | KY FU | progress |
| 10/05/2026 | Fire-Resistance Rated Construction | Benjamin Plotnick | progress |
| 10/05/2026 | Lighting controls | KY FU | energy_progress |
| 10/05/2026 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 10/05/2026 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 10/05/2026 | HVAC-R and service water piping design and insulation | Peter Gerazounis | energy_progress |
| 10/05/2026 | Fire-Resistant Penetrations and Joints | Benjamin Plotnick | special |
| 10/05/2026 | HVAC-R and service water heating equipment | Peter Gerazounis | energy_progress |
| 10/05/2026 | Interior lighting power | KY FU | energy_progress |
| 09/25/2026 | Fire-Resistant Penetrations and Joints | JOHN CATAPANO | special |
| 09/25/2026 | Fire-Resistant Penetrations and Joints | JOHN CATAPANO | special |
| 09/08/2026 | Final | KY FU | progress |
| 09/08/2026 | Mechanical Systems | KY FU | special |
| 09/04/2026 | Final | KY FU | progress |
| 08/20/2026 | Sprinkler Systems | Robert Concessi | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Starbucks | Restaurant / Food Service | Floor 1 | Project M01363908 Project M01363923 |
| Amtrust Re | Office | Floor 8 | Project M01335913 |
| Webster Bank | Bank / Financial branch | Floors 5, 6 | Project M01295741 |
| Signers | Office | Floors 13, 14 | Project M01185321 |
| Savanna | Office | Floors 4, 6, 15, 23 | Project M00803469 Project M00803968 Project M00804047 Project M00804062 Project M08036542 Project M00730414 Project M00730499 Project M00730540 Project M00651524 Project M00651612 Project M00651630 Project M00651633 |
| Makimai Sushi | Restaurant / Food Service | Floor 1 | Project M00741118 |
| K&LGroup | Office | Floor 2 | Project M00451906 Project M00451882 Project M00452189 Project M00452213 Project M00477393 |
| Cushman & Wakefield | Office | Floor 18 | Project M00196055 |