| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/30/2019 | $1.6M | — | Private party → Private party | $967/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FIRMITAS ENGR'G & STRC'T DSG'N PLLC | 3 | 12/23/2024 |
| FILAMENT ARCHITECTURE STUDIO, PLLC | 6 | 07/16/2024 |
| WILLIAM F. RYAN, JR. P.E. PC | 2 | 06/03/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BURNHAM NATIONWIDE INC | 10 | 03/21/2026 |
| JENNY FLORES EXPEDITING | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JOHN HLAD P & H CO., INC | Plumbing | 6 | 07/08/2026 |
| EXCELLENT CONTRACTING LLC | General Contractor | 5 | 07/08/2026 |
| EXCELLENT GENERAL CONTRA* | General Contractor | 3 | 03/21/2026 |
| MARTIN PLG & HTG INC | Plumbing | 3 | 07/08/2026 |
| PALONE BROTHERS AIR | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACE STRUCTURAL ENGINEERIN | 496 | 4 | 12/23/2024 |
| FILAMENT ARCHITECTURE STU | 8909 | 2 | 07/16/2024 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 06/03/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | EXCELLENT GENERAL CONTRA* | 05/28/2025 |
| DOB NOW | General Construction | Signed-off | EXCELLENT CONTRACTING LLC | 07/30/2024 |
| DOB NOW | Plumbing | Signed-off | JOHN HLAD P & H CO., INC | 06/21/2024 |
| DOB NOW | General Construction | Signed-off | EXCELLENT CONTRACTING LLC | 06/12/2024 |
| DOB NOW | General Construction | Signed-off | EXCELLENT CONTRACTING LLC | 11/09/2023 |
| DOB NOW | Plumbing | Signed-off | MARTIN PLG & HTG INC | 12/29/2020 |
| DOB NOW | Mechanical Systems | Signed-off | PALONE BROTHERS AIR | 07/23/2020 |
| DOB NOW | Plumbing | Signed-off | MARTIN PLG & HTG INC | 07/14/2020 |
| BIS | OT | ISSUED | GRD CONSTRUCTION INC | 08/26/2020 |
| BIS | OT | ISSUED | GRD CONSTRUCTION INC | 06/29/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2020 | Complete | SUPER CHARGED ELEC. INC. | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/18/2025 | Masonry | ANTHONY UGBEBOR | special |
| 04/18/2025 | Final | ANTHONY UGBEBOR | progress |
| 04/18/2025 | Concrete - Cast-In-Place | ANTHONY UGBEBOR | special |
| 04/18/2025 | Subgrade Inspections | ANTHONY UGBEBOR | special |
| 12/16/2024 | Final | ANTHONY UGBEBOR | progress |
| 12/16/2024 | Masonry | — | special |
| 12/16/2024 | Subgrade Inspections | — | special |
| 12/16/2024 | Concrete - Cast-In-Place | ANTHONY UGBEBOR | special |
| 07/25/2024 | Final | MICHELLE KROCHMAL | progress |
| 07/25/2024 | Fire-Resistant Penetrations and Joints | MICHELLE KROCHMAL | special |
| 07/05/2024 | Fire-Resistant Penetrations and Joints | MICHELLE KROCHMAL | special |
| 07/05/2024 | Final | ANTHONY UGBEBOR | progress |
| 07/05/2024 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 07/05/2024 | Subgrade Inspections | — | special |
| 07/05/2024 | Masonry | — | special |
| 07/05/2024 | Concrete - Cast-In-Place | ANTHONY UGBEBOR | special |
| 07/05/2024 | Final | MICHELLE KROCHMAL | progress |
| 06/04/2021 | HVAC and service water heating system controls | William Ryan | energy_progress |
| 06/04/2021 | Mechanical Systems | William Ryan | special |
| 06/04/2021 | Final | William Ryan | progress |
| 06/04/2021 | HVAC insulation and sealing | William Ryan | energy_progress |
| 06/04/2021 | Maintenance information | William Ryan | energy_progress |
| 06/04/2021 | HVAC and service water heating equipment | William Ryan | energy_progress |
| 06/02/2021 | Mechanical Systems | William Ryan | special |
| 06/02/2021 | HVAC and service water heating system controls | William Ryan | energy_progress |