| Owner | Filings | Most Recent |
|---|---|---|
| TWO TREES MANAGEMENT | 114 | 07/08/2026 |
| 45 MAIN ASSOCIATES | 17 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | 5 | 03/22/2026 |
| 50 WEST 23RD ST A B | 15 | 03/22/2026 |
| 50 W 23RD ST A LLC | 1 | 03/22/2026 |
| 50 WEST 23 ST A LLC | 1 | 03/22/2026 |
| MATAWA | 1 | 03/22/2026 |
| MATANA | 33 | 03/22/2026 |
| NEW GREEN 50 W 23 REALTY | 2 | 03/22/2026 |
| S L GREEN REAL ESTATE | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| B2 ENGINEERING PC | 9 | 06/02/2026 |
| MARCO GIARDINA ARCHITECTURE, PLLC | 2 | 08/25/2025 |
| PATTI & ANTHES CONSULTING ENGINEERS | 4 | 08/21/2025 |
| THE BROOKLYN STUDIO | 7 | 07/25/2025 |
| JOHN F. GIUSEFFI, ARCHITECT, PC | 2 | 01/27/2025 |
| CATAPANO ENGINEERING PC | 11 | 02/29/2024 |
| LILKER ASSOCIATES CONSULTING ENGINE | 4 | 11/04/2022 |
| KZ ENGINEERING, P.C | 2 | 03/02/2022 |
| INSIGHT STUDIO ARCHITECTURE PC | 2 | 01/28/2022 |
| JOEL PHAGOO P.E. PLLC | 1 | 05/18/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 27 | 03/21/2026 |
| CATAPANO ENGINEERING | 22 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| CBA CONSULTANTS | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ONE MAIN CONSTRUCTION | General Contractor | 22 | 07/08/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 7 | 07/08/2026 |
| ACC CONSTRUCTION CORP | General Contractor | 6 | 03/21/2026 |
| CS BRIDGE CORP | General Contractor | 4 | 03/21/2026 |
| CAPITOL FIRE SPRINKLER | Plumbing | 3 | 03/22/2026 |
| TOP PLUMBING AND HEATING | Plumbing | 3 | 07/08/2026 |
| CARA PLUMBING GROUP INC | Plumbing | 3 | 07/08/2026 |
| WATERFIRE INC | Plumbing | 2 | 07/08/2026 |
| LB GENERAL CONTRACTING CO | General Contractor | 2 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 2 | 03/21/2026 |
| ANCO ELECTL CONTCTNG INC | Electrical | 2 | 03/22/2026 |
| ENOBRAC PLUMBING, INC | Fire Protection | 1 | 07/08/2026 |
| ENOBRAC PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| MORELAND CONSTRUCTION GR* | General Contractor | 1 | 04/09/2026 |
| CAPITOL FIRE SPRINKLER CO | Fire Protection | 1 | 07/08/2026 |
| JOSEPH BRAMAN | Electrical | 1 | 03/21/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| JOSEPH WEINSTEIN ELECTRIC | Electrical | 1 | 03/22/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| PRECISION SPKLR SVCS LLC | Fire Protection | 1 | 07/08/2026 |
| MILL BROOK FIRE PROTECTION | Fire Protection | 1 | 07/08/2026 |
| LEVINE, GEORGE | Fire Protection | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOMANI INSPECTION SERVICE | 843 | 6 | 08/25/2025 |
| THE BROOKLYN STUDIO OF AR | 2684 | 4 | 07/25/2025 |
| ALAN MARGOLIN & ASSOC | 423 | 1 | 01/27/2025 |
| CATAPANO ENGINEERING & AR | 3235 | 10 | 02/29/2024 |
| C.M. TESTING LABORATORY, | 1352 | 1 | 05/23/2023 |
| LILKER ASSOCIATES CONSULT | 816 | 5 | 11/04/2022 |
| B2 ENGINEERING D.P.C. | 5433 | 3 | 08/16/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 10/30/2025 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 10/29/2025 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 09/04/2025 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 07/28/2025 |
| DOB NOW | Sprinklers | Signed-off | CAPITOL FIRE SPRINKLER CO | 06/13/2025 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 05/12/2025 |
| DOB NOW | Plumbing | Signed-off | TOP PLUMBING AND HEATING | 04/17/2025 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 03/31/2025 |
| DOB NOW | Mechanical Systems | Signed-off | LB GENERAL CONTRACTING CO | 03/18/2025 |
| DOB NOW | General Construction | Signed-off | LB GENERAL CONTRACTING CO | 03/17/2025 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 03/10/2025 |
| DOB NOW | General Construction | Signed-off | MORELAND CONSTRUCTION GR* | 02/19/2025 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 08/03/2023 |
| DOB NOW | Sprinklers | Signed-off | LEGUCI PIPING&HEATING LLC | 08/01/2023 |
| DOB NOW | General Construction | Signed-off | ACC CONSTRUCTION CORP | 06/26/2023 |
| DOB NOW | Construction Fence | Signed-off | ACC CONSTRUCTION CORP | 06/24/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ACC CONSTRUCTION CORP | 06/24/2023 |
| DOB NOW | Sprinklers | Signed-off | PRECISION SPKLR SVCS LLC | 09/07/2022 |
| DOB NOW | Plumbing | Signed-off | WATERFIRE INC | 08/22/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | ONE MAIN CONSTRUCTION | 08/19/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 06/30/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 06/30/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 06/21/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 06/21/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 06/03/2022 |
| DOB NOW | Plumbing | Signed-off | ENOBRAC PLUMBING, INC | 06/03/2022 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 06/03/2022 |
| DOB NOW | Mechanical Systems | Signed-off | CLUNE CONSTRUCTION CO LP | 05/25/2022 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 05/23/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 03/04/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 03/04/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CS BRIDGE CORP | 03/02/2022 |
| DOB NOW | General Construction | Signed-off | ONE MAIN CONSTRUCTION | 02/24/2022 |
| DOB NOW | General Construction | Signed-off | CLUNE CONSTRUCTION CO LP | 02/22/2022 |
| DOB NOW | General Construction | Permit Issued | ONE MAIN CONSTRUCTION | 06/14/2021 |
| DOB NOW | Plumbing | Signed-off | WATERFIRE INC | 02/25/2020 |
| DOB NOW | Mechanical Systems | Signed-off | ONE MAIN CONSTRUCTION | 11/12/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | CS BRIDGE CORP | 11/16/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 05/21/2018 |
| BIS | EQ | ISSUED | ONE MAIN CONSTRUCTION | 01/29/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/02/2026 | Signed-off | CARA PLUMBING GROUP INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Permit Issued | POWER SURGE ELECTRIC, INC | General Wiring |
| 03/19/2025 | Complete | P & Z ELECTRIC CORP | General Wiring |
| 01/21/2025 | Complete | DAVEN ELECTRIC CORP | — |
| 03/15/2024 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | 5 meters |
| 02/08/2024 | Permit Issued | OMD ELECTRICAL CORP | 1 meters, 1 new_meters |
| 11/02/2023 | Complete | ANCO ELECTL CONTCTNG INC | General Wiring |
| 03/17/2023 | Permit Issued | OMD ELECTRICAL CORP | 1 meters, 1 new_meters |
| 07/28/2022 | Permit Issued | INTERSTATE ELECTRIC, LLC | General Wiring |
| 07/22/2022 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 06/03/2022 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 02/25/2022 | Complete | NASH ELECTRIC SERVICES IN | — |
| 02/19/2020 | Complete | AXCEL ELECTRIC CO., INC. | — |
| 02/25/2019 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 11/14/2018 | Complete | NASH ELECTRIC SERVICES IN | — |
| 05/18/2018 | Complete | ANTHONY G FERRY INC | Lighting |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/17/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/16/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/10/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/29/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/09/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/13/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/31/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/31/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/09/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/12/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/06/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/05/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/02/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/18/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/26/2025 | Final | MARCO GIARDINA | progress |
| 08/26/2025 | Fire-Resistance Rated Construction | JOHN MCMONAGLE | progress |
| 08/26/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/15/2025 | Fire-Resistance Rated Construction | Brendan Coburn | progress |
| 07/15/2025 | Fire-Resistant Penetrations and Joints | Brendan Coburn | special |
| 07/11/2025 | Fire-Resistant Penetrations and Joints | Brendan Coburn | special |
| 07/11/2025 | Fire-Resistance Rated Construction | Brendan Coburn | progress |
| 07/03/2025 | Final | Brendan Coburn | progress |
| 06/16/2025 | Final | Brendan Coburn | progress |
| 05/22/2025 | Fire-Resistant Penetrations and Joints | Brendan Coburn | special |
| 05/22/2025 | Fire-Resistance Rated Construction | Brendan Coburn | progress |
| 05/22/2025 | Final | Brendan Coburn | progress |
| 04/15/2025 | Final | John Anthes | progress |
| 04/15/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 04/15/2025 | Mechanical Systems | JOHN MCMONAGLE | special |
| 04/15/2025 | Fire-Resistance Rated Construction | JOHN MCMONAGLE | progress |
| 04/15/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 04/15/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 04/15/2025 | Final | MARCO GIARDINA | progress |
| 03/21/2025 | Fire-Resistance Rated Construction | Brendan Coburn | progress |
| 03/21/2025 | Fire-Resistant Penetrations and Joints | Brendan Coburn | special |
| 03/21/2025 | Final | Brendan Coburn | progress |
| 02/25/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 02/25/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 02/25/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Perspire Studios | Retail | Floor 1 | Project M01164280 |
| BuzzFeed | Office | Floors 5, 6 | Project M01176421 |
| Trustpilot | Office | Floor 10 | Project M01167554 |
| Bizzabo | Office | Floor 9 | Project M00726208 Project M00726219 |