| Owner | Filings | Most Recent |
|---|---|---|
| New York City Housing Authority | 42 | 08/30/2026 |
| Zoria Housing | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Dewberry Engineers | 5 | 05/26/2026 |
| Shenoy Engineering | 3 | 07/24/2025 |
| Synergy Strategic Design Architects | 3 | 07/25/2024 |
| Self Propriety (MD A Islam) | 5 | 07/24/2024 |
| Ronnette Riley Architect | 1 | 05/06/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Municipal Building Consultants | 5 | 03/21/2026 |
| Neris | 4 | 03/21/2026 |
| Synergy Strategic Design Architects | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Kordun Construction | General Contractor | 11 | 07/08/2026 |
| J & N Construction Group | General Contractor | 5 | 04/09/2026 |
| J & N Construction Group | Scaffold | 3 | 07/08/2026 |
| Kordun Construction | Plumbing | 3 | 07/08/2026 |
| Jemco Electric Contractors | Electrical | 1 | 03/22/2026 |
| D.D.S. Mechanical PBG & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Bureau Veritas Na | 6902 | 7 | 07/24/2025 |
| MP Engineers & Architects | 1438 | 3 | 07/25/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Kordun Construction | 05/21/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Kordun Construction | 05/21/2026 |
| DOB NOW | Plumbing | Signed-off | Kordun Construction | 02/03/2026 |
| DOB NOW | General Construction | Signed-off | J & N Construction Group | 12/19/2025 |
| DOB NOW | Plumbing | Signed-off | D.D.S. Mechanical PBG & Heating | 08/08/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Kordun Construction | 04/10/2025 |
| DOB NOW | General Construction | Signed-off | Kordun Construction | 04/10/2025 |
| DOB NOW | Plumbing | Signed-off | Kordun Construction | 01/29/2025 |
| DOB NOW | General Construction | Signed-off | J & N Construction Group | 08/15/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | J & N Construction Group | 05/15/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | J & N Construction Group | 05/08/2024 |
| DOB NOW | Supported Scaffold | Signed-off | J & N Construction Group | 04/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Kordun Construction | 04/04/2024 |
| DOB NOW | General Construction | Signed-off | Kordun Construction | 04/04/2024 |
| DOB NOW | General Construction | Signed-off | Kordun Construction | 12/05/2023 |
| DOB NOW | Plumbing | Signed-off | Kordun Construction | 12/04/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Kordun Construction | 12/04/2023 |
| BIS | EQ | ISSUED | Zoria Housing | 08/07/2015 |
| BIS | EQ | ISSUED | Vikrant Contracting & Builder | 08/03/2015 |
| BIS | EQ | ISSUED | Zoria Housing | 08/03/2015 |
| BIS | OT | ISSUED | Zoria Housing | 07/07/2015 |
| BIS | EQ | ISSUED | AMC United | 01/30/2002 |
| BIS | PL | ISSUED | Olimpia Mechanical | 05/20/1999 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/29/2021 | Signed-off | Kordun Construction | Ventilation Systems | Ventilation Greenheck AER-S20C 1,000 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2026 | Signed-off | Kordun Construction | Gas, Water/Sanitary |
| 07/24/2025 | Signed-off | D.D.S. Mechanical PBG & Heating | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2024 | Permit Issued | Aujla Electric | — |
| 04/26/2024 | Complete | A.T.J. Electrical Co | General Wiring |
| 06/26/2023 | Permit Issued | Meco Electric Co | General Wiring |
| 04/25/2021 | Complete | City Grid Electric | General Wiring |
| 04/08/2021 | Complete | City Grid Electric | General Wiring |
| 08/15/2018 | Complete | Jemco Electric Contractors | General Wiring |
| 07/23/2018 | Complete | Zena Electric | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/25/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/01/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/05/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/25/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/23/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/05/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/02/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/18/2025 | Tenant Protection Plan Compliance | — | special |
| 07/18/2025 | Post-installed Anchors | IBRAHIM MOURAD | special |
| 07/18/2025 | Fire-Resistant Penetrations and Joints | IBRAHIM MOURAD | special |
| 04/30/2025 | Tenant Protection Plan Compliance | — | special |
| 04/30/2025 | Post-installed Anchors | — | special |
| 04/30/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 03/03/2025 | Structural Cold-Formed Steel | IBRAHIM MOURAD | special |
| 03/03/2025 | Concrete - Cast-In-Place | IBRAHIM MOURAD | special |
| 03/03/2025 | Final | IBRAHIM MOURAD | progress |
| 10/04/2024 | Structural Cold-Formed Steel | — | special |
| 07/30/2024 | Final | IBRAHIM MOURAD | progress |
| 07/30/2024 | Concrete - Cast-In-Place | IBRAHIM MOURAD | special |
| 06/27/2024 | Post-installed Anchors | JAMES WILSON | special |
| 06/27/2024 | Masonry | JAMES WILSON | special |
| 06/27/2024 | Fire-Resistant Penetrations and Joints | JAMES WILSON | special |
| 06/27/2024 | Insulation placement and R values | JAMES WILSON | energy_progress |
| 06/27/2024 | Air barrier - visual inspection | JAMES WILSON | energy_progress |
| 06/27/2024 | Structural Stability – Alterations of existing buildings | JAMES WILSON | special |
| 01/28/2021 | Final | IBRAHIM MOURAD | progress |
| 01/28/2021 | Mechanical Systems | IBRAHIM MOURAD | special |