RoofUnder Construction7p · 3 filings · 16 docs
ArchitectureGeneralOther
General construction modifications on 22nd floor (ext.) as per plans filed herewith.
On file for this project
5 documents · 5 drawing sheets
FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
Structural modifications taking place on the 22nd floor as per plans filed herewith.
On file for this project
8 documents · 1 drawing sheet
Floor 31Under Construction16p · 5 filings · 18 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
Project M01446045Permit Issued · 09/30/2026
Architectural modifications taking place on the 31st floor as per plans filed herewith. No change in use, egress or occupancy.
Sprinkler modifications taking place on the 21st and 31st floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 3 drawing sheets
Mechanical modifications taking place on the 21st and 31st floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 30Under Construction47p · 1 filing · 13 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler modifications taking place on the 30th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
13 documents · 9 drawing sheets
Floor 29Under Construction31p · 7 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Architectural modifications taking place on the 19th and 29th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents · 5 drawing sheets
Mechanical modifications taking place on the 19th and 29th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Sprinkler modifications taking place on the 19th and 29th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 288p · 4 filings · 20 docs
ArchitectureDMElectricalGeneralPlumbing
Modification of existing Sprinkler system per plans filed herewith. No change to use, occupancy, or egress
On file for this project
7 documents · 2 drawing sheets
Modification of existing plumbing system per plans filed herewith
On file for this project
3 documents · 2 drawing sheets
Modification of 19th and 28th floors per plans filed herewith. No change to use, occupancy, or egress
On file for this project
8 documents · 7 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 271p · 1 filing · 3 docs
Fire Protection
install 56 sprinkler heads on existing sprinkler system at 27th floor . no change in use, egress oroccupancy.
On file for this project
3 documents · 1 drawing sheet
Floor 264p · 2 filings · 13 docs
Fire ProtectionMechanical
Sprinkler modifications taking place on the 26th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
7 documents · 2 drawing sheets
Mechanical modifications taking place on the 26th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Floor 25
Floor 24
Floor 23
Floor 22Under Construction12p · 8 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
General construction modifications on 22nd floor (ext.) as per plans filed herewith.
On file for this project
5 documents
General construction modifications on the 22nd floor (ext.) as per plans filed herewith.
On file for this project
9 documents · 1 drawing sheet
Structural modifications taking place on the 22nd floor as per plans filed herewith.
On file for this project
8 documents
Latest 3 of 8 filings on this floor.
Floor 2114p · 4 filings · 18 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbing
Sprinkler modifications taking place on the 21st and 31st floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Mechanical modifications taking place on the 21st and 31st floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Plumbing modifications taking place on the 21st and 31st floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 202p · 2 filings · 12 docs
GeneralPlumbing
Modification of existing plumbing per plans filed herewith
On file for this project
5 documents · 1 drawing sheet
Modification of 20th floor per plans filed herewith
On file for this project
7 documents · 1 drawing sheet
Floor 19Under Construction29p · 8 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Architectural modifications taking place on the 19th and 29th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents · 6 drawing sheets
Mechanical modifications taking place on the 19th and 29th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
6 documents · 3 drawing sheets
Sprinkler modifications taking place on the 19th and 29th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14Under Construction7p · 2 filings · 20 docs
ArchitectureDMFire ProtectionGeneralPlumbing
Issued Permit Scope
Plumbing
Sprinkler modifications taking place on the 14th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
13 documents · 5 drawing sheets
NYULH - MEN'S HEALTH CENTER EXPANSION - PLUMBING MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
16 documents
Floor 13
Floor 12
Floor 11
Floor 101p · 1 filing · 12 docs
Architecture
REMOVAL AND INSTALL WALLS, DOORS, FLOORS FINISHES AND CEILINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
12 documents · 1 drawing sheet
Floor 91p · 1 filing · 8 docs
Structural
Modification of 8th floor per plans filed herewith
On file for this project
8 documents · 1 drawing sheet
Floor 87p · 4 filings · 13 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Modification of 8th floor Sprinkler/standpipe systems per plans filed herewith
On file for this project
4 documents · 2 drawing sheets
Modification of 8th floor plumbing per plans filed herewith
On file for this project
3 documents · 2 drawing sheets
Modification of 8th floor per plans filed
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 7
Floor 6
Floor 558p · 9 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingOther
MODIFICATION OF EXISTING SPRINKLER PLANS AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 6 drawing sheets
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 6 drawing sheets
INTERIOR RENOVATION OF 5TH FLOOR AND NEW STAIR CONNECTING 4TH AND 5TH FLOOR AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 29 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 418p · 5 filings · 20 docs
ArchitectureDMMechanicalPlumbing
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES AND RELATED PIPING AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 6 drawing sheets
INTERIOR RENOVATION OF 5TH FLOOR AND NEW STAIR CONNECTING 4TH AND 5TH FLOOR AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 3 drawing sheets
REMOVAL AND INSTALLATION OF DUCT WORK, DIFFUSERS, FANS, A/C UNIT AND RELATED MECHANICAL PIPING AS SHOWN ON PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 4 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 312p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
MODIFICATION TO EXISTING SPRINKLER SYSTEM AND RELATED PIPING AS SHOWN ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 2 drawing sheets
REMOVAL AND INSTALL WALLS, DOORS, FLOORS FINISHES AND CEILINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
12 documents · 4 drawing sheets
REMOVAL AND INSTALLATION OF DUCT WORK, DIFFUSERS, FANS, A/C UNITS AND RELATED MECHANICAL PIPING AS SHOWN ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 6 drawing sheets
Floor 223p · 8 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
NYULH - MEN'S HEALTH CENTER EXPANSION - PLUMBING MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
16 documents · 7 drawing sheets
STRUCTURAL STEEL SUPPORT AND REINFORCEMENT OF EXISTING FRAMING FOR NEW EXTERIOR MARQUEE; NEW CONCRETE SLAB BUILD-UPS AT FIRST FLOOR; CONCRETE HOUSEKEEPING PAD INSTALLATION BELOW NEW MEP EQUIPMENT, NO CHANGE TO USE , EGRESS, OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Modification of 1st-3rd floors and Mez as per plans filed herewith.
On file for this project
22 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 150p · 13 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Plumbing · Sprinklers
INTERIOR RENOVATION OF PARTITIONS, CEILING, DOORS AND FINISHES AS SHOWN ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 12 drawing sheets
INSTALLATION OF A/C UNITS, DUCTWORK, DIFFUSERS AND RELATED PIPING AS SHOWN ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
11 documents · 6 drawing sheets
MODIFICATION OF EXISTING SPRINKLER SYSTEM AND RELATED PIPING AS SHOWN ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
10 documents · 5 drawing sheets
Latest 3 of 8 filings on this floor.
Mezzanine1p · 1 filing · 20 docs
Structural
Modification of 1st-3rd floors and Mez as per plans filed herewith.
On file for this project
22 documents · 1 drawing sheet
Cellar12p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES AND RELATED PIPING AND DRAINAGE FOR MARQUEE AS SHOWN ON DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
12 documents · 1 drawing sheet
MODIFY SPRINKLER SYSTEM AS PER PLANS. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
3 documents · 1 drawing sheet
Modification of ground floor per plans filed herewith
On file for this project
5 documents · 4 drawing sheets
Latest 3 of 4 filings on this floor.
Sub-Cellar1p · 1 filing · 11 docs
Structural
Modification of Cellar and Sub-Cellar per plans filed herewith. No change in use, egress or occupancy.
On file for this project
11 documents · 1 drawing sheet