Office with commercial, 7-19 stories
Rockefeller Center
610 5TH AVENUE · BIN 1082656
💬 Discuss this project
1937Year Built
9Stories
O6Building Class
C5-2.5Zoning
272,637 sfGross Floor Area
61Units
LL97 Covered1 Active Violation ▸FISP: SAFE
Office with commercial, 7-19 stories · Owner of record: Rcpi Landmark Properties, LLC Attn: Tracey Frazzetta · 63,261 sf lot · 4.31 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofTerrace Alt 2 plumbing demolitionUnder Construction27p · 13 filings · 20 docs
Floor 8Roof antenna and equipment installation1 filing · 4 docs
Floor 7Terrace Alt 2 plumbing demolitionUnder Construction31p · 20 filings · 20 docs
Floor 6L CattertonUnder Construction65p · 8 filings · 20 docs
Floor 5L Catterton87p · 12 filings · 20 docs
Floor 4Hamilton Lane, L CattertonUnder Construction79p · 15 filings · 20 docs
Floor 3Staples58p · 8 filings · 20 docs
Floor 2
Floor 1Capri Holdings, Michael Kors +384p · 16 filings · 20 docs
CellarCapri Holdings, Aesop +1149p · 35 filings · 20 docs
Sub-CellarAtomix, Tishman Speyer Sea Grill84p · 11 filings · 20 docs
Sub-BasementRoof antenna and equipment installation4p · 4 filings · 15 docs
Site & exteriorGap NYFW, World Cup Telemundo Fan Village +5Under Construction48p · 33 filings · 20 docs
Filed — no permit issuedIndependent protected bulkhead wraps around rooftop6p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Rcpi Landmarks Properties50207/08/2026
Tishman Speyer Properties25510/13/2026
Rcpi Trust3703/21/2026
Rockefeller Center Properties1703/21/2026
Catbird NYC503/22/2026
Nbcuniversal209/13/2026
Quantum Design203/21/2026
Rcpi103/21/2026
R & S Associates103/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Gillman Consulting6003/21/2026
Walter T. Gorman, PE6303/21/2026
Municipal Building Consultants2803/21/2026
Codegreen603/21/2026
EA Design Group803/21/2026
M G McLaren Engineering203/21/2026
Construction Permit Services103/21/2026
TK Arcdesign203/21/2026
Outsource Consultants603/21/2026
Sam Mather Architect403/21/2026
AE Design Solution403/21/2026
RPO203/21/2026
Spring Scaffolding203/21/2026
Walter T Gorman Pepc3703/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Coyle ContractingGeneral Contractor3207/08/2026
Winick ProductionsGeneral Contractor1707/08/2026
Core Four ConstructionGeneral Contractor1507/28/2026
A&A PlumbingPlumbing1309/13/2026
W.J. Regan & CompanyGeneral Contractor1107/08/2026
Schimenti Construction CoGeneral Contractor907/08/2026
Turner Construction CompanyGeneral Contractor707/08/2026
Pace PlumbingFire Protection707/08/2026
Tristate Plumbing ServicesPlumbing607/08/2026
PSI PartnersFire Protection507/08/2026
Royal Concrete and Mason*specialty_contractor404/09/2026
BNW Riggingspecialty_contractor303/21/2026
Reem Plumbing & HeatingPlumbing307/08/2026
Kle ConstructionGeneral Contractor303/21/2026
JRM Construction ManagementGeneral Contractor304/09/2026
Finaly General ContractingGeneral Contractor307/08/2026
Innovative Heating SolutiPlumbing207/08/2026
L.E.A. ElectricElectrical203/22/2026
ConstructomicsGeneral Contractor203/21/2026
Integral Construction ofGeneral Contractor208/18/2026
Nucor ConstructionGeneral Contractor207/08/2026
NYFF EventsGeneral Contractor209/03/2026
Robert HindmanGeneral Contractor203/21/2026
Walker Design StudiosGeneral Contractor207/08/2026
Tri-State DismantlingScaffold207/08/2026
CM PlumbingPlumbing207/08/2026
Atlas-Acon Electric ServiceElectrical203/21/2026
Mac FelderPlumbing207/08/2026
Reem Plumbing & HeatingFire Protection207/08/2026
SKH MechanicalFire Protection207/08/2026
Queue Electrical ContractorsElectrical103/22/2026
Core Scaffold SystemsScaffold107/08/2026
Spring ScaffoldingScaffold104/09/2026
Atlas-Acon Electric ServiceElectrical103/22/2026
Premier ElectricElectrical103/22/2026
Aggressive Fire ProtectionFire Protection107/08/2026
A&M Warshaw ServicesFire Protection107/08/2026
Anchor PipingFire Protection107/08/2026
A Plus PlumbingPlumbing107/08/2026
A + SprinklerFire Protection106/28/2026
D&D Electl Construction CoElectrical103/22/2026
Denko MechanicalFire Protection107/08/2026
Dependable MechanicalFire Protection107/08/2026
Geoffrey A. Lagas & AssociatesPlumbing107/08/2026
Sirina Fire ProtectionFire Protection107/08/2026
Julian SprinklerFire Protection107/08/2026
Tristate Plumbing ServicesFire Protection107/08/2026
Mega PlumbingFire Protection108/06/2026
Mega PlumbingPlumbing108/06/2026
Miter ConstructionGeneral Contractor107/08/2026
Mill Brook Fire ProtectionFire Protection108/30/2026
Nationwide MechanicalPlumbing107/08/2026
Rockefeller CenterElectrical103/21/2026
Irving Haase & CoGeneral Contractor109/24/2026
Digital Construction TechnologiesGeneral Contractor104/10/2026
Sconda Canvas ProductsGeneral Contractor107/08/2026
Benchmark BuildersGeneral Contractor107/08/2026
Pem ElectricalElectrical103/21/2026
4IR IdealGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Walter T. Gorman, P.E., P2684110/09/2026
AK Engineering678309/19/2025
Metric Consulting and Ins1803407/23/2025
Richard H. Balser Engineering3028207/03/2025
KMB Design Group513104/28/2025
Integrity Consulting Service666412/19/2023
Welldone Inspection8628105/25/2023
CNS Inspection Services7566105/19/2023
Future Tech Consultants O5891301/14/2022
Codegreen510510/14/2021
DNA Controlled Inspection554501/19/2021
Skyline Engineering267101/30/2020
Building Lifecycle
All (300)Filed (78)Permit Issued (62)Signed Off (29)Inspection (44)Objection (57)Special Inspection (30)
10/09/2026
Filed — Alteration
Alterations to mechanical system on 6th floor as per plans. No change to use, egress or occupancy.
M01411228-P1
10/07/2026
Special inspection requirement — Interior lighting power
Walter Gorman
10/07/2026
Special inspection requirement — Maintenance information
Walter Gorman
10/07/2026
Special inspection requirement — Metering
Walter Gorman
10/07/2026
Special inspection requirement — Post-installed Anchors
Walter Gorman
10/07/2026
Special inspection requirement — Lighting controls
Walter Gorman
10/07/2026
Special inspection requirement — Final
Walter Gorman
10/07/2026
Special inspection requirement — Mechanical Systems
Walter Gorman
10/07/2026
Special inspection requirement — Duct leakage testing, insulation and design
Walter Gorman
09/23/2026
Permit issued — Mechanical Systems
M01411228-I1-MS
09/11/2026
Permit issued — Plumbing
M01411239-I1-PL
09/10/2026
Filed — No Work
M01445999-P1
09/02/2026
Filed — Alteration
Alterations to 7th floor terrace as per plans. No change to use, egress or occupancy.
M01103866-P2
09/02/2026
Permit issued — General Construction
M01447310-I1-GC
08/27/2026
Permit issued — Sprinklers
M01411234-I1-EW-SP
08/26/2026
Filed — Alteration
Install of temp Truss structure, prod equip, no alt to exist structures for GAP NYFW Pop-Up Activation. TPA not required. Producer is responsible to monitor site safety & implement HWAP. All production equipment removed upon event complete
M01447310-I1
08/18/2026
Filed — No Work
M01445999-I1
08/18/2026
Special inspection requirement — Final
DANNY TRUJILLO
08/17/2026
Permit issued — General Construction
M01411219-I1-GC
08/10/2026
Filed — Alteration
Alterations to mechanical system on 6th floor as per plans. No change to use, egress or occupancy.
M01411228-I1
08/10/2026
Filed — Alteration
Alterations to sprinkler system on 6th floor as per plans. No change to use, egress or occupancy.
M01411234-I1
08/10/2026
Special inspection requirement — Final
Richard DeMarco
08/07/2026
Filed — Alteration
General construction work on entire 6th floor as per plans. No change to use. egress or occupancy.
M01411219-I1
08/06/2026
Filed — Alteration
Alterations to plumbing system on 6th floor as per plans. No change to use, egress or occupancy.
M01411239-I1
08/05/2026
Permit issued — Sprinklers
M01407874-I1-EW-SP
08/05/2026
Permit issued — Plumbing
M01407884-I1-PL
08/03/2026
Signed off — Alteration
Installation of new AT&T site on the roof. Install 2 antennas, 10 RRH units, 1 GPS antenna and 1 equipment platform with cabinets. Related conduits through 7th-8th floor and service connection in the sub-basement.
M01184824-I1
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/30/2026
Special inspection requirement — Post-installed Anchors
Walter Gorman
07/30/2026
Special inspection requirement — Fire-Resistance Rated Construction
Walter Gorman
07/30/2026
Special inspection requirement — Final
SARAH VITEK
07/30/2026
Special inspection requirement — Maintenance information
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/30/2026
Special inspection requirement — Interior lighting power
07/30/2026
Special inspection requirement — Lighting controls
07/30/2026
Special inspection requirement — Metering
07/30/2026
Special inspection requirement — Duct leakage testing, insulation and design
07/27/2026
Permit issued — General Construction
M01243803-I1-GC
07/22/2026
Permit issued — Mechanical Systems
M01407840-I1-MS
07/21/2026
Filed — Alteration
Demolition and general construction on the partial 4th floor as per plans. No change to use. egress or occupancy.
M01243803-I1
07/21/2026
Filed — Alteration
Alterations to sprinkler system in partial 4th floor as per plans. No change to use, egress or occupancy.
M01407874-I1
07/21/2026
Filed — Alteration
Alterations to plumbing system in partial 4th floor as per plans. No change to use, egress or occupancy.
M01407884-I1
07/21/2026
Filed — Alteration
Alterations to mechanical system in 4th floor as per plans. No change to use, egress or occupancy.
M01407840-I1
07/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/17/2026
Special inspection requirement — Post-installed Anchors
Walter Gorman
07/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Walter Gorman
07/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walter Gorman
07/10/2026
Filed — No Work
M01428893-I1
06/30/2026
Signed off — Alteration
Installation of temp truss video screen, no alt to exist structures for Annual Rink Video Display. No TPA required. Producer is responsible to monitor site safety & implement HWAP. All production equipment removed upon event completion
M01268774-I1
06/25/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/23/2026
Permit issued — General Construction
M01417445-I1-GC
06/22/2026
Filed — Alteration
Alterations to 7th floor terrace as per plans. No change to use, egress or occupancy.
M01103866-P1
06/22/2026
Filed — No Work
M01417446-I1
06/22/2026
Special inspection requirement — Final
Richard DeMarco
06/18/2026
Filed — Alteration
M01417445-I1
06/17/2026
Special inspection requirement — Final
Richard DeMarco
06/16/2026
Special inspection requirement — Final
DANNY TRUJILLO
06/09/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/04/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/03/2026
Special inspection requirement — Sprinkler Systems
Walter Gorman
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedIrving Haase & Co09/23/2026
DOB NOWPlumbingPermit IssuedA&A Plumbing09/11/2026
DOB NOWGeneral ConstructionPermit IssuedNYFF Events09/02/2026
DOB NOWSprinklersPermit IssuedMill Brook Fire Protection08/27/2026
DOB NOWGeneral ConstructionPermit IssuedIntegral Construction of08/17/2026
DOB NOWPlumbingPermit IssuedMega Plumbing08/05/2026
DOB NOWSprinklersPermit IssuedMega Plumbing08/05/2026
DOB NOWGeneral ConstructionPermit IssuedCore Four Construction07/27/2026
DOB NOWMechanical SystemsPermit IssuedCore Four Construction07/22/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions06/23/2026
DOB NOWGeneral ConstructionPermit IssuedSconda Canvas Products05/15/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions04/10/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions03/09/2026
DOB NOWPlumbingPermit IssuedA&A Plumbing02/03/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions01/27/2026
DOB NOWGeneral ConstructionPermit IssuedRoyal Concrete and Mason*01/27/2026
DOB NOWStructuralSigned-offRoyal Concrete and Mason*01/27/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions10/16/2025
DOB NOWPlumbingSigned-offA&A Plumbing10/02/2025
DOB NOWSprinklersSigned-offAnchor Piping09/24/2025
DOB NOWMechanical SystemsSigned-off4IR Ideal09/23/2025
DOB NOWGeneral ConstructionSigned-offIntegral Construction of09/23/2025
DOB NOWGeneral ConstructionPermit IssuedWinick Productions09/22/2025
DOB NOWGeneral ConstructionSigned-offWinick Productions09/15/2025
DOB NOWGeneral ConstructionSigned-offWinick Productions09/09/2025
DOB NOWSprinklersSigned-offDependable Mechanical08/15/2025
DOB NOWPlumbingSigned-offA Plus Plumbing07/25/2025
DOB NOWMechanical SystemsPermit IssuedJRM Construction Management07/25/2025
DOB NOWSprinklersSigned-offA + Sprinkler07/25/2025
DOB NOWGeneral ConstructionPermit IssuedJRM Construction Management07/18/2025
DOB NOWPlumbingSigned-offA&A Plumbing07/15/2025
DOB NOWGeneral ConstructionPermit IssuedJRM Construction Management07/10/2025
DOB NOWConstruction FenceSigned-offSpring Scaffolding07/03/2025
DOB NOWAntennaSigned-offDigital Construction Technologies06/30/2025
DOB NOWGeneral ConstructionPermit IssuedWinick Productions04/22/2025
DOB NOWMechanical SystemsSigned-offWalker Design Studios04/18/2025
DOB NOWGeneral ConstructionSigned-offWalker Design Studios04/18/2025
DOB NOWPlumbingSigned-offA&A Plumbing02/18/2025
DOB NOWGeneral ConstructionSigned-offWinick Productions09/03/2024
DOB NOWSprinklersSigned-offReem Plumbing & Heating08/06/2024
+ 60 more permits on file
2 projects · most recent 10/09/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
10/09/2026Permit IssuedIrving Haase & CoAir Conditioning Systems
Cooling
International Enviro-Tec HPP-D, 08 1,000 CFM · Fan Coil Indoor ×7
HPP-C, 08 800 CFM · Fan Coil Indoor ×2
HPP-D, 06 600 CFM · Fan Coil Indoor ×2
07/23/2025Permit IssuedJRM Construction ManagementAir Conditioning Systems
Cooling
Aaon H3-ERB-8-0-28FC-000 244,700 BTU · Ahu ×1
5 projects · most recent 08/10/2026
FiledStatusContractorScope
08/10/2026Permit IssuedLeguci Piping & Heating122 heads
07/21/2026Permit IssuedReal Plumbing19 heads
09/19/2025Signed-offAnchor Piping113 heads
07/23/2025Signed-offA + Sprinkler22 heads
01/08/2021Signed-offA&M Warshaw Services—
8 projects · most recent 08/10/2026
Water/Sanitary Gas
FiledStatusContractorScope
08/10/2026———
08/06/2026Permit IssuedA&A PlumbingWater/Sanitary
07/21/2026———
07/21/2026Permit IssuedReal PlumbingWater/Sanitary
09/19/2025Signed-offA&A PlumbingWater/Sanitary
07/23/2025Signed-offA Plus PlumbingWater/Sanitary
09/16/2022Permit IssuedMCLNY Plumbing & HeatingGas, Water/Sanitary
01/29/2020——Water/Sanitary
25 projects · most recent 09/10/2026
General Wiring Lighting
FiledStatusContractorScope
09/10/2026Permit IssuedZerem ElectricGeneral Wiring
09/02/2026Permit IssuedZerem Electric—
02/04/2026Permit IssuedTitan Electrical & Elev ContractingGeneral Wiring
10/07/2025Permit IssuedL.E.A. ElectricGeneral Wiring
10/07/2025Permit IssuedL.E.A. Electric—
07/28/2025Permit IssuedOmta Tech—
07/18/2025Permit IssuedCiti-Wide ElectricGeneral Wiring
12/11/2024CompletePremier ElectricGeneral Wiring
08/04/2023CompleteErne Valley ElectricGeneral Wiring
07/18/2023CompleteEmpire State Electric MaintenanceGeneral Wiring, Lighting
02/06/2023CompleteEmpire State Electric Maintenance—
09/09/2022Permit IssuedMRD Electrical ServicesGeneral Wiring
05/18/2022CompleteD&D Electl Construction CoGeneral Wiring
11/02/2021CompleteM.C. Electrical NYGeneral Wiring
10/14/2021Permit IssuedLive Wire Electric 1General Wiring
2 projects · most recent 07/21/2026
Steel Concrete
FiledStatusContractorScope
07/21/2026Permit IssuedCore Four Construction1 scope_items
01/19/2026Signed-offRoyal Concrete and Mason*Steel, Concrete
1 project · most recent 05/18/2026
FiledStatusContractorScope
05/18/2026———
▾Field Inspections (DOB CAP) — 61
DateTypeResultReport
06/25/2026Pass-Final CND-Occupancy InspectionPassView ↗
06/09/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/04/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/02/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/29/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/23/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/23/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/08/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/06/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/30/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/30/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/24/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/03/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/08/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/22/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/19/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/12/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/07/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/27/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/21/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/21/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/21/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/04/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/14/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
Latest 25 of 61.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
10/07/2026Mechanical SystemsWalter Gormanspecial
10/07/2026Post-installed AnchorsWalter Gormanspecial
10/07/2026FinalWalter Gormanprogress
10/07/2026Duct leakage testing, insulation and designWalter Gormanenergy_progress
10/07/2026Lighting controlsWalter Gormanenergy_progress
10/07/2026MeteringWalter Gormanenergy_progress
10/07/2026Maintenance informationWalter Gormanenergy_progress
10/07/2026Interior lighting powerWalter Gormanenergy_progress
08/18/2026FinalDANNY TRUJILLOprogress
08/10/2026FinalRichard DeMarcoprogress
07/30/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
07/30/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
07/30/2026Duct leakage testing, insulation and design—energy_progress
07/30/2026Maintenance information—energy_progress
07/30/2026Interior lighting power—energy_progress
07/30/2026Lighting controls—energy_progress
07/30/2026Metering—energy_progress
07/30/2026FinalSARAH VITEKprogress
07/30/2026Fire-Resistance Rated ConstructionWalter Gormanprogress
07/30/2026Post-installed AnchorsWalter Gormanspecial
07/17/2026Post-installed AnchorsWalter Gormanspecial
07/17/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
07/17/2026Energy Code Compliance InspectionsWalter Gormanprogress
07/15/2026Fire-Resistant Penetrations and JointsWalter Gormanspecial
06/22/2026FinalRichard DeMarcoprogress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Gap NYFWRetail—
Project M01447310 Alteration · Permit Entire · 08/26/2026
L CattertonOfficeFloors 4–6
Project M01411228 Alteration · Permit Entire · 08/10/2026
Project M01411234 Alteration · Permit Entire · 08/10/2026
Project M01411219 Alteration · Permit Entire · 08/07/2026
Project M01411239 Alteration · Permit Entire · 08/06/2026
Project M00986106 Alteration · LOC Issued · 01/08/2024
Project M00872423 Alteration · LOC Issued · 07/26/2023
Project M00873827 Alteration · LOC Issued · 07/26/2023
Project M00873834 Alteration · LOC Issued · 07/26/2023
Project M00873825 Alteration · LOC Issued · 07/19/2023
Project M08035946 Alteration · LOC Issued · 11/10/2022
Project M00761293 Alteration · LOC Issued · 09/09/2022
Project M00564762 Alteration · LOC Issued · 09/08/2021
Hamilton LaneOfficeFloor 4
Project M01243803 Alteration · Permit Entire · 07/21/2026
Project M01407840 Alteration · Permit Entire · 07/21/2026
Project M01407874 Alteration · Permit Entire · 07/21/2026
Project M01407884 Alteration · Permit Entire · 07/21/2026
Project M08052575 Alteration · LOC Issued · 01/20/2023
Project M08052553 Alteration · LOC Issued · 01/12/2023
Project M08052562 Alteration · LOC Issued · 01/12/2023
World Cup Telemundo Fan VillageEvents & gatherings—
Project M01417445 Alteration · Permit Entire · 06/18/2026
Van Cleef & ArpelsRetail—
Project M01381473 Alteration · Permit Entire · 04/09/2026
Ralph LaurenRetail—
Project M01347143 Alteration · Permit Entire · 01/16/2026
MonclerRetail—
Project M01299843 Alteration · Permit Entire · 10/10/2025
Ryder Cup Live 2025Events & gatherings—
Project M01282621 Alteration · Permit Entire · 09/17/2025
Ryder CupEvents & gatherings—
Project M01281644 Alteration · LOC Issued · 09/11/2025
Capri HoldingsRetailCellar, Floor 1
Project M01248988 Alteration · Permit Entire · 07/23/2025
Project M01245280 Alteration · Permit Entire · 07/02/2025
AesopRetailCellar, Floor 1
Project M00988473 Alteration · LOC Issued · 03/07/2024
Project M00988481 Alteration · LOC Issued · 03/07/2024
Project M00988485 Alteration · LOC Issued · 03/07/2024
Project M00988648 Alteration · LOC Issued · 03/05/2024
Tous AtelierRetailFloor 1
Project M00905248 Alteration · LOC Issued · 09/22/2023
Robert IndianaArts / Culture / Entertainment—
Project M00903673 Alteration · LOC Issued · 08/04/2023
Johyun Gallery & Tishman SpeyerArts / Culture / Entertainment—
Project M00878277 Alteration · Permit Entire · 05/19/2023
SKIMSRetail—
Project M00864848 Alteration · LOC Issued · 05/03/2023
StaplesRetailFloor 3
Project M08008779 Alteration · LOC Issued · 01/12/2023
Project M08008787 Alteration · LOC Issued · 01/12/2023
Project M08008827 Alteration · LOC Issued · 01/12/2023
Project M08055086 Alteration · LOC Issued · 01/12/2023
Project M08055095 Alteration · LOC Issued · 01/11/2023
Project M08055101 Alteration · LOC Issued · 01/11/2023
Michael KorsRetailFloor 1
Project M08029170 Alteration · Permit Entire · 11/22/2022
AtomixRestaurant / Food ServiceSub-cellar, Cellar
Project M00649852 Alteration · LOC Issued · 01/14/2022
Project M00535197 Alteration · LOC Issued · 07/20/2021
Project M00539715 Alteration · LOC Issued · 07/20/2021
Project M00539824 Alteration · Permit Entire · 07/20/2021
Project M00541205 Alteration · LOC Issued · 07/20/2021
Met Museum ShopRetailFloor 1
Project M00449551 Alteration · Permit Entire · 01/19/2021
Project M00438465 Alteration · Permit Entire · 01/08/2021
Tishman Speyer Sea GrillRestaurant / Food ServiceSub-cellar, Cellar
Project M00273113 Alteration · LOC Issued · 01/31/2020
Project M00273160 Alteration · LOC Issued · 01/31/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 2,868 on file (BIS + DOB NOW)
▸Plans & Drawings158
▸DOB NOWPlans/Sketch105
09/06/2026M01381473-I1Request digital key ↗
09/04/2026M00477853-P1Request digital key ↗
09/04/2026M00477853-I1Request digital key ↗
Showing 3 of 105 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸DOB NOWPlans/Sketch - Plumbing15
09/05/2026M00250979-I1Request digital key ↗
09/05/2026M00250973-I1Request digital key ↗
09/04/2026M00352746-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems7
09/05/2026M00250969-I1Request digital key ↗
09/05/2026M00273113-P1Request digital key ↗
09/05/2026M00273113-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler7
09/04/2026M00352747-I1Request digital key ↗
09/04/2026M00413460-I1Request digital key ↗
09/04/2026M00432347-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Protection of Mechanical Methods1
09/04/2026M00457543-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPlans/Sketch - General Construction1
09/04/2026M00449551-I1Request digital key ↗
▸Applications & Permits559
▸BISPLAN / WORK APPROVAL APPLICATION284
10/23/2025122971276Open ↗
05/21/2025102824847Open ↗
05/19/2025102824847Open ↗
Showing 3 of 284 on file for this type
▸BISWORK PERMIT APPLICATION184
08/15/2022122139444Open ↗
01/27/2021140995127Open ↗
01/21/2021140994912Open ↗
Showing 3 of 184 on file for this type
▸DOB NOWLPC Approval/Permit91
10/11/2026M01411228-P1Open ↗
09/05/2026M00250979-I1Open ↗
09/05/2026M00273113-P1Open ↗
Showing 3 of 91 on file for this type
▸Zoning, Tax Lot & Property Records1
▸BISZoning Diagram (ZD1)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications857
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION370
03/27/2020123829250Open ↗
03/27/2020123829250Open ↗
Showing 2 of 370 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature157
10/14/2026M01445999-P1Open ↗
10/11/2026M01411228-P1Open ↗
09/06/2026M01381473-I1Open ↗
Showing 3 of 157 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST84
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 84 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT63
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 63 on file for this type
▸DOB NOWProgress Inspector Seal & Signature59
10/14/2026M01103866-P2Open ↗
10/11/2026M01411228-P1Open ↗
10/11/2026M01411228-P1Open ↗
Showing 3 of 59 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM57
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 57 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature52
10/11/2026M01411228-P1Open ↗
10/11/2026M01411228-P1Open ↗
10/02/2026M00988485-I1Open ↗
Showing 3 of 52 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION7
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 6 on file for this type
▸BISPC FULL REPORT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Trade Schedules & Equipment166
▸BISSELF-CERT PLUMBING NOTICE61
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 61 on file for this type
▸BISSCHEDULE B - PLUMBING40
09/29/2020123552921Open ↗
08/15/2020123552921Open ↗
Showing 2 of 40 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE40
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 40 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISSPRINKLER INSP REPORT : FP-857
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸Environmental & Asbestos257
▸DOB NOWDEP ACP-5: Asbestos Assessment Report110
10/11/2026M01411228-P1Open ↗
09/05/2026M00250979-I1Open ↗
09/05/2026M00250969-I1Open ↗
Showing 3 of 110 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)80
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 80 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'56
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 56 on file for this type
▸BISASBESTOS INSPECTION REPORT6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance56
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS27
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 27 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISNYCECC EXEMPTION5
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 5 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.1
09/04/2026M00413350-I1Open ↗
▸Inspections & Test Reports38
▸BISTECHNICAL REPORT: RESPONSIBILITY18
04/11/2023140957579Open ↗
09/22/2021140937360Open ↗
09/03/2021123748908Open ↗
Showing 3 of 18 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSPRAYED FIRE-RESISTANT MATERIALS2
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTRUCTURAL STEEL - WELDING1
11/13/2023140995314Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
11/13/2023140994912Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
11/13/2023140995314Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
11/13/2023140995314Open ↗
▸BISSTRUCTURAL STEEL - DETAILS1
11/13/2023140995314Open ↗
▸Approvals, Objections & Sign-offs283
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST106
07/02/2024101881689Open ↗
07/02/2024101407158Open ↗
04/29/2024101745033Open ↗
Showing 3 of 106 on file for this type
▸BISLANDMARKS APPROVAL89
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 89 on file for this type
▸BISADMINISTRATIVE OBJECTIONS62
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 62 on file for this type
▸BISLANDMARKS SIGNOFF8
11/14/2023140995314Open ↗
11/14/2023140995127Open ↗
11/14/2023140994912Open ↗
Showing 3 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
08/15/2022122139444Open ↗
Showing 1 of 7 on file for this type
▸BISFINAL5
11/13/2023140995314Open ↗
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
04/03/2024102824847Open ↗
04/02/2024102824847Open ↗
03/22/2024102824847Open ↗
▸BISCCD1-Construction Code Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISLETTERS - APPRVD FAB CERT-INTENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWLandmark Approval1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership236
▸BISCOST AFFIDAVIT229
11/02/2022140957579Open ↗
09/03/2021123748908Open ↗
02/04/2021123829250Open ↗
Showing 3 of 229 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW37
11/13/2023140995314Open ↗
11/13/2023140995127Open ↗
11/13/2023140994912Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms238
▸BISEFILING COVER SHEET146
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 146 on file for this type
▸BISBOROUGH INTAKE FORM48
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 48 on file for this type
▸BISADDITIONAL INFORMATION32
09/29/2020123552921Open ↗
07/17/2020123829250Open ↗
07/01/2020123829250Open ↗
Showing 3 of 32 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET12
12/23/2020140995314Open ↗
12/23/2020140995127Open ↗
12/23/2020140994912Open ↗
Showing 3 of 12 on file for this type
▸Other Documents17
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION7
10/06/2020140957579Open ↗
Showing 1 of 7 on file for this type
▸DOB NOWProof of Historic Building7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
12/04/2020123552921Open ↗
▸DOB NOWIRA Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type