| Owner | Filings | Most Recent |
|---|---|---|
| Grand Street Artists Coop | 16 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MD Mostafa | 1 | 09/06/2026 |
| Li Architect Associate | 8 | 09/12/2024 |
| Ospino Engineering | 4 | 11/28/2023 |
| Dean Mendez RA | 2 | 11/24/2023 |
| Katz Architecture | 2 | 11/01/2023 |
| Mohammad Ahead, PE | 2 | 01/25/2022 |
| Enthink Engineers | 2 | 11/03/2021 |
| Potential Engineering | 1 | 10/04/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Jme Building Consulting | 12 | 03/21/2026 |
| Expediting | 2 | 03/21/2026 |
| Right Way Services NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Aarco Contracting | Scaffold | 12 | 03/21/2026 |
| Avarga Construction | Scaffold | 9 | 03/21/2026 |
| MNK Enterprises | Scaffold | 6 | 03/21/2026 |
| Avarga Construction | General Contractor | 3 | 03/21/2026 |
| Ness Mechanical P & H | Plumbing | 2 | 07/08/2026 |
| Rite Way Heating | Plumbing | 2 | 03/22/2026 |
| Dordevic Adc | General Contractor | 2 | 03/21/2026 |
| Vir Contracting | General Contractor | 1 | 03/21/2026 |
| B B Mechanical Plumbing & Heating | Plumbing | 1 | 03/21/2026 |
| MPC Plumbing & Heating | Plumbing | 1 | 03/21/2026 |
| Superior Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| I.K.E. Electrical | Electrical | 1 | 03/22/2026 |
| Aviva Builders | General Contractor | 1 | 10/06/2026 |
| Envy NY II | General Contractor | 1 | 07/08/2026 |
| Splen Construction | General Contractor | 1 | 07/08/2026 |
| Apple Renaissance Rest | General Contractor | 2 | 08/03/2016 |
| Empire Scaffolding Systems | General Contractor | 1 | 10/24/2002 |
| Michael H | General Contractor | 1 | 05/11/1998 |
| Spring Scaffolding | General Contractor | 1 | 07/28/2016 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Ikra Consulting | 7032 | 1 | 09/06/2026 |
| Li Architect Associate, P | 1104 | 4 | 09/11/2024 |
| Katz Architecture | 1371 | 4 | 11/01/2023 |
| Professional Solutions GR | 1756 | 1 | 10/04/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Aviva Builders | 10/05/2026 |
| DOB NOW | Plumbing | Signed-off | Ness Mechanical P & H | 08/22/2024 |
| DOB NOW | General Construction | Signed-off | Avarga Construction | 11/21/2023 |
| DOB NOW | Supported Scaffold | Signed-off | Avarga Construction | 11/13/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Avarga Construction | 11/02/2023 |
| DOB NOW | Plumbing | Signed-off | Superior Plumbing & Heating | 10/26/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Avarga Construction | 10/11/2023 |
| DOB NOW | General Construction | Signed-off | Envy NY II | 09/26/2023 |
| DOB NOW | Supported Scaffold | Signed-off | Aarco Contracting | 05/20/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Aarco Contracting | 05/20/2022 |
| DOB NOW | Supported Scaffold | Signed-off | Aarco Contracting | 01/26/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Aarco Contracting | 01/26/2022 |
| DOB NOW | General Construction | Permit Issued | Splen Construction | 11/03/2021 |
| DOB NOW | Supported Scaffold | Signed-off | MNK Enterprises | 11/03/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK Enterprises | 11/03/2021 |
| BIS | OT | ISSUED | Dordevic Adc | 04/18/2018 |
| BIS | PL | ISSUED | B&B Mechanical Plumbing & Heating | 04/18/2018 |
| BIS | MH | ISSUED | Dordevic Adc | 04/18/2018 |
| BIS | OT | ISSUED | Apple Renaissance Rest | 08/03/2016 |
| BIS | OT | ISSUED | Apple Renaissance Rest | 08/02/2016 |
| BIS | EQ | ISSUED | Spring Scaffolding | 07/28/2016 |
| BIS | PL | ISSUED | MPC Plumbing & Heating | 03/04/2010 |
| BIS | OT | ISSUED | Vir Contracting | 02/16/2010 |
| BIS | EQ | ISSUED | Empire Scaffolding System | 10/24/2002 |
| BIS | EQ | ISSUED | Michael H | 05/11/1998 |
| BIS | OT | ISSUED | GJD Construction | 03/27/1996 |
| BIS | OT | ISSUED | John Delorenzo & Brothers | 01/24/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | Joe Electrical | General Wiring |
| 04/26/2024 | Complete | All City Electrical | General Wiring |
| 12/04/2023 | Complete | A&E Electrical Systems | General Wiring |
| 10/16/2023 | Permit Issued | High Quality Electric | — |
| 11/03/2021 | Complete | Richard Neu | — |
| 04/11/2018 | Permit Issued | I.K.E. Electrical | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/18/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/27/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/12/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/17/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 01/11/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2026 | Final | MD MOSTAFA | progress |
| 08/13/2026 | Energy Code Compliance Inspections | MD MOSTAFA | progress |
| 08/13/2026 | Fire-Resistant Penetrations and Joints | MD MOSTAFA | special |
| 09/17/2024 | Fire-Resistant Penetrations and Joints | Ling Li | special |
| 09/17/2024 | Tenant Protection Plan Compliance | Ling Li | special |
| 09/17/2024 | Fire-Resistance Rated Construction | Ling Li | progress |
| 09/17/2024 | Interior lighting power | Ling Li | energy_progress |
| 09/17/2024 | Energy Code Compliance Inspections | Ling Li | progress |
| 09/17/2024 | Tenant Protection Plan Compliance | Ling Li | special |
| 09/17/2024 | Tenant Protection Plan Compliance | Ling Li | special |
| 09/09/2024 | Interior lighting power | Ling Li | energy_progress |
| 09/09/2024 | Fire-Resistant Penetrations and Joints | Ling Li | special |
| 09/09/2024 | Tenant Protection Plan Compliance | — | special |
| 09/09/2024 | Energy Code Compliance Inspections | Ling Li | progress |
| 09/09/2024 | Fire-Resistance Rated Construction | Ling Li | progress |
| 09/09/2024 | Tenant Protection Plan Compliance | — | special |
| 09/09/2024 | Tenant Protection Plan Compliance | — | special |
| 07/15/2024 | Tenant Protection Plan Compliance | — | special |
| 06/03/2024 | Tenant Protection Plan Compliance | — | special |
| 11/13/2023 | Masonry | David Katz | special |
| 11/13/2023 | Tenant Protection Plan Compliance | David Katz | special |
| 11/13/2023 | Fire-Resistant Penetrations and Joints | David Katz | special |
| 11/13/2023 | Final | David Katz | progress |
| 11/13/2023 | Fire-Resistance Rated Construction | David Katz | progress |
| 11/01/2023 | Masonry | David Katz | special |