| Owner | Filings | Most Recent |
|---|---|---|
| CAVALRY | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SHARON ENGINEERING, P.C | 4 | 05/13/2026 |
| CHUN ENGINEERING CONSULTANT PLLC | 6 | 04/23/2025 |
| HAMANN ENGINEERING, PLLC | 1 | 11/09/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| CAVALRY LLC | 8 | 03/21/2026 |
| BIG ORANGE EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CAVALRY LLC | General Contractor | 6 | 07/08/2026 |
| BIG I RESTORATION INC | General Contractor | 4 | 07/08/2026 |
| CAVALRY GC&P LLC | General Contractor | 2 | 07/04/2026 |
| FLOW-RIGHT FIRE SUPP CORP | Fire Protection | 1 | 07/08/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHUN ENGINEERING CONSULTA | 9605 | 7 | 05/13/2026 |
| DAL H CHUN ENGINEER PC | 1972 | 1 | 07/02/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | FLOW-RIGHT FIRE SUPP CORP | 07/06/2026 |
| DOB NOW | General Construction | Permit Issued | CAVALRY GC&P LLC | 07/02/2026 |
| DOB NOW | Construction Fence | Permit Issued | BIG I RESTORATION INC | 05/07/2026 |
| DOB NOW | Plumbing | Permit Issued | FLOW-RIGHT PLBG & HTG COR | 04/13/2026 |
| DOB NOW | Foundation | Permit Issued | CAVALRY LLC | 07/21/2025 |
| DOB NOW | Support of Excavation | Signed-off | CAVALRY LLC | 07/16/2025 |
| DOB NOW | Structural | Signed-off | CAVALRY LLC | 07/01/2025 |
| DOB NOW | General Construction | Permit Issued | CAVALRY LLC | 07/01/2025 |
| DOB NOW | Construction Fence | Permit Issued | BIG I RESTORATION INC | 12/24/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | BIG I RESTORATION INC | 08/28/2024 |
| DOB NOW | General Construction | Permit Issued | BIG I RESTORATION INC | 11/22/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/13/2026 | Permit Issued | CAVALRY GC&P LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin 5MXS48TVJU 48,500 BTU · Condensing Unit ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | FLOW-RIGHT PLBG & HTG COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/16/2025 | Permit Issued | DENMAR ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | FLOW-RIGHT FIRE SUPP CORP | Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/08/2026 | Structural Stability – Alterations of existing buildings | JAMES CHUN | special |
| 06/08/2026 | Wood – High-Load Diaphragms | JAMES CHUN | special |
| 06/08/2026 | Final | CLOUD LEE | progress |
| 06/08/2026 | Post-installed Anchors | JAMES CHUN | special |
| 09/09/2024 | Structural Stability – Alterations of existing buildings | JAMES CHUN | special |
| 07/09/2024 | Footing and Foundation | JAMES CHUN | progress |
| 07/09/2024 | Concrete - Cast-In-Place | JAMES CHUN | special |
| 07/09/2024 | Subgrade Inspections | JAMES CHUN | special |
| 07/09/2024 | Subsurface Conditions – Fill Placement & In-Place Density | JAMES CHUN | special |
| 07/09/2024 | Final | CLOUD LEE | progress |
| 05/29/2024 | Air barrier - visual inspection | JAMES CHUN | energy_progress |
| 05/28/2024 | Fire-Resistant Penetrations and Joints | JAMES CHUN | special |
| 05/28/2024 | Energy Code Compliance Inspections | JAMES CHUN | progress |
| 01/09/2024 | Permanent certificate | JAMES CHUN | energy_progress |
| 01/09/2024 | Air barrier — testing | JAMES CHUN | energy_progress |
| 01/09/2024 | Electric vehicle service equipment requirements | JAMES CHUN | energy_progress |
| 01/09/2024 | Maintenance information | JAMES CHUN | energy_progress |
| 01/09/2024 | Insulation placement and R values | JAMES CHUN | energy_progress |
| 01/09/2024 | Fenestration areas | JAMES CHUN | energy_progress |
| 01/09/2024 | Interior lighting power | JAMES CHUN | energy_progress |
| 01/09/2024 | Fenestration air leakage | JAMES CHUN | energy_progress |
| 01/09/2024 | Fenestration and door U-factor and product ratings | JAMES CHUN | energy_progress |
| 11/15/2023 | Structural Stability – Alterations of existing buildings | JAMES CHUN | special |