← Back
Two family brick
726 FENIMORE STREET
BROOKLYN · BIN 3107347
💬 Discuss this project
1950Year Built
2Stories
B1Building Class
R6Zoning
2,080 sfGross Floor Area
2Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Two family brick · Owner of record: NYC PACT PRESERVATION PARTNERS LLC · 1,948 sf lot · 1.07 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof2p · 1 filing · 10 docs
Floor 24p · 3 filings · 20 docs
Floor 15p · 4 filings · 20 docs
Cellar2p · 1 filing · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW YORK CITY HOUSING AUTHORITY304/09/2026
NYC HOUSING AUTHORITY303/21/2026
NYC PACT PRESERVATION PARTNERS203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
METROPOLIS GROUP INC803/21/2026
RYBAK DEVELOPMENT403/21/2026
BARNWELL CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FSC D&C LLCGeneral Contractor507/08/2026
LS GENERAL CORPGeneral Contractor303/21/2026
LET IT GROW, INCORPORATEDGeneral Contractor204/09/2026
PYRAMID ETC COMPANIES, LLGeneral Contractor204/09/2026
A & E PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
METRIC CONSULTING AND INS1803701/29/2025
Building Lifecycle
All (45)Filed (7)Permit Issued (9)Signed Off (4)Violation (1)Inspection (4)Objection (2)Special Inspection (18)
03/19/2026
Signed off — Alteration
Scope of work includes the repair and/or replacement of heating, and ventilation systems of existing building.
B00932210-I1
03/17/2026
Permit issued — General Construction
B00918189-I1-GC
03/11/2026
Signed off — Alteration
Installation of plumbing fixtures along with related piping.
B00928426-I1
03/10/2026
Signed off — Alteration
STRUCTURAL WORK FOR REFRAMING EXISTING WOOD JOISTS AT FIRST FLOOR AS PER DRAWINGS.
B00911113-I1
12/08/2025
Permit issued — General Construction
B00918189-I1-GC
09/10/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/21/2025
Signed off — Alteration
Facade repairs and roof replacement. No changes in egress, use or occupancy.
B00930353-I1
07/11/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/27/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/27/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/25/2025
Permit issued — Structural
B00911113-I1-ST
06/25/2025
Permit issued — General Construction
B01157952-I1-GC
02/28/2025
Permit issued — Plumbing
B00928426-I1-PL
02/25/2025
Permit issued — General Construction
B01157952-I1-GC
02/20/2025
Permit issued — Mechanical Systems
B00932210-I1-MS
02/03/2025
Permit issued — General Construction
B00918189-I1-GC
01/29/2025
Filed — Alteration
Scope of work includes the repair and/or replacement of heating, and ventilation systems of existing building.
B00932210-I1
01/29/2025
Filed — Alteration
Installation of plumbing fixtures along with related piping.
B00928426-I1
01/27/2025
Filed — Alteration
WORK SHALL INCLUDE DIRECT REPLACEMENT OF FINISHES DIRECT REPLACEMENT OF APARTMENT KITCHEN, BATHROOMS, DOORS AND WINDOW SASHES.
B00918189-I1
01/16/2025
Filed — Alteration
GENERAL LANDSCAPING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01157952-I1
01/08/2025
Special inspection requirement — Electrical motors and elevators
SAMI HAJJAR P.E
01/08/2025
Special inspection requirement — Maintenance information
SAMI HAJJAR P.E
01/08/2025
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
01/06/2025
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
12/18/2024
Special inspection requirement — Final
SAMI HAJJAR P.E
07/11/2024
Permit issued — General Construction
B00930353-I1-GC
06/24/2024
Filed — Alteration
Facade repairs and roof replacement. No changes in egress, use or occupancy.
B00930353-P1
06/21/2024
Special inspection requirement — Final
SAMI HAJJAR P.E
06/21/2024
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
06/21/2024
Special inspection requirement — Energy Code Compliance Inspections
SAMI HAJJAR P.E
06/21/2024
Special inspection requirement — Masonry
SAMI HAJJAR P.E
06/21/2024
Special inspection requirement — Insulation placement and R values
SAMI HAJJAR P.E
03/08/2024
Filed — Alteration
Facade repairs and roof replacement. No changes in egress, use or occupancy.
B00930353-I1
09/11/2023
Special inspection requirement — Final
SAMI HAJJAR P.E
09/11/2023
Special inspection requirement — Mechanical Systems
SAMI HAJJAR P.E
09/11/2023
Special inspection requirement — Energy Code Compliance Inspections
SAMI HAJJAR P.E
09/08/2023
Objection raised — Other
09/08/2023
Objection resolved — Addressed
09/01/2023
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
09/01/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
SAMI HAJJAR P.E
08/30/2023
Filed — Alteration
STRUCTURAL WORK FOR REFRAMING EXISTING WOOD JOISTS AT FIRST FLOOR AS PER DRAWINGS.
B00911113-I1
08/02/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
SAMI HAJJAR P.E
08/02/2023
Special inspection requirement — Structural Wood Frame
SAMI HAJJAR P.E
07/28/2023
Special inspection requirement — Final
SAMI HAJJAR P.E
11/01/2018
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC03/17/2026
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC12/08/2025
DOB NOWStructuralSigned-offPYRAMID ETC COMPANIES, LL06/25/2025
DOB NOWGeneral ConstructionSigned-offLET IT GROW, INCORPORATED06/25/2025
DOB NOWPlumbingSigned-offA & E PLUMBING CORP02/28/2025
DOB NOWGeneral ConstructionSigned-offLET IT GROW, INCORPORATED02/25/2025
DOB NOWMechanical SystemsSigned-offPYRAMID ETC COMPANIES, LL02/20/2025
DOB NOWGeneral ConstructionSigned-offFSC D&C LLC02/03/2025
DOB NOWGeneral ConstructionSigned-offLS GENERAL CORP07/11/2024
BISEQISSUEDZORIA HOUSING, LLC10/28/2010
BISBLISSUEDTOWN COOLING INC04/16/1996
BISPLISSUEDTOWN COOLING INC.04/09/1996
1 project · most recent 09/03/2025
General Wiring
FiledStatusContractorScope
09/03/2025CompleteATLAS-ACON ELEC. SERVICEGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
09/10/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/11/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/27/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/27/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
01/08/2025Electrical motors and elevatorsSAMI HAJJAR P.Eenergy_progress
01/08/2025Maintenance informationSAMI HAJJAR P.Eenergy_progress
01/08/2025Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
01/06/2025Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
12/18/2024FinalSAMI HAJJAR P.Eprogress
06/21/2024FinalSAMI HAJJAR P.Eprogress
06/21/2024Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
06/21/2024Energy Code Compliance InspectionsSAMI HAJJAR P.Eprogress
06/21/2024MasonrySAMI HAJJAR P.Especial
06/21/2024Insulation placement and R valuesSAMI HAJJAR P.Eenergy_progress
09/11/2023FinalSAMI HAJJAR P.Eprogress
09/11/2023Mechanical SystemsSAMI HAJJAR P.Especial
09/11/2023Energy Code Compliance InspectionsSAMI HAJJAR P.Eprogress
09/01/2023Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
09/01/2023HVAC-R and service water piping design and insulationSAMI HAJJAR P.Eenergy_progress
08/02/2023Structural Stability – Alterations of existing buildingsSAMI HAJJAR P.Especial
08/02/2023Structural Wood FrameSAMI HAJJAR P.Eprogress
07/28/2023FinalSAMI HAJJAR P.Eprogress
▾Documents — 56 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/26/2026B00911113-I1Request digital key ↗
08/24/2026B00930353-I1Request digital key ↗
08/24/2026B00930353-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
09/03/2025300442992Open ↗
11/03/2010320236339Open ↗
▸BISWORK PERMIT APPLICATION1
11/03/2010320236339Open ↗
▸Seals & Professional Certifications26
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026B01157952-I1Open ↗
09/01/2026B00930353-P1Open ↗
09/01/2026B00930353-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/24/2026B00930353-I1Open ↗
08/23/2026B00918189-P1Open ↗
08/23/2026B00932210-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/01/2026B01157952-I1Open ↗
09/01/2026B00930353-P1Open ↗
08/30/2026B00911113-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
11/03/2010320236339Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
11/03/2010320236339Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
11/03/2010320236339Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/23/2026B00932210-I1Open ↗
08/13/2026B00911113-I1Open ↗
08/13/2026B00928426-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
11/03/2010320236339Open ↗
▸Approvals, Objections & Sign-offs12
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/24/2026B00930353-I1Open ↗
08/23/2026B00918189-P1Open ↗
08/13/2026B00911113-I1Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
03/09/2012320236339Open ↗
12/16/2011320236339Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
11/03/2010320236339Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
03/09/2012320236339Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
11/03/2010320236339Open ↗