← Back
Condo, residential tower (mixed-use, multi-family elevator) [derived]
Key West Condominium
750 COLUMBUS AVENUE · BIN 1079308
💬 Discuss this project
1988Year Built
12Stories
RMBuilding Class
C1-9Zoning
314,997 sfGross Floor Area
299Units
LL97 CoveredRent Stabilized54 Open Violations ▸FISP: SWARMP
Condo, residential tower (mixed-use, multi-family elevator) [derived] · 40,368 sf lot · 7.8 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 2 filings · 5 docs
Floor 123p · 1 filing · 4 docs
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 11p · 1 filing · 6 docs
Cellar4p · 3 filings · 12 docs
BasementUnder Construction13p · 6 filings · 20 docs
Sub-BasementUnder Construction10p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
EQUITY RESIDENTIAL7307/08/2026
RYAN HEALTH704/09/2026
KINGS GROUP NY404/09/2026
WEST 96 ST APTS103/22/2026
ELYSIUM CONSTRUCTION503/22/2026
STONEHENGE MANAGEMENT103/22/2026
OWNER OF 110 WEST 97 STRE103/22/2026
CITIZENS ICON HOLDINGS,LL103/22/2026
AMERICAN PROPERTY FINANCI303/22/2026
VALE WESTDALE HOUSING103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PA BUILDERS, INCGeneral Contractor404/09/2026
YM PRO CORPGeneral Contractor303/21/2026
STRUCTURAL PRESERV SYSTEMGeneral Contractor307/03/2026
A & M WARSHAW PLBG & HTGPlumbing203/22/2026
MAIN POWER ELECT CONTRElectrical203/22/2026
GILBANE BUILDING COMPANYGeneral Contractor204/09/2026
KINGS GROUP NY CORPGeneral Contractor104/09/2026
PAR PLUMBING CO., INCGeneral Contractor107/08/2026
JEFFREY VULPIS PLMBNG LLCPlumbing107/08/2026
VMC PLUMBING & HEATING INPlumbing107/08/2026
INTERBORO SIGN ELEC MAIScaffold107/08/2026
DERRICK RAMDEENElectrical103/21/2026
UNIVERSAL SIGNS SVCScaffold107/08/2026
MOHAMMOD BHUYAINElectrical103/21/2026
NU-WIRE ELECTRIC, INCElectrical103/22/2026
A&M WARSHAW SERVICES LLCFire Protection106/28/2026
CASE PLUMBING LLCFire Protection107/08/2026
BINDELA CONSTRUCTION LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK ENGINEERING PC678403/25/2026
METROSPEC SIA6420605/22/2025
SOCOTEC ENGINEERING4983103/26/2025
MG NEW YORK ARCHITECTS, P3444210/11/2024
NY RESTORATION TECHNOLOGY6187108/30/2024
VINCENT J. LIOTTA P. E.1974109/11/2023
PIRO STUDIO LLC7503110/08/2021
Building Lifecycle
All (176)Filed (23)Permit Issued (24)Signed Off (11)Facade (FISP) (12)Violation (60)Inspection (16)Special Inspection (30)
08/20/2026
Signed off — Alteration
Modify sprinklers to accommodate fit out in the existing pharmacy.
M01251659-I1
07/20/2026
Signed off — Alteration
Modify sprinklers to accommodate fit out in the existing pharmacy.
M01251659-S1
07/02/2026
Permit issued — Suspended Scaffold
M01109394-I1-SC
07/01/2026
Permit issued — Suspended Scaffold
M01109390-I1-SC
07/01/2026
Permit issued — General Construction
M01065682-I1-GC
06/12/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/09/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/09/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/29/2026
Violation issued (HPD, closed)
A
04/07/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
Ari Kamo
03/26/2026
Special inspection requirement — Sprinkler Systems
Ari Kamo
03/26/2026
Special inspection requirement — Post-installed Anchors
Ari Kamo
03/25/2026
Filed — Alteration
Modify sprinklers to accommodate fit out in the existing pharmacy.
M01251659-P1
03/06/2026
Special inspection requirement — Tenant Protection Plan Compliance
Ari Kamo
03/06/2026
Special inspection requirement — Sprinkler Systems
Ari Kamo
03/06/2026
Special inspection requirement — Post-installed Anchors
Ari Kamo
11/26/2025
Signed off — Alteration
PLUMBING WORK TO PROVIDE PIPING, HANGERS, FIXTURES AND ALL MATERIAL AND LABOR FOR THE DOMESTIC WATER, SANITARY, NATURAL GAS AND ALL OTHER PLUMBING SYSTEMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01132798-I1
11/26/2025
Signed off — Alteration
GENERAL CONSTRUCTION FOR INTERIOR TENANT-FIT-OUT RENOVATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01132767-I1
11/26/2025
Signed off — Alteration
MECHANICAL WORK ASSOCIATED WITH INTERIOR COMMERCIAL TENANT-FIT-OUT RENOVATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01132790-I1
11/17/2025
Violation issued (HPD, closed)
I
11/06/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/27/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/22/2025
Signed off — Alteration
M01159146-I1
10/07/2025
Signed off — Alteration
ERECT ACCESORY BUSINESS WALL SIGN FOR NAYA, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01212901-I1
10/06/2025
Filed — Alteration
ERECT ACCESORY BUSINESS WALL SIGN FOR NAYA, NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01212901-P1
10/06/2025
Special inspection requirement — Final
JERE MURDOCH
10/02/2025
Permit issued — Sprinklers
M01251659-S3-EW-SP
09/15/2025
Filed — Alteration
Modify sprinklers to accommodate fit out in the existing pharmacy.
M01251659-S3
08/18/2025
Violation issued (HPD, closed)
C
08/14/2025
Permit issued — Mechanical Systems
M01251659-S1-MS
08/07/2025
Permit issued — General Construction
M01251659-I1-GC
07/25/2025
Filed — Alteration
Modify sprinklers to accommodate fit out in the existing pharmacy.
M01251659-S1
07/24/2025
Filed — Alteration
Modify sprinklers to accommodate fit out in the existing pharmacy.
M01251659-I1
07/10/2025
Special inspection requirement — Duct leakage testing, insulation and design
Ari Kamo
07/10/2025
Special inspection requirement — Maintenance information
Ari Kamo
07/07/2025
Special inspection requirement — Tenant Protection Plan Compliance
Ari Kamo
07/07/2025
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
07/07/2025
Special inspection requirement — Energy Code Compliance Inspections
Ari Kamo
07/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
07/07/2025
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
07/07/2025
Special inspection requirement — Tenant Protection Plan Compliance
Ari Kamo
07/07/2025
Special inspection requirement — Energy Code Compliance Inspections
Ari Kamo
07/07/2025
Special inspection requirement — Final
Ari Kamo
07/07/2025
Special inspection requirement — Post-installed Anchors
Ari Kamo
07/07/2025
Special inspection requirement — Mechanical Systems
Ari Kamo
07/07/2025
Special inspection requirement — Final
Ari Kamo
07/07/2025
Special inspection requirement — Interior lighting power
Ari Kamo
07/02/2025
Permit issued — Suspended Scaffold
M01109394-I1-SC
07/02/2025
Permit issued — Suspended Scaffold
M01109390-I1-SC
07/02/2025
Violation issued (HPD, closed)
B
06/11/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/09/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
05/28/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH YOUNG
05/23/2025
Special inspection requirement — Tenant Protection Plan Compliance
JOSEPH YOUNG
05/23/2025
Special inspection requirement — Post-installed Anchors
JOSEPH YOUNG
05/23/2025
Special inspection requirement — Energy Code Compliance Inspections
JOSEPH YOUNG
05/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
JOSEPH YOUNG
05/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
JOSEPH YOUNG
Latest 60 of 176 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM07/02/2026
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM07/01/2026
DOB NOWGeneral ConstructionPermit IssuedSTRUCTURAL PRESERV SYSTEM07/01/2026
DOB NOWSprinklersPermit IssuedA&M WARSHAW SERVICES LLC10/02/2025
DOB NOWMechanical SystemsSigned-offGILBANE BUILDING COMPANY08/14/2025
DOB NOWGeneral ConstructionSigned-offGILBANE BUILDING COMPANY08/07/2025
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM07/02/2025
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM07/02/2025
DOB NOWSignSigned-offUNIVERSAL SIGNS & SVC INC05/14/2025
DOB NOWMechanical SystemsSigned-offPA BUILDERS, INC04/08/2025
DOB NOWGeneral ConstructionSigned-offPA BUILDERS, INC04/08/2025
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM03/27/2025
DOB NOWGeneral ConstructionPermit IssuedSTRUCTURAL PRESERV SYSTEM03/10/2025
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM02/20/2025
DOB NOWSprinklersSigned-offS & L PLUMBING INC01/15/2025
DOB NOWPlumbingSigned-offM. SPINELLI PLB & HTG INC12/31/2024
DOB NOWMechanical SystemsPermit IssuedPAR PLUMBING CO., INC12/24/2024
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP12/23/2024
DOB NOWGeneral ConstructionSigned-offPA BUILDERS, INC12/17/2024
DOB NOWMechanical SystemsSigned-offPA BUILDERS, INC12/17/2024
DOB NOWGeneral ConstructionSigned-offBINDELA CONSTRUCTION LLC11/06/2024
DOB NOWGeneral ConstructionSigned-offYM PRO CORP01/26/2022
DOB NOWPlumbingSigned-offJEFFREY VULPIS PLMBNG LLC05/26/2021
DOB NOWSignSigned-offINTERBORO SIGN & ELEC MAI10/03/2019
BIS—ISSUEDCENTRAL CONSTRUCTION MANAGEMENT01/10/2025
BIS—ISSUEDCENTRAL CONSTRUCTION MANAGEMENT11/13/2024
BIS—ISSUEDELYSIUM CONSTRUCTION INC06/22/2021
BIS—ISSUEDELYSIUM CONSTRUCTION INC04/21/2021
BISPLISSUEDCC CONTROLLED PLBG CO INC12/17/2018
BISFBISSUEDC C CONTROLLED COMBUSTION07/27/2018
BISOTISSUEDV & I CONSTRUCTION INC06/22/2018
BISOTISSUEDV & I CONSTRUCTION INC06/20/2018
BISOTISSUEDV & I CONSTRUCTION INC06/15/2018
BISOTISSUEDV & I CONSTRUCTION INC06/15/2018
BISMHISSUEDCITY VENTILATION LLC12/11/2017
BISOTISSUEDEMPRISE CONSTRUCTION INC08/18/2017
BISPLISSUEDSO PLUMBING & HEATING INC08/15/2017
BISOTISSUEDEMPIRE STATE CONTRACTING08/09/2017
BISMHISSUEDEMPIRE STATE CONTRACTING08/09/2017
BISPLISSUEDCC CONTROLLED PLBG CO INC07/26/2017
+ 34 more permits on file
3 projects · most recent 03/25/2026
Air Conditioning Systems Heating and Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
03/25/2026Signed-offGILBANE BUILDING COMPANYHeating and Air Conditioning Systems
Heat / Cool
— CUH-1-1 921W-3404-W WCI 100 CFM · Electric Heater ×1
09/11/2023Permit IssuedPAR PLUMBING CO., INCAir Conditioning Systems
Cooling
Trane CSAA025UA 12,000 CFM · Chiller ×2
10/08/2021——Air Conditioning Systems, Heating Systems
Cooling
Mitsubishi Electric PUMY-P60-NHMU 59,000 BTU · Vrf Outdoor ×1
Heating
Mitsubishi Electric MLZ-KP18-NA 21,000 BTU · Ahu ×3
1 project · most recent 03/25/2026
Sprinkler System
FiledStatusContractorScope
03/25/2026Permit IssuedA&M WARSHAW SERVICES LLCSprinkler System
13 projects · most recent 10/07/2025
General Wiring Lighting HVAC Wiring
FiledStatusContractorScope
10/07/2025Permit IssuedSNB ELECTRICAL CONTNG CORGeneral Wiring
08/22/2025CompleteRELIANT ELEC'L CONT'G INCGeneral Wiring, Lighting
07/16/2025CompleteMEGA ELEC'L CONTR'G, INCGeneral Wiring
12/23/2024CompleteHIGH QUALITY ELECTRIC OF—
06/16/2023CompletePROSTO ELECTRIC CORPLighting
02/24/2023Permit IssuedALLIANCE ELEVATOR COMPANY—
04/25/2022CompleteMAIN POWER ELECT CONTRGeneral Wiring
07/07/2021CompleteHYLAN DATACOM & ELECL LLC2 meters, 1 new_meters
12/02/2019CompletePAGS ELECTRICAL CONTNG LLGeneral Wiring
03/05/2019Permit IssuedSTAR ELEC'L CONTRACTORS C—
09/10/2018Permit IssuedNU-WIRE ELECTRIC, INCGeneral Wiring
06/06/2018Permit IssuedMEO ELECTRIC CORP—
12/19/2017CompleteFICHERA ELECTRIC, INCHVAC Wiring
1 project · most recent 02/12/2025
FiledStatusContractorScope
02/12/2025Permit IssuedSTRUCTUAL PRESV SYSTEM—
▾Field Inspections (DOB CAP) — 16
DateTypeResultReport
06/12/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/09/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/09/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/07/2026Pass-Final CND-Occupancy InspectionPassView ↗
11/06/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/27/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/11/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/09/2025Pass-Final Boiler Equipment InspectionPassView ↗
05/28/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/04/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/17/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/09/2024Pass-Final CND-Occupancy InspectionPassView ↗
09/15/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/16/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 73
DateRequirementInspectorRole
03/26/2026Post-installed AnchorsAri Kamospecial
03/26/2026Tenant Protection Plan ComplianceAri Kamospecial
03/26/2026Sprinkler SystemsAri Kamospecial
03/06/2026Tenant Protection Plan ComplianceAri Kamospecial
03/06/2026Sprinkler SystemsAri Kamospecial
03/06/2026Post-installed AnchorsAri Kamospecial
10/06/2025FinalJERE MURDOCHprogress
07/10/2025Maintenance informationAri Kamoenergy_progress
07/10/2025Duct leakage testing, insulation and designAri Kamoenergy_progress
07/07/2025Tenant Protection Plan ComplianceAri Kamospecial
07/07/2025HVAC-R and service water heating equipmentAri Kamoenergy_progress
07/07/2025Interior lighting powerAri Kamoenergy_progress
07/07/2025Energy Code Compliance InspectionsAri Kamoprogress
07/07/2025FinalAri Kamoprogress
07/07/2025Tenant Protection Plan ComplianceAri Kamospecial
07/07/2025Mechanical SystemsAri Kamospecial
07/07/2025Post-installed AnchorsAri Kamospecial
07/07/2025FinalAri Kamoprogress
07/07/2025Energy Code Compliance InspectionsAri Kamoprogress
07/07/2025HVAC-R and service water heating system controlsAri Kamoenergy_progress
07/07/2025Fire-Resistant Penetrations and JointsAri Kamospecial
05/23/2025Tenant Protection Plan ComplianceJOSEPH YOUNGspecial
05/23/2025HVAC-R and service water heating system controlsJOSEPH YOUNGenergy_progress
05/23/2025HVAC-R and service water heating equipmentJOSEPH YOUNGenergy_progress
05/23/2025HVAC-R and service water piping design and insulationJOSEPH YOUNGenergy_progress
Latest 25 of 73.
▾Documents — 1,131 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch23
09/06/2026M00050514-I1Request digital key ↗
09/06/2026M00026583-I1Request digital key ↗
09/03/2026M00578267-I1Request digital key ↗
Showing 3 of 23 on file for this type
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00463789-I1Request digital key ↗
▸Applications & Permits234
▸BISPLAN / WORK APPROVAL APPLICATION144
03/04/2024123797551Open ↗
02/15/2024123797551Open ↗
07/09/2021123797551Open ↗
Showing 3 of 144 on file for this type
▸BISWORK PERMIT APPLICATION87
11/13/2024123797551Open ↗
11/06/2024123797551Open ↗
04/21/2021123797551Open ↗
Showing 3 of 87 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
07/20/2022123797551Open ↗
Showing 1 of 2 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records4
▸BISZONING DIAGRAM3
05/05/2022123797551Open ↗
09/21/2020123797551Open ↗
09/14/2020123797551Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
02/01/2021123797551Open ↗
▸Seals & Professional Certifications255
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION121
02/14/2020122521217Open ↗
02/14/2020122521217Open ↗
02/12/2020123797551Open ↗
Showing 3 of 121 on file for this type
▸DOB NOWProgress Inspector Seal & Signature29
09/02/2026M01132767-I1Open ↗
09/02/2026M01132767-I1Open ↗
09/01/2026M01132798-P2Open ↗
Showing 3 of 29 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature22
09/06/2026M00050514-I1Open ↗
09/06/2026M00026583-I1Open ↗
09/03/2026M00578267-I1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/30/2026M01251659-P1Open ↗
09/02/2026M01132767-I1Open ↗
09/01/2026M01132798-P2Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Trade Schedules & Equipment92
▸BISSELF-CERT PLUMBING NOTICE30
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 30 on file for this type
▸BISSCHEDULE B - PLUMBING22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE18
02/23/2018140652719Open ↗
02/22/2018140652719Open ↗
Showing 2 of 18 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION-PERMIT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSPRINKLER INSP REPORT : FP-852
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISEQUIPMENT USE PERMITS2
01/09/2018123169702Open ↗
Showing 1 of 2 on file for this type
▸BISBOILERS - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection17
▸BISTenant Protection Plan and Notes12
02/12/2020123797551Open ↗
04/26/2018123390561Open ↗
03/06/2018123446495Open ↗
Showing 3 of 12 on file for this type
▸BISSTREET TREE CHECKLIST4
02/12/2020123797551Open ↗
Showing 1 of 4 on file for this type
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
02/11/2021123797551Open ↗
▸Environmental & Asbestos61
▸BISASBESTOS: CERTIFICATION (DEP ACP5)28
02/12/2020123797551Open ↗
03/06/2018123446495Open ↗
Showing 2 of 28 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report16
09/03/2026M00578267-I1Open ↗
08/26/2026M01121709-I1Open ↗
08/25/2026M01132767-I1Open ↗
Showing 3 of 16 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Energy Compliance63
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS39
02/12/2020123797551Open ↗
10/30/2019122991726Open ↗
10/16/2019123446495Open ↗
Showing 3 of 39 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS12
10/30/2019122991726Open ↗
10/16/2019123446495Open ↗
05/10/2019123307965Open ↗
Showing 3 of 12 on file for this type
▸BISTR8: Energy Code Progress Inspections3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISLIGHTING IN DWELLING UNITS1
07/20/2022123797551Open ↗
▸BISINTERIOR LIGHTING POWER1
07/20/2022123797551Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
07/20/2022123797551Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/20/2022123797551Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY7
03/05/2021123797551Open ↗
Showing 1 of 7 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)3
07/20/2022123797551Open ↗
07/20/2022123797551Open ↗
07/20/2022123797551Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
07/20/2022123797551Open ↗
▸Approvals, Objections & Sign-offs131
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST68
12/30/2020110190187Open ↗
10/06/2020110190187Open ↗
07/22/2020110190187Open ↗
Showing 3 of 68 on file for this type
▸BISADMINISTRATIVE OBJECTIONS20
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 20 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION19
01/21/2025123797551Open ↗
11/13/2024123797551Open ↗
08/06/2019110190187Open ↗
Showing 3 of 19 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE15
11/02/2020123797551Open ↗
06/20/2020123797551Open ↗
02/12/2020123797551Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
08/21/2026M01251659-S3Open ↗
08/21/2026M01251659-P1Open ↗
08/21/2026M01251659-P2Open ↗
Showing 3 of 5 on file for this type
▸BISSUPERSEDING LETTER3
11/13/2024123797551Open ↗
11/06/2024123797551Open ↗
Showing 2 of 3 on file for this type
▸BISHPD LETTER OF DEFERRAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership94
▸BISCOST AFFIDAVIT86
02/14/2020122521217Open ↗
02/12/2020123797551Open ↗
10/30/2019122991726Open ↗
Showing 3 of 86 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCIVIL PENALTY AFFADAVIT/REQUEST3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Filing & Intake Forms129
▸BISEFILING COVER SHEET52
02/12/2020123797551Open ↗
04/03/2018123390561Open ↗
03/06/2018123446495Open ↗
Showing 3 of 52 on file for this type
▸BISBOROUGH INTAKE FORM36
11/13/2024123797551Open ↗
11/06/2024123797551Open ↗
06/05/2020110190187Open ↗
Showing 3 of 36 on file for this type
▸BISADDITIONAL INFORMATION35
05/05/2022123797551Open ↗
05/05/2022123797551Open ↗
07/23/2021123797551Open ↗
Showing 3 of 35 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸Other Documents9
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSUSTAINABLE ROOF ZONE FORM1
09/15/2020123797551Open ↗
▸DOB NOWIRA Certification1
08/13/2026M01109394-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01109390-I1Open ↗
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/13/2026M00050514-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01109390-I1Open ↗