1915Year Built
12Stories
D4Building Class
R8Zoning
116,520 sfGross Floor Area
78Units
LL97 CoveredRent Stabilized0 Active ViolationsFISP: SWARMP
Elevator cooperative · Owner of record: 771 West End Ave · 12,600 sf lot · 9.25 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofThe Lovett Company, LLCUnder Construction4p · 3 filings · 20 docs
Floor 12Unit 12G, Unit 12EF, Unit 12GEF +19p · 4 filings · 20 docs
Floor 11Unit 11A, Unit 11BUnder Construction65p · 2 filings · 20 docs
Floor 10Unit 10K8p · 1 filing · 20 docs
Floor 9Unit 9KUnder Construction5p · 1 filing · 9 docs
Floor 8
Floor 7
Floor 6Unit 6D, Unit 6E9p · 2 filings · 18 docs
Floor 5Unit 5DUnder Construction8p · 1 filing · 8 docs
Floor 4Unit 4EF1p · 1 filing · 5 docs
Floor 3
Floor 2Unit 2D15p · 1 filing · 20 docs
Floor 1
CellarInterior Renovations Alt 2 _ Gc5p · 1 filing · 20 docs
BasementThe Lovett Company, LLC1p · 1 filing · 8 docs
Sub-BasementThe Lovett Company, LLC6p · 2 filings · 13 docs
Site & exteriorThe Lovett Company, LLC15p · 3 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
771 West End Avenu11903/22/2026
The Lovett Company3607/08/2026
Diversifie303/21/2026
771 Wea in203/21/2026
Charter103/22/2026
Shareholder103/21/2026
Co-OP Owner103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BRP Construction Group1203/21/2026
PS Engineers403/21/2026
Meszaros Engineering1403/21/2026
J.A.M. Associates1203/21/2026
Synergy Building Consultants103/21/2026
The Lovett Group203/21/2026
MMSR Consulting Group403/21/2026
William Vitacco Associates1003/21/2026
Dynamic Building Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Gruda-Ni ConstructionGeneral Contractor1009/30/2026
David EvanGeneral Contractor904/09/2026
Kings Group NYScaffold707/08/2026
Monarch Plumbing & HeatingPlumbing410/03/2026
Two-Tone ContractingGeneral Contractor307/08/2026
Coolquest Mechanicalspecialty_contractor303/21/2026
Norman Project ManagementGeneral Contractor303/21/2026
T.N.T. Plumbing & HeatingPlumbing207/08/2026
Gallery Restorationspecialty_contractor203/21/2026
Champ Plumbing & HeatingPlumbing207/08/2026
Cochrane Plumbing & HeatingPlumbing207/08/2026
Magnum Plumbing & HeatingPlumbing207/08/2026
Norlin Electrical ContractorsElectrical103/21/2026
Omd ElectricalElectrical103/21/2026
Boxwood ConstructionGeneral Contractor107/08/2026
Enterprise Electrical SystemsElectrical103/21/2026
George Holness G.CElectrical103/21/2026
Lippolis ElectricElectrical103/21/2026
Grid City ElectricElectrical103/22/2026
Kanaris ContractingGeneral Contractor107/08/2026
Farella MichaelElectrical103/21/2026
Denmar ElectricElectrical103/22/2026
We Work GroupGeneral Contractor110/07/2026
K. C. ElectricElectrical103/21/2026
R.J.C. MechanicalPlumbing110/14/2026
Simple Choice Plumbing and HTPlumbing107/08/2026
Hydrokinetic Plumbing & Heating IPlumbing107/08/2026
Argon ElectricalElectrical103/22/2026
M&M Plumbing & HeatingPlumbing107/08/2026
Mike Lewkovicz Electric CompanyElectrical103/21/2026
L.J.F. & Sons Electrical ContsElectrical103/22/2026
WCK ElectricElectrical103/21/2026
Farella ElectricElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Iva Filipovic Architect3142208/26/2026
Design and Soltuions Stud7953507/02/2026
RHL Engineering712301/29/2026
Meszaros Engineering963712/09/2025
KZ Engineering4665111/06/2024
AK Engineering678410/23/2024
Framework Engineering8217208/04/2023
Sia Inspections7306208/02/2023
Leo Y Lee Associates2481201/11/2023
Jon Libasci3068101/12/2022
Tecc Designs and Solution7184105/03/2020
Building Lifecycle
02/20/2028
Facade inspection report due (FISP Cycle 9, sub-cycle B)
The filing window opened 02/21/2026. No Cycle 9 filing on record yet
10/13/2026
Permit issued — Plumbing
M01412553-S1-PL
10/06/2026
Permit issued — General Construction
M01412553-I1-GC
10/02/2026
Permit issued — Plumbing
M01403563-S1-PL
09/29/2026
Permit issued — General Construction
M01403563-I1-GC
280 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedR.J.C. Mechanical10/13/2026
DOB NOWGeneral ConstructionPermit IssuedWe Work Group10/06/2026
DOB NOWPlumbingPermit IssuedMonarch Plumbing & Heating10/02/2026
DOB NOWGeneral ConstructionPermit IssuedGruda-Ni Construction09/29/2026
DOB NOWPlumbingPermit IssuedT.N.T. Plumbing & Heating03/12/2026
DOB NOWMechanical SystemsPermit IssuedDavid Evan01/13/2026
DOB NOWGeneral ConstructionPermit IssuedDavid Evan01/12/2026
DOB NOWMechanical SystemsPermit IssuedDavid Evan11/26/2025
DOB NOWGeneral ConstructionPermit IssuedDavid Evan10/03/2025
DOB NOWGeneral ConstructionPermit IssuedDavid Evan10/03/2025
DOB NOWGeneral ConstructionSigned-offKanaris Contracting03/20/2025
DOB NOWPlumbingSigned-offM&M Plumbing & Heating03/10/2025
DOB NOWPlumbingPermit IssuedT.N.T. Plumbing & Heating02/19/2025
DOB NOWGeneral ConstructionPermit IssuedDavid Evan02/10/2025
DOB NOWMechanical SystemsPermit IssuedDavid Evan02/10/2025
DOB NOWSuspended ScaffoldSigned-offL & Z Restoration12/03/2024
DOB NOWMechanical SystemsSigned-offCoolquest Mechanical11/27/2024
DOB NOWSuspended ScaffoldPermit IssuedTwo-Tone Contracting11/22/2024
DOB NOWPlumbingSigned-offSimple Choice Plumbing and HT11/22/2024
DOB NOWGeneral ConstructionSigned-offNorman Project Management10/02/2024
DOB NOWSuspended ScaffoldPermit IssuedTwo-Tone Contracting09/11/2024
DOB NOWGeneral ConstructionSigned-offTwo-Tone Contracting06/14/2024
DOB NOWSidewalk ShedSigned-offKings Group NY05/02/2024
DOB NOWSuspended ScaffoldPermit IssuedTwo-Tone Contracting12/07/2023
DOB NOWPlumbingSigned-offMonarch Plumbing & Heating11/22/2023
DOB NOWGeneral ConstructionSigned-offGruda-Ni Construction11/06/2023
DOB NOWGeneral ConstructionSigned-offTwo-Tone Contracting05/30/2023
DOB NOWPlumbingSigned-offHydrokinetic Plumbing & Heating I05/09/2023
DOB NOWSidewalk ShedSigned-offKings Group NY05/04/2023
DOB NOWGeneral ConstructionSigned-offGallery Restoration04/24/2023
DOB NOWPlumbingSigned-offMonarch Plumbing & Heating12/09/2022
DOB NOWPlumbingSigned-offCochrane Plumbing & Heating07/15/2022
DOB NOWPlumbingSigned-offMonarch Plumbing & Heating07/13/2022
DOB NOWGeneral ConstructionSigned-offGruda-Ni Construction07/11/2022
DOB NOWSidewalk ShedSigned-offKings Group NY05/18/2022
DOB NOWGeneral ConstructionSigned-offBoxwood Construction01/16/2022
DOB NOWMechanical SystemsSigned-offGruda-Ni Construction11/16/2021
DOB NOWSidewalk ShedSigned-offKings Group NY07/13/2021
DOB NOWPlumbingSigned-offCochrane Plumbing & Heating12/01/2020
DOB NOWPlumbingSigned-offChamp Plumbing & Heating09/15/2020
+ 54 more permits on file
1 project · most recent 10/23/2024
Heating and Air Conditioning Systems
FiledStatusContractorScope
10/23/2024Signed-offCoolquest MechanicalHeating and Air Conditioning Systems
3 projects · most recent 07/02/2026
Gas Water/Sanitary
FiledStatusContractorScope
07/02/2026Permit IssuedMonarch Plumbing & HeatingGas, Water/Sanitary
01/29/2026Permit IssuedT.N.T. Plumbing & HeatingGas, Water/Sanitary
10/23/2024Signed-offSimple Choice Plumbing and HTGas, Water/Sanitary
25 projects · most recent 10/11/2026
General Wiring
FiledStatusContractorScope
10/11/2026Permit IssuedJP & Son ElectricGeneral Wiring
09/30/2026Permit IssuedAll City ElectricalGeneral Wiring
08/10/2026CompleteAxcel Electric Co—
08/01/2025CompleteElpo Electrical ContgGeneral Wiring
02/25/2025Permit IssuedConductor Electrical Services—
02/25/2025Permit IssuedConductor Electrical ServicesGeneral Wiring
03/27/2024CompleteNion ElectricGeneral Wiring
12/14/2023CompleteL.J.F. & Sons Electrical ContsGeneral Wiring
11/24/2023CompleteArgon ElectricalGeneral Wiring
09/12/2022CompleteHigh Quality Electric of—
07/11/2022Permit IssuedArgon ElectricalGeneral Wiring
10/07/2021CompleteRobert Chimenti—
05/25/2021CompleteGrid City Electric—
01/26/2021CompleteRobert Chimenti—
11/20/2020CompleteLeone Electric CoGeneral Wiring
1 project · most recent 09/05/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
09/05/2024Permit IssuedTwo-Tone ContractingSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 23
DateTypeResultReport
03/20/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/10/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/13/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/01/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/08/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/23/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/24/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/21/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/10/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/29/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/04/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/23/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/24/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/19/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
04/15/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/23/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/17/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/11/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/15/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/27/2022Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 78
DateRequirementInspectorRole
06/07/2026Fire-Resistant Penetrations and JointsIVA FILIPOVICspecial
06/07/2026Fire-Resistant Penetrations and JointsIVA FILIPOVICspecial
06/07/2026Final—progress
06/07/2026Post-installed AnchorsIVA FILIPOVICspecial
03/11/2026Fire-Resistant Penetrations and JointsVincent Gentilespecial
03/11/2026HVAC-R and service water heating system controlsRICHARD LEMANSKYenergy_progress
03/11/2026HVAC-R and service water piping design and insulationRICHARD LEMANSKYenergy_progress
03/11/2026Maintenance informationRICHARD LEMANSKYenergy_progress
03/11/2026Lighting in dwelling unitsOLGA BAKICenergy_progress
03/11/2026HVAC-R and service water heating equipmentRICHARD LEMANSKYenergy_progress
03/11/2026Energy Code Compliance InspectionsRICHARD LEMANSKYprogress
03/11/2026FinalRICHARD LEMANSKYprogress
03/11/2026Mechanical SystemsVincent Gentilespecial
01/14/2026Energy Code Compliance InspectionsRICHARD LEMANSKYprogress
01/14/2026Fire-Resistant Penetrations and JointsVincent Gentilespecial
01/14/2026Mechanical SystemsVincent Gentilespecial
01/14/2026HVAC-R and service water piping design and insulationRICHARD LEMANSKYenergy_progress
01/14/2026HVAC-R and service water heating equipmentRICHARD LEMANSKYenergy_progress
01/14/2026HVAC-R and service water heating system controlsRICHARD LEMANSKYenergy_progress
01/14/2026Lighting in dwelling unitsOLGA BAKICenergy_progress
01/14/2026Maintenance informationRICHARD LEMANSKYenergy_progress
01/14/2026FinalRICHARD LEMANSKYprogress
12/09/2025Tenant Protection Plan ComplianceChristian Meszarosspecial
10/03/2025Maintenance informationRICHARD LEMANSKYenergy_progress
10/03/2025Fire-Resistant Penetrations and JointsVincent Gentilespecial
Latest 25 of 78.
957 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account