| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 8 | 09/01/2026 |
| BUSHBURG BUILDERS | 70 | 07/17/2026 |
| RUDIN MANAGEMENT | 715 | 07/08/2026 |
| 110 WALL STREET | 17 | 07/08/2026 |
| PINE RE LLC | 1 | 03/22/2026 |
| TARGET CONSTRUCTION | 1 | 03/22/2026 |
| 80 PINE | 100 | 03/22/2026 |
| JRM CONSTRUCTION MGMT | 5 | 03/22/2026 |
| BENCHMARK BUILDERS | 1 | 03/22/2026 |
| RUDDIN MANAGEMENT CORP | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/06/2024 | $160.0M | — | 80 PINE LLC → PINE RE LLC | $145/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CETRARUDDY ARCHITECTURE DPC | 6 | 07/10/2026 |
| YOU GAO | 2 | 07/10/2026 |
| HATFIELD GROUPD ENGINEERING | 3 | 06/17/2026 |
| ENV ARCHITECTS, DPC | 1 | 05/28/2026 |
| DAGHER ENGINEERING PLLC | 11 | 11/20/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 05/14/2025 |
| SEVERUD ASSOCIATES | 13 | 04/27/2025 |
| URBAN INTEGRATIONS | 1 | 04/08/2025 |
| MSM ENGINEERING SERVICES, PLLC | 1 | 01/21/2025 |
| BKA ARCHITECTS | 2 | 06/05/2024 |
| LORING CONSULTING ENGINEERS, INC. | 48 | 10/03/2023 |
| TPG ARCHITECTURE, LLP | 3 | 08/04/2023 |
| JOHN F. GIUSEFFI, ARCHITECT, PC | 4 | 05/24/2023 |
| ANTONIO LEO ARCHITECT | 9 | 04/11/2023 |
| FOGARTY FINGER ARCHITECTURE PLLC | 10 | 03/30/2023 |
| MONTROY ARCHITECTURE PLLC | 1 | 02/22/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 2 | 02/16/2023 |
| JAROS BAUM & BOLLES | 24 | 01/26/2023 |
| MOHAMMAD AHEAD, PE | 2 | 09/27/2022 |
| COSENTINI ASSOCIATES | 3 | 08/17/2022 |
| ENTHINK ENGINEERS LLC | 1 | 08/17/2022 |
| HOWARD I SHAPIRO & ASSOCIATES | 1 | 07/14/2022 |
| OFFICE OF JAMES RUDERMAN | 2 | 05/13/2022 |
| ROBERT DERECTOR ASSOCIATES | 3 | 04/11/2022 |
| A/R ENVIRONETICS ARCHITECTS PC | 1 | 04/08/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 49 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 20 | 03/21/2026 |
| GREEN LIGHT EXPEDITING LLC | 68 | 03/21/2026 |
| JM ZONING, LLC. | 32 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| UNITED SAFETY CONSULTANTS | 1 | 03/21/2026 |
| RIZZO GROUP | 8 | 03/21/2026 |
| LOUIS STRIAR | 12 | 03/21/2026 |
| WILLIAM VITTACO ASSOCIATES | 11 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JRM CONSTRUCTION MGMT LLC | General Contractor | 46 | 07/08/2026 |
| TARGET CONSTRUCTION LLC | General Contractor | 17 | 07/08/2026 |
| JAMES E FITZGERALD INC | General Contractor | 16 | 07/08/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 8 | 07/08/2026 |
| RETAIL PROJECT MANGEMENT | General Contractor | 7 | 07/08/2026 |
| COGEN ELEC'L SERVICES,INC | Electrical | 7 | 03/22/2026 |
| TOWER FIRE PROTECTION INC | Fire Protection | 7 | 07/08/2026 |
| A + SPRINKLER CORP | Fire Protection | 6 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 6 | 09/01/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 6 | 07/08/2026 |
| A PLUS PLUMBING CORP | Plumbing | 6 | 07/08/2026 |
| ON-TRAC CONSTRUCTION ASSO | General Contractor | 4 | 04/09/2026 |
| HUNTER ROBERTS CONSTRUCTION | General Contractor | 4 | 07/08/2026 |
| A & M WARSHAW PLBG & HTG | Plumbing | 4 | 07/08/2026 |
| BENCHMARK BUILDERS LLC | General Contractor | 4 | 04/09/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 4 | 07/17/2026 |
| TEAM ELECTRIC, INC | Electrical | 3 | 03/22/2026 |
| CHARLES TRILIVAS | Electrical | 3 | 03/21/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 3 | 07/08/2026 |
| TRISTATE PLBG SVCS CORP | Plumbing | 3 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 3 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 3 | 07/08/2026 |
| ALLSTATE SPRINKLER LLC | Fire Protection | 2 | 07/08/2026 |
| THOMPSON MICHAEL | Electrical | 2 | 03/21/2026 |
| MARLIN MECHANICAL INC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 16 | 07/10/2026 |
| YOU GAO | 9407 | 2 | 07/10/2026 |
| PROJECT TACTICAL SOLUTION | 5859 | 1 | 05/28/2026 |
| BIG APPLE GROUP NY, LLC | 1258 | 2 | 05/08/2025 |
| SOCOTEC ENGINEERING | 4983 | 1 | 06/05/2024 |
| CROSSCHECK INSPECTION SER | 544 | 110 | 10/03/2023 |
| ETI CONSULTANTS LLC | 7694 | 2 | 02/01/2022 |
| LORING CONSULTING ENGINEE | 3311 | 5 | 09/01/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 08/31/2026 |
| DOB NOW | Sign | Permit Issued | NEPTUNE SIGNS&AWNINGS INC | 08/24/2026 |
| DOB NOW | Sprinklers | Permit Issued | SAFETY FIRE SPRINKLER CORP | 07/16/2026 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 06/24/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC. | 06/08/2026 |
| DOB NOW | General Construction | Permit Issued | DESIMONE BUILDERS LLC | 06/01/2026 |
| DOB NOW | Construction Fence | Permit Issued | TARGET CONSTRUCTION LLC | 05/26/2026 |
| DOB NOW | Structural | Permit Issued | TARGET CONSTRUCTION LLC | 05/15/2026 |
| DOB NOW | Sprinklers | Permit Issued | SAFETY FIRE SPRINKLER CORP | 05/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | TARGET CONSTRUCTION LLC | 04/29/2026 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 04/01/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC | 03/10/2026 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 02/11/2026 |
| DOB NOW | Plumbing | Signed-off | YG SERVICES INC | 02/09/2026 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 06/26/2025 |
| DOB NOW | Structural | Permit Issued | TARGET CONSTRUCTION LLC | 05/30/2025 |
| DOB NOW | Sprinklers | Permit Issued | SAFETY FIRE SPRINKLER CORP | 05/12/2025 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 05/05/2025 |
| DOB NOW | Construction Fence | Permit Issued | TARGET CONSTRUCTION LLC | 04/09/2025 |
| DOB NOW | Plumbing | Permit Issued | YG SERVICES INC | 03/18/2025 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 03/14/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC | 03/11/2025 |
| DOB NOW | Sprinklers | Permit Issued | SAFETY FIRE SPRINKLER CORP | 03/06/2025 |
| DOB NOW | Structural | Permit Issued | TARGET CONSTRUCTION LLC | 03/05/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | TARGET CONSTRUCTION LLC | 03/04/2025 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 02/28/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | TARGET CONSTRUCTION LLC | 02/18/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | GWT ENTERPRISES INC | 01/21/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | GWT ENTERPRISES INC | 01/21/2025 |
| DOB NOW | Mechanical Systems | Signed-off | STAR COMPANIESS LLC | 11/18/2024 |
| DOB NOW | General Construction | Signed-off | STAR COMPANIESS LLC | 11/18/2024 |
| DOB NOW | Plumbing | Signed-off | MICHAEL ITSKOVICH | 11/15/2024 |
| DOB NOW | General Construction | Permit Issued | ATLANTIC CONSTRUCTION SER | 06/10/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | ATLANTIC CONSTRUCTION SER | 06/07/2024 |
| DOB NOW | Structural | Signed-off | BENCHMARK BUILDERS LLC | 06/16/2023 |
| DOB NOW | General Construction | Signed-off | BENCHMARK BUILDERS LLC | 06/16/2023 |
| DOB NOW | Structural | Signed-off | BENCHMARK BUILDERS LLC | 05/26/2023 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 04/14/2023 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 04/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | MARLIN MECHANICAL INC | 04/10/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/10/2026 | Permit Issued | TARGET CONSTRUCTION LLC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PQRY-P120YLMU-A2 135,000 BTU · Vrf Outdoor ×1 PQRY-P144YLMU-A2 160,000 BTU · Vrf Outdoor ×1 PQRY-P96YLMU-A2 108,000 BTU · Vrf Outdoor ×1 |
| 01/16/2025 | Permit Issued | TARGET CONSTRUCTION LLC | Air Conditioning Systems | Cooling Trane GEVK0604 50,250 BTU · Wshp ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | SAFETY FIRE SPRINKLER COR | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | MPI PLUMBING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/23/2026 | Permit Issued | TFK ELECTRIC CORP | General Wiring |
| 05/04/2026 | Complete | GREEN APPLE ELECL SVCS LL | — |
| 05/01/2026 | Complete | GREEN APPLE ELECL SVCS LL | — |
| 04/24/2026 | Permit Issued | NEE ELECTRICAL, LLC | — |
| 11/26/2025 | Permit Issued | TFK ELECTRIC CORP | General Wiring |
| 11/24/2025 | Permit Issued | MAN POWER ELECTRIC INC | — |
| 11/24/2025 | Permit Issued | TFK ELECTRIC CORP | General Wiring |
| 04/17/2025 | Permit Issued | SOLAS ELECTRICAL CORP | — |
| 03/06/2025 | Permit Issued | MAN POWER ELECTRIC INC | — |
| 01/21/2025 | Permit Issued | RICHARD NEU | — |
| 06/07/2024 | Complete | BIGMAN BROS., INC. | General Wiring |
| 02/27/2024 | Complete | COGEN ELEC'L SERVICES,INC | — |
| 02/01/2024 | Complete | COGEN ELEC'L SERVICES,INC | General Wiring |
| 12/20/2023 | Complete | COGEN ELEC'L SERVICES,INC | General Wiring |
| 12/05/2023 | Complete | COGEN ELEC'L SERVICES,INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | SAFETY FIRE SPRINKLER COR | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2025 | Permit Issued | CORE SCAFFOLD SYSTEMS INC | Sidewalk Shed |
| 01/21/2025 | Permit Issued | GWT ENTERPRISES INC | Fence, Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/28/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/11/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/06/2026 | Pass CND-Occupancy Inspection | Pass | View ↗ |
| 02/20/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/10/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/10/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/29/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/06/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 12/04/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/01/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/19/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/08/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 08/06/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/06/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/06/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/16/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/20/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/15/2026 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 07/15/2026 | Luminous Exit Path Markings | SOORJBALLY HARILALL | special |
| 07/15/2026 | Mastic and Intumescent Fire-resistant Coatings | SOORJBALLY HARILALL | special |
| 07/15/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | SOORJBALLY HARILALL | special |
| 07/15/2026 | Energy Code Compliance Inspections | SOORJBALLY HARILALL | progress |
| 07/15/2026 | Sprayed fire-resistant materials | SOORJBALLY HARILALL | special |
| 07/15/2026 | Wall Panels, Curtain Walls, and Veneers | SOORJBALLY HARILALL | special |
| 07/10/2026 | Final | You Gao | progress |
| 07/10/2026 | Structural Stability – Alterations of existing buildings | You Gao | special |
| 06/17/2026 | Air barrier - visual inspection | — | energy_progress |
| 06/17/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 06/17/2026 | Fenestration areas | — | energy_progress |
| 06/17/2026 | Fenestration air leakage | — | energy_progress |
| 06/15/2026 | Tenant Protection Plan Compliance | — | special |
| 06/15/2026 | Energy Code Compliance Inspections | — | progress |
| 06/15/2026 | Wall Panels, Curtain Walls, and Veneers | — | special |
| 06/15/2026 | Preliminary | — | progress |
| 05/06/2026 | Final | Max Lee | progress |
| 05/06/2026 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 03/23/2026 | Energy Code Compliance Inspections | SOORJBALLY HARILALL | progress |
| 03/23/2026 | Fenestration areas | SOORJBALLY HARILALL | energy_progress |
| 03/23/2026 | Sprayed fire-resistant materials | SOORJBALLY HARILALL | special |
| 03/23/2026 | Mastic and Intumescent Fire-resistant Coatings | SOORJBALLY HARILALL | special |
| 03/23/2026 | Chimneys and vents | SOORJBALLY HARILALL | special |
| 03/23/2026 | Fire-Resistance Rated Construction | SOORJBALLY HARILALL | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Vibrant | Office | Floors 18, 19 | Project M00826137 Project M00822918 |
| Elefterakis, Elefterakis & Panek | Office | Floors 36, 38 | Project M08009174 Project M08009168 Project M00481512 |
| CureMD & Infopro | Office | Floor 21 | Project M00736843 |
| AccuWeather | Office | Floor 26 | Project M00706592 |
| NYPIUA | Office | Floor 31 | Project M00690716 |
| Cure MD | Office | Floor 21 | Project M00646721 Project M00646623 |
| Pranary Digital | Office | Floor 30 | Project M00669044 |
| January Digital | Office | Floor 30 | Project M00667849 |
| Lactalis American Group | Office | Floor 35 | Project M00499295 Project M00499287 |