RoofUnder Construction15p · 1 filing · 4 docs
ArchitectureMechanical
Issued Permit Scope
General Construction
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 221p · 1 filing · 4 docs
Fire Protection
Sprinkler modifications taking place on the 5, 6, 9, 14, 16, 17, 19, 21 and 22 floors as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 1 drawing sheet
Floor 21Under Construction19p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 20Under Construction25p · 4 filings · 20 docs
ArchitectureDMGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Minor demolition with modifications to existing reception area to accommodate open plan seating. Patching ceilings, walls, floors and columns on the 20th floor (Hall Capital Partners) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 5 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 19Under Construction17p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Sprinkler modifications taking place on the 5, 6, 9, 14, 16, 17, 19, 21 and 22 floors as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 1 drawing sheet
Floor 18Under Construction16p · 2 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Floor 17Under Construction16p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Sprinkler modifications taking place on the 5, 6, 9, 14, 16, 17, 19, 21 and 22 floors as per plans filed herewith. No change in use, egress or occupancy
On file for this project
4 documents · 1 drawing sheet
Floor 16Under Construction18p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 15Under Construction27p · 5 filings · 20 docs
ArchitectureGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 14Under Construction17p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 13Under Construction18p · 3 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Floor 12Under Construction15p · 2 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Floor 11Under Construction21p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 10Under Construction26p · 8 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 9Under Construction18p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 8Under Construction20p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 7Under Construction19p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 6Under Construction21p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 5Under Construction21p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 4Under Construction20p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 3Under Construction20p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 1ST, 2ND AND 3RD FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
41 documents
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Latest 3 of 5 filings on this floor.
Floor 2Under Construction26p · 9 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
GENERAL CONSTRUCTION AND FACADE MODIFICATIONS TAKING PLACE ON FLOORS 2-21 AND ROOF AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 1ST, 2ND AND 3RD FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
41 documents
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Latest 3 of 8 filings on this floor.
Floor 1Under Construction13p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 1ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
13 documents · 2 drawing sheets
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 1ST, 2ND AND 3RD FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
41 documents
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
Latest 3 of 7 filings on this floor.
CellarUnder Construction8p · 5 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 1ST, 2ND AND 3RD FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
41 documents
STRUCTURAL MODIFICATIONS TAKING PLACE ON FLOORS 1 - 21 AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
33 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE IN THE CELLAR, FLOORS 1-11, 13-16TH AND 21ST FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.