| Firm | Filings | Most Recent |
|---|---|---|
| LAWRENCE K. SHAPIRO & ASSOCIATES | 1 | 05/27/2026 |
| NYCDEP | 3 | 10/23/2023 |
| WILLIAM B. LOFTUS, P.E. | 1 | 05/24/2023 |
| NYC DEP | 1 | 05/24/2023 |
| NEW YORK CITY DEP | 1 | 07/08/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| HDR | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 2 | 03/21/2026 |
| RPO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JOHN P PICONE INC | General Contractor | 23 | 08/14/2026 |
| WELKIN ENTERPRISES,LLC | Plumbing | 4 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AEIS LLC | 280 | 1 | 10/23/2023 |
| M & J ENGINEERING PC | 7419 | 5 | 10/23/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | JOHN P PICONE INC | 08/13/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | JOHN P PICONE INC | 06/04/2026 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 06/03/2026 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 06/03/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN P PICONE INC | 06/02/2026 |
| DOB NOW | Support of Excavation | Permit Issued | JOHN P PICONE INC | 06/02/2026 |
| DOB NOW | Plumbing | Permit Issued | WELKIN ENTERPRISES,LLC | 09/05/2025 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 08/12/2025 |
| DOB NOW | Structural | Permit Issued | JOHN P PICONE INC | 07/30/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN P PICONE INC | 07/30/2025 |
| DOB NOW | Support of Excavation | Permit Issued | JOHN P PICONE INC | 07/29/2025 |
| DOB NOW | Earth Work | Permit Issued | JOHN P PICONE INC | 05/23/2025 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 05/23/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN P PICONE INC | 11/26/2024 |
| DOB NOW | Plumbing | Permit Issued | WELKIN ENTERPRISES,LLC | 08/02/2024 |
| DOB NOW | Earth Work | Permit Issued | JOHN P PICONE INC | 07/31/2024 |
| DOB NOW | Support of Excavation | Permit Issued | JOHN P PICONE INC | 07/31/2024 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 07/31/2024 |
| DOB NOW | Plumbing | Permit Issued | WELKIN ENTERPRISES,LLC | 07/01/2024 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 06/26/2024 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 11/28/2023 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 11/02/2023 |
| DOB NOW | Support of Excavation | Permit Issued | JOHN P PICONE INC | 10/03/2023 |
| DOB NOW | Plumbing | Permit Issued | WELKIN ENTERPRISES,LLC | 08/17/2023 |
| DOB NOW | General Construction | Permit Issued | JOHN P PICONE INC | 05/30/2023 |
| DOB NOW | Support of Excavation | Permit Issued | JOHN P PICONE INC | 05/26/2023 |
| DOB NOW | Foundation | Permit Issued | JOHN P PICONE INC | 03/07/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2023 | Permit Issued | JOHN P PICONE INC | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/28/2023 | Permit Issued | VERDE ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2023 | Permit Issued | JOHN P PICONE INC | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/01/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/17/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/17/2026 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 06/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/12/2026 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 06/11/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/22/2024 | Fire-Resistant Penetrations and Joints | ABDUL SOMAT | special |
| 01/22/2024 | Mastic and Intumescent Fire-resistant Coatings | ABDUL SOMAT | special |
| 10/23/2023 | Concrete - Cast-In-Place | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Concrete - Precast | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Deep Foundation Elements | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Masonry | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Post-installed Anchors | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Sprayed fire-resistant materials | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Structural Cold-Formed Steel | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Structural Steel - Details | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Structural Steel - High Strength Bolting | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Structural Steel - Welding | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Subgrade Inspections | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Subsurface Conditions – Fill Placement & In-Place Density | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Lighting controls | IAN JONATHAN GONZALES | energy_progress |
| 10/23/2023 | Aluminum Construction | IAN JONATHAN GONZALES | special |
| 10/23/2023 | Maintenance information | IAN JONATHAN GONZALES | energy_progress |
| 10/23/2023 | Protection of exposed foundation insulation | IAN JONATHAN GONZALES | energy_progress |
| 10/23/2023 | Lighting in dwelling units | IAN JONATHAN GONZALES | energy_progress |
| 10/23/2023 | Energy Code Compliance Inspections | IAN JONATHAN GONZALES | progress |
| 10/23/2023 | Final | Amr Aly | progress |
| 10/23/2023 | Fire-Resistance Rated Construction | IAN JONATHAN GONZALES | progress |
| 10/23/2023 | Footing and Foundation | IAN JONATHAN GONZALES | progress |
| 10/23/2023 | Lowest Floor Elevation | IAN JONATHAN GONZALES | progress |