| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01056400 ↗ | 50 WEST 34TH STREET MANHATTAN | Alteration | Signed-off | 05/24/2024 | 08/08/2024 | Design TMALIHAN ARCHITECT NYC, LLC. Contractor BR CONSTRUCTION GROUP INC | REMOVE EXISTING TEMPORARY STRUCTURE FOR TEMPORARY EXHIBIT: HARRY POTTER |
| M00835178 ↗ | 50 WEST 34TH STREET MANHATTAN | Alteration | Signed-off | 03/21/2023 | 04/05/2023 | Design TMALIHAN ARCHITECT NYC, LLC. Owner HERALD TOWERS LLC Contractor AUTHENTIC PLBG CORP | Temporary Use/ Exhibit Harry Potter The Exhibition New York: Respectfully submitting PAA to revise plan to omit Electric Water Heater per Pl… |
| S08031408 ↗ | 1205 CASTLETON AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 11/28/2022 | — | Design TMALIHAN ARCHITECT NYC, LLC. | — |
| M00517705 ↗ | 1 NORTH END AVENUE MANHATTAN | Alteration | Signed-off | 05/17/2021 | 12/30/2021 | Design TMALIHAN ARCHITECT NYC, LLC. Contractor BR CONSTRUCTION GROUP INC | Interior temporary exhibit- Van Gogh: The Immersive Experience. Installation of temporary structure - non load bearing partitions and minor … |
| M00626668 ↗ | 234 WEST 42 STREET MANHATTAN | Alteration | Signed-off | 11/23/2021 | 11/30/2021 | Design TMALIHAN ARCHITECT NYC, LLC. Contractor SJG CONSTRUCTION CORP | RELOCATE PENDANT HUNG HEX LIGHT HOUSING TO WALL MOUNTED ON THE EXISTING 7TH FLOOR MADAME TUSSAUDS, NEW YORK. NO CHANGE IN USE, EGGRESS OR O… |
| Name | Projects together | Most recent |
|---|---|---|
| TMALIHAN ARCHITECT NYC, LLC. | 5 | 05/24/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| BR CONSTRUCTION GROUP INC | 3 | 05/24/2024 |
| S.O.S. PLBG & HTG LTD | 1 | 05/01/2023 |
| SJG CONSTRUCTION CORP | 1 | 03/28/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| HERALD TOWERS, INC. | 1 | 05/01/2023 |
| NYC ECONOMIC DEVELOPMENT CORP | 1 | 03/28/2022 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01056400 ↗ | 50 WEST 34TH STREET MANHATTAN | Alteration | Signed-off | 05/24/2024 | 08/08/2024 | Design TMALIHAN ARCHITECT NYC, LLC. Contractor BR CONSTRUCTION GROUP INC | REMOVE EXISTING TEMPORARY STRUCTURE FOR TEMPORARY EXHIBIT: HARRY POTTER |
| M00835178 ↗ | 50 WEST 34TH STREET MANHATTAN | Alteration | Signed-off | 03/21/2023 | 04/05/2023 | Design TMALIHAN ARCHITECT NYC, LLC. Owner HERALD TOWERS LLC Contractor AUTHENTIC PLBG CORP | Temporary Use/ Exhibit Harry Potter The Exhibition New York: Respectfully submitting PAA to revise plan to omit Electric Water Heater per Pl… |
| S08031408 ↗ | 1205 CASTLETON AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 11/28/2022 | — | Design TMALIHAN ARCHITECT NYC, LLC. | — |
| M00517705 ↗ | 1 NORTH END AVENUE MANHATTAN | Alteration | Signed-off | 05/17/2021 | 12/30/2021 | Design TMALIHAN ARCHITECT NYC, LLC. Contractor BR CONSTRUCTION GROUP INC | Interior temporary exhibit- Van Gogh: The Immersive Experience. Installation of temporary structure - non load bearing partitions and minor … |
| M00626668 ↗ | 234 WEST 42 STREET MANHATTAN | Alteration | Signed-off | 11/23/2021 | 11/30/2021 | Design TMALIHAN ARCHITECT NYC, LLC. Contractor SJG CONSTRUCTION CORP | RELOCATE PENDANT HUNG HEX LIGHT HOUSING TO WALL MOUNTED ON THE EXISTING 7TH FLOOR MADAME TUSSAUDS, NEW YORK. NO CHANGE IN USE, EGGRESS OR O… |
| Building | Filings | Most Recent |
|---|---|---|
| 50 WEST 34TH STREET ↗ | 4 | 05/24/2024 |
| 1205 CASTLETON AVENUE ↗ | 1 | 11/28/2022 |
| 1 NORTH END AVENUE ↗ | 2 | 03/30/2022 |
| 234 WEST 42 STREET ↗ | 2 | 03/28/2022 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 05/24/2024 | Fire-Resistant Penetrations and Joints | 50 WEST 34TH STREET | Teresa Malihan-Haggerty | special |
| 05/23/2024 | Final | 50 WEST 34TH STREET | Teresa Malihan-Haggerty | progress |
| 05/02/2023 | Fire-Resistant Penetrations and Joints | 50 WEST 34TH STREET | Teresa Malihan-Haggerty | special |
| 05/02/2023 | Energy Code Compliance Inspections | 50 WEST 34TH STREET | Teresa Malihan-Haggerty | progress |
| 11/28/2022 | Fenestration air leakage | 1205 CASTLETON AVENUE | — | energy_progress |
| 11/28/2022 | Fenestration and door U-factor and product ratings | 1205 CASTLETON AVENUE | — | energy_progress |
| 11/28/2022 | Interior lighting power | 1205 CASTLETON AVENUE | — | energy_progress |
| 11/28/2022 | Fire-Resistance Rated Construction | 1205 CASTLETON AVENUE | — | progress |
| 11/28/2022 | Energy Code Compliance Inspections | 1205 CASTLETON AVENUE | — | progress |
| 11/28/2022 | Masonry | 1205 CASTLETON AVENUE | Teresa Malihan-Haggerty | special |
| 11/28/2022 | Fire-Resistant Penetrations and Joints | 1205 CASTLETON AVENUE | Teresa Malihan-Haggerty | special |
| 11/04/2022 | Final | 1205 CASTLETON AVENUE | Teresa Malihan-Haggerty | progress |
| 03/30/2022 | Final | 234 WEST 42 STREET | Teresa Malihan-Haggerty | progress |
| 03/30/2022 | Fire-Resistant Penetrations and Joints | 234 WEST 42 STREET | Teresa Malihan-Haggerty | special |
| 03/30/2022 | Sprayed fire-resistant materials | 234 WEST 42 STREET | Teresa Malihan-Haggerty | special |
| 03/22/2022 | Fire-Resistant Penetrations and Joints | 1 NORTH END AVENUE | Teresa Malihan-Haggerty | special |
| 03/22/2022 | Final | 1 NORTH END AVENUE | Teresa Malihan-Haggerty | progress |
| 03/18/2022 | Final | 234 WEST 42 STREET | Teresa Malihan-Haggerty | progress |
| 03/18/2022 | Sprayed fire-resistant materials | 234 WEST 42 STREET | Teresa Malihan-Haggerty | special |
| 03/18/2022 | Fire-Resistant Penetrations and Joints | 234 WEST 42 STREET | Teresa Malihan-Haggerty | special |