| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01175202 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 03/03/2025 | 03/06/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLMNG & HTG CORP Filer MARY MCKEOWN | Arc'Teryx, Space B - New sprinkler heads and piping in existing commercial space for new tenant layout . No change in egress use or occupan… |
| M01175198 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 03/03/2025 | 03/05/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLUMBING & HEATIN Filer MARY MCKEOWN | ARC'TERYX Space B - New plumbing fixtures per plans filed herewith to accommodate new layout for New tenant Arc'Teryx. No change in egress… |
| M01175654 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 02/28/2025 | 03/03/2025 | Contractor STEADFAST DEVELOPMENT AND Filer MARY MCKEOWN | ARC'TERYX, SPACE B - Structural work associated with new tenant build out as per plans filed herewith. No change in egress, use or occupanc… |
| M01156185 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/17/2025 | 02/18/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLMNG & HTG CORP Filer MARY MCKEOWN | Arc'Teryx - Removal of existing sprinkler heads and piping in existing commercial space for new tenant layout . Installation of temporary lo… |
| M01150852 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Permit Issued | 01/17/2025 | 02/06/2025 | Design MEYERS+ ENGINEERS Contractor STEADFAST DEVELOPMENT AND Filer MARY MCKEOWN | Arc'teryx - Partial Removal/Installation of mechanical equipment and associated ducts and piping as per plans filed herewith. . No change i… |
| M01150884 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/17/2025 | 02/03/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLUMBING & HEATIN Filer MARY MCKEOWN | ARC'TERYX - FILING FOR REMOVAL OF PLUMBING FIXTURES. CAP ALL UNUSED PIPING. NO CHANGE IN EGRESS, USE OR OCCUPANCY. |
| Name | Projects together | Most recent |
|---|---|---|
| MEYERS+ ENGINEERS | 5 | 01/30/2026 |
| SALVATOR A. CARADONNA JR. | 3 | 05/30/2024 |
| M-ENGINEERING NEW YORK, LLC | 2 | 08/02/2023 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 1 | 09/10/2025 |
| Z.S. ENGINEERING, D.P.C. | 1 | 07/05/2023 |
| skylab architecture | 1 | 01/02/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| STEADFAST DEVELOPMENT AND | 4 | 01/30/2026 |
| SKINNER PLMNG & HTG CORP | 3 | 09/12/2025 |
| NATIONAL MAINTENANCE, INC | 2 | 01/23/2023 |
| SKINNER PLUMBING & HEATIN | 2 | 03/03/2025 |
| COMMERCIAL CONSTRUCTION M | 1 | 08/02/2023 |
| MAUCERI SIGN CO., INC | 1 | 05/30/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| RCPI LANDMARK PROPERTIES, LLC | 6 | 01/30/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| MARY MCKEOWN | 6 | 01/30/2026 |
| WILLIAM VITACCO ASSOCIATES | 2 | 07/05/2023 |
| ALL IN PERMIT CONSULTANTS | 1 | 05/30/2024 |
| BURNHAM NATIONWIDE INC | 1 | 08/02/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01175202 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 03/03/2025 | 03/06/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLMNG & HTG CORP Filer MARY MCKEOWN | Arc'Teryx, Space B - New sprinkler heads and piping in existing commercial space for new tenant layout . No change in egress use or occupan… |
| M01175198 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 03/03/2025 | 03/05/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLUMBING & HEATIN Filer MARY MCKEOWN | ARC'TERYX Space B - New plumbing fixtures per plans filed herewith to accommodate new layout for New tenant Arc'Teryx. No change in egress… |
| M01175654 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 02/28/2025 | 03/03/2025 | Contractor STEADFAST DEVELOPMENT AND Filer MARY MCKEOWN | ARC'TERYX, SPACE B - Structural work associated with new tenant build out as per plans filed herewith. No change in egress, use or occupanc… |
| M01156185 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/17/2025 | 02/18/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLMNG & HTG CORP Filer MARY MCKEOWN | Arc'Teryx - Removal of existing sprinkler heads and piping in existing commercial space for new tenant layout . Installation of temporary lo… |
| M01150852 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Permit Issued | 01/17/2025 | 02/06/2025 | Design MEYERS+ ENGINEERS Contractor STEADFAST DEVELOPMENT AND Filer MARY MCKEOWN | Arc'teryx - Partial Removal/Installation of mechanical equipment and associated ducts and piping as per plans filed herewith. . No change i… |
| M01150884 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/17/2025 | 02/03/2025 | Design MEYERS+ ENGINEERS Contractor SKINNER PLUMBING & HEATIN Filer MARY MCKEOWN | ARC'TERYX - FILING FOR REMOVAL OF PLUMBING FIXTURES. CAP ALL UNUSED PIPING. NO CHANGE IN EGRESS, USE OR OCCUPANCY. |
| M01123505 ↗ | 600 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/02/2025 | 01/09/2025 | Design skylab architecture Contractor STEADFAST DEVELOPMENT AND | Removal of non load bearing partitions, flooring, ceilings, finishes, escalator and stairs per plans filed herewith to accommodate new layou… |
| M01039906 ↗ | 149 5 AVENUE MANHATTAN | Alteration | Signed-off | 05/30/2024 | 06/24/2024 | Design SALVATOR A. CARADONNA JR. Contractor MAUCERI SIGN CO., INC | Modify existing approved signage to include indirect lighting fixtures. Signage approved under #M00738193. |
| M00833789 ↗ | 250 VESEY STREET MANHATTAN | Alteration | Signed-off | 03/24/2023 | 04/03/2023 | Design Z.S. ENGINEERING, D.P.C. Contractor SKINNER PLMNG & HTG CORP | Modifications to an existing sprinkler system for new retail tenant (Arc'Teryx, Space 115). |
| M00831161 ↗ | 250 VESEY STREET MANHATTAN | Alteration | Signed-off | 03/27/2023 | 03/30/2023 | Design M-ENGINEERING NEW YORK, LLC Contractor STEADFAST DEVELOPMENT AND | Structural work as shown on plans. (Unit 115- Arc'Teryx). |
| M00738193 ↗ | 149 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/23/2023 | 01/25/2023 | Design SALVATOR A. CARADONNA JR. Contractor NATIONAL MAINTENANCE, INC | ERECT NON-ILLUMINATED ACCESSORY BUSINESS SIGN AND D/F BLADE SIGN ON 5TH AVENUE ELEVATION. SIGNS ACCESSORY TO ARCTERYX |
| M00731912 ↗ | 149 5 AVENUE MANHATTAN | Alteration | Signed-off | 07/15/2022 | 07/22/2022 | Design M-ENGINEERING NEW YORK, LLC Contractor COMMERCIAL CONSTRUCTION M Filer BURNHAM NATIONWIDE INC | Filing herewith application for Mechanical work as per drawings submitted. No change in use, egress or occupancy. |
| M00436004 ↗ | 139 5 AVENUE MANHATTAN | Alteration | Signed-off | 01/12/2021 | 01/22/2021 | Design SALVATOR A. CARADONNA JR. Contractor NATIONAL MAINTENANCE, INC | ERECT NON-ILLUMINATED BUSINESS WALL SIGN & (1) NON-ILLUMINATED D/F BLADE SIGN. SIGNS ARE ACCESSORY TO ARC'TERYX. NO CHANGE IN USE, EGRESS … |
| Building | Filings | Most Recent |
|---|---|---|
| 600 5 AVENUE ↗ | 7 | 01/30/2026 |
| 149 5 AVENUE ↗ | 3 | 05/30/2024 |
| 250 VESEY STREET ↗ | 2 | 07/05/2023 |
| 139 5 AVENUE ↗ | 1 | 01/12/2021 |