Back
Tenant
Baccarat
Tenant
MANHATTAN · 6
1 building
6
Total Filings
6
Projects on File
1
Buildings Worked
0
Projects w/ Open Permits
Tenant
Primary Trade
Activity
Projects by first filing month6 projects all-time
0246Jun '25 · 5Nov '25 · 1Jun '25Jul '25Aug '25Sep '25Oct '25Nov '25
bars = month · line = 3-mo average
Portfolio status
Browse projects →
Signed off6100%
By project type
Alteration6
Most active buildings
All buildings →
33 9TH AVENUEMANHATTAN · latest 12/04/2025
6 projects
Key relationships
Everyone →
Design firms
Filing representatives
4 projects
1 projects
Contractors
3 projects
1 projects
1 projects
Owners
Most recent projects
All projects →
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
M01308237 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off11/18/202512/04/2025
Contractor WEINFELD, ELLIOT
Replacement Face on existing Illuminated Sign Cabinet as per NYC Landmark Preservation Commission Approval MISC-26-01118 - Baccarat - No cha…
M01235835 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/25/202507/29/2025Baccarat Sprinkler work associated with build out. No change in egress, use or occupancy.
M01234575 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/25/202507/16/2025Baccarat Minor plumbing work associated with build out. No change in egress, use or occupancy.
M01234640 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/25/202507/11/2025
Contractor MICHILLI INC
Baccarat. Mechanical work associated with tenant build out. No change in egress, use or occupancy.
M01235961 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/26/202507/08/2025
Contractor MICHILLI INC
Baccarat Structural work associated with tenant build out per plans filed herewith. Structural support for HVAC units, new had rail and ada…
M01234559 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/23/202507/07/2025
Contractor MICHILLI INC
Baccarat Install non load bearing partition, flooring, ceilings, finishes, ADA ramp and fixtures per plans filed herewith. No change in egr…
Counts cover all 6 projects (6 DOB NOW). Dated by first filing; BIS projects by first permit issuance.
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Meyers+ Engineers306/25/2025
Christie Engineering111/06/2025
Leon Skvirsky PE111/18/2025
O'Neil Langan Architects106/23/2025
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Michilli311/06/2025
A + Sprinkler106/25/2025
L.S. Sign Co111/18/2025
MCL NY Industries106/25/2025
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Midtown Equities511/18/2025
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Mary McKeown411/06/2025
Louis Striar111/18/2025
6 DOB NOW projects, anchored the same way as Buildings Worked. Status is the project's permit state today: open = at least one permit currently issued. BIS projects show their raw permit status and are not counted as open.
All 6Signed off 6
6 projects
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
M01308237 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off11/18/202512/04/2025
Contractor WEINFELD, ELLIOT
Replacement Face on existing Illuminated Sign Cabinet as per NYC Landmark Preservation Commission Approval MISC-26-01118 - Baccarat - No cha…
M01235835 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/25/202507/29/2025Baccarat Sprinkler work associated with build out. No change in egress, use or occupancy.
M01234575 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/25/202507/16/2025Baccarat Minor plumbing work associated with build out. No change in egress, use or occupancy.
M01234640 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/25/202507/11/2025
Contractor MICHILLI INC
Baccarat. Mechanical work associated with tenant build out. No change in egress, use or occupancy.
M01235961 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/26/202507/08/2025
Contractor MICHILLI INC
Baccarat Structural work associated with tenant build out per plans filed herewith. Structural support for HVAC units, new had rail and ada…
M01234559 ↗33 9TH AVENUE
MANHATTAN
AlterationSigned-off06/23/202507/07/2025
Contractor MICHILLI INC
Baccarat Install non load bearing partition, flooring, ceilings, finishes, ADA ramp and fixtures per plans filed herewith. No change in egr…
Click a row for this entity's own projects, plans and documents at that building.
BuildingFilingsMost Recent
33 9TH AVENUE ↗611/18/2025
▾Documents — 34 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/23/2026M01234559-I1 · 33 9TH AVENUERequest digital key ↗
08/23/2026M01235835-I1 · 33 9TH AVENUERequest digital key ↗
08/23/2026M01234575-I1 · 33 9TH AVENUERequest digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits6
▸DOB NOWLPC Approval/Permit6
08/13/2026M01234640-I1 · 33 9TH AVENUEOpen ↗
08/13/2026M01234575-I1 · 33 9TH AVENUEOpen ↗
08/13/2026M01235961-P1 · 33 9TH AVENUEOpen ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/23/2026M01234640-I1 · 33 9TH AVENUEOpen ↗
08/23/2026M01235961-P1 · 33 9TH AVENUEOpen ↗
08/23/2026M01235961-I1 · 33 9TH AVENUEOpen ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026M01235835-I1 · 33 9TH AVENUEOpen ↗
09/23/2026M01235835-I1 · 33 9TH AVENUEOpen ↗
08/28/2026M01235961-P1 · 33 9TH AVENUEOpen ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026M01235961-P1 · 33 9TH AVENUEOpen ↗
08/28/2026M01235961-P1 · 33 9TH AVENUEOpen ↗
08/26/2026M01234559-I1 · 33 9TH AVENUEOpen ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/23/2026M01234640-I1 · 33 9TH AVENUEOpen ↗
08/23/2026M01235961-I1 · 33 9TH AVENUEOpen ↗
08/23/2026M01235961-P1 · 33 9TH AVENUEOpen ↗
Showing 3 of 6 on file for this type
▸Other Documents1
▸DOB NOWProof of Historic Building1
08/13/2026M01234640-I1 · 33 9TH AVENUEOpen ↗