| Owner | Filings | Most Recent |
|---|---|---|
| Deere Real Estate Services | 79 | 03/21/2026 |
| 55 Broadway Associates LLC Ear | 71 | 03/22/2026 |
| Premisys Real Estate Services | 12 | 03/21/2026 |
| 209-219 Sullivan Development | 10 | 03/21/2026 |
| 24 W 40 Associates | 7 | 03/21/2026 |
| Harbor Group | 3 | 03/22/2026 |
| E.S. Gordon Co | 3 | 03/21/2026 |
| Papoos | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/01/2014 | $157.0M | — | 55 BROADWAY, L.L.C. → EAR 55 BROADWAY, LLC | $507/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| WB Engineers & Consultants | 53 | 08/18/2026 |
| The Derosa Group, PC Architects | 15 | 07/28/2026 |
| Newtec Engineering | 1 | 04/02/2026 |
| CSA Group NY Architects & Engineers | 1 | 02/18/2026 |
| CSA Group | 1 | 02/18/2026 |
| Gregory Ralph, Architect | 1 | 02/09/2026 |
| Tecc Solutions | 1 | 09/29/2025 |
| Spencer | 3 | 12/16/2024 |
| SRA Architecture + Engineering | 1 | 06/13/2024 |
| Roger de Electric Co | 3 | 03/25/2024 |
| Concessi Engineering | 14 | 05/24/2023 |
| Loring Consulting Engineers | 4 | 11/10/2022 |
| CFS Engineering | 4 | 09/20/2022 |
| Anthony Johnson Architects | 2 | 09/13/2022 |
| DPM Architecture | 1 | 11/01/2021 |
| HC Engineering | 2 | 08/10/2021 |
| Smartdesign Architecture | 1 | 08/10/2021 |
| Jack Stone Engineers | 3 | 08/09/2021 |
| CD&A | 1 | 09/09/2020 |
| Office of James Ruderman | 1 | 07/13/2020 |
| Green Design | 2 | 10/23/2019 |
| Leon Skvirsky PE | 2 | 12/04/2018 |
| Baileys Engineering | 1 | 11/06/2018 |
| Salvator A. Caradonna JR | 1 | 02/28/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Metropolis Group | 128 | 03/21/2026 |
| Design 2147 | 1 | 03/21/2026 |
| Salamon Engineering | 6 | 03/21/2026 |
| SRA Architecture + Engineering | 6 | 03/21/2026 |
| Empire City Consultants | 4 | 03/21/2026 |
| Archetype Consultants | 12 | 03/21/2026 |
| Mbe Code Zoning | 8 | 03/21/2026 |
| JP Expedite | 4 | 03/21/2026 |
| AE Design Solution | 2 | 03/21/2026 |
| Atlantic Building Supply | 4 | 03/21/2026 |
| Building Brothers | 4 | 03/21/2026 |
| All in Permit Consultants | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Brick by Brick Builders | General Contractor | 28 | 08/06/2026 |
| Firequest | Fire Protection | 18 | 08/26/2026 |
| Gateway Builders Construction | General Contractor | 11 | 07/08/2026 |
| Kaj NY Construction | Scaffold | 7 | 07/08/2026 |
| Platinum Carpentry | General Contractor | 6 | 07/08/2026 |
| A Plus Plumbing | Plumbing | 5 | 07/08/2026 |
| KCM Plumbing & Heating Co | Plumbing | 4 | 07/08/2026 |
| N.Y. Preferred Development | General Contractor | 4 | 07/08/2026 |
| M&D Fire Sprinkler | Fire Protection | 4 | 08/26/2026 |
| Albros Electric | Electrical | 4 | 03/21/2026 |
| Polyhase Electrical Sol | Electrical | 3 | 03/22/2026 |
| SKH Mechanical | Fire Protection | 3 | 07/08/2026 |
| Starlite Plumbing | Plumbing | 3 | 08/05/2026 |
| Asco Sprinkler Co | Fire Protection | 3 | 07/08/2026 |
| The Manlyn Development Group | General Contractor | 3 | 07/08/2026 |
| Everest Scaffolding | Scaffold | 2 | 03/21/2026 |
| A&H Express Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Abr Plumbing & Heating Contracting | Plumbing | 2 | 07/08/2026 |
| State Electl Contng | Electrical | 2 | 03/21/2026 |
| Nucor Construction | General Contractor | 2 | 07/08/2026 |
| Signs Cad | Sign hanger | 2 | 07/08/2026 |
| Dependable Mechanical | Fire Protection | 2 | 10/14/2026 |
| Evergreen Builders & Con* | General Contractor | 2 | 07/08/2026 |
| Vallesigns & Awnings | Sign hanger | 2 | 07/08/2026 |
| P.S.I. Mechanical | Plumbing | 2 | 07/08/2026 |
| Wharton Smith Construction NY * | General Contractor | 2 | 04/09/2026 |
| William C. Gerakaris P&H | Plumbing | 1 | 07/08/2026 |
| Delta Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Dudley Jamal | Electrical | 1 | 03/21/2026 |
| Dudley & Associates Lic. Electric | Electrical | 1 | 03/21/2026 |
| Par Plumbing Co., Inc.o | Fire Protection | 1 | 03/21/2026 |
| Air Cooling & Heating | specialty_contractor | 1 | 04/09/2026 |
| Donnelly Mechanical | specialty_contractor | 1 | 04/09/2026 |
| Exclusive Restoration | specialty_contractor | 1 | 04/09/2026 |
| National Maintenance | Sign hanger | 1 | 07/08/2026 |
| Access Plumbing | Plumbing | 1 | 07/08/2026 |
| Allstate Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Ariana Contracting | Fire Protection | 1 | 06/02/2026 |
| A + Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Bent Mechanical | Plumbing | 1 | 07/08/2026 |
| Copper Plumbing | Plumbing | 1 | 07/08/2026 |
| E.M.P. Fire Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Expert Fire Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Metrotech Mechanical | Plumbing | 1 | 07/08/2026 |
| Tap Plumbing | Plumbing | 1 | 07/08/2026 |
| VMC Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agir Electrical Ltd D/B/A | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WB Engineering | 533 | 59 | 08/18/2026 |
| Obaid Mian | 849 | 1 | 04/02/2026 |
| CSA Group NY Architects A | 6928 | 2 | 02/18/2026 |
| MJ Engineering & Design | 5546 | 1 | 02/09/2026 |
| Tecc Designs and Solution | 7184 | 1 | 09/29/2025 |
| SE Inspections | 7486 | 4 | 12/16/2024 |
| Richmond Testing Lab | 263 | 3 | 03/25/2024 |
| Concessi Engineering | 540 | 13 | 05/24/2023 |
| MEP Inspections | 1102 | 5 | 11/10/2022 |
| Becker Engineering | 633 | 5 | 09/20/2022 |
| Special Testing & Consulting | 1688 | 3 | 08/10/2021 |
| Sag Engineering & Consulting | 608 | 1 | 07/13/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | Dependable Mechanical | 10/13/2026 |
| DOB NOW | General Construction | Permit Issued | Brick by Brick Builders | 08/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Brick by Brick Builders | 08/05/2026 |
| DOB NOW | Plumbing | Permit Issued | Starlite Plumbing | 08/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | M&D Fire Sprinkler | 08/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | M&D Fire Sprinkler | 07/22/2026 |
| DOB NOW | Plumbing | Permit Issued | Starlite Plumbing | 07/21/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Brick by Brick Builders | 07/21/2026 |
| DOB NOW | General Construction | Permit Issued | Brick by Brick Builders | 07/21/2026 |
| DOB NOW | Sprinklers | Permit Issued | M&D Fire Sprinkler | 07/21/2026 |
| DOB NOW | Sprinklers | Permit Issued | M&D Fire Sprinkler | 06/29/2026 |
| DOB NOW | Plumbing | Permit Issued | Starlite Plumbing | 06/29/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Brick by Brick Builders | 06/22/2026 |
| DOB NOW | Sprinklers | Permit Issued | Firequest | 06/22/2026 |
| DOB NOW | Plumbing | Permit Issued | A&H Express Plumbing & Heating | 06/17/2026 |
| DOB NOW | General Construction | Permit Issued | Brick by Brick Builders | 06/16/2026 |
| DOB NOW | Sprinklers | Permit Issued | Dependable Mechanical | 06/16/2026 |
| DOB NOW | General Construction | Permit Issued | Brick by Brick Builders | 06/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Brick by Brick Builders | 06/16/2026 |
| DOB NOW | General Construction | Permit Issued | Wharton Smith Construction NY * | 04/06/2026 |
| DOB NOW | Sprinklers | Permit Issued | Ariana Contracting | 04/03/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Donnelly Mechanical | 04/03/2026 |
| DOB NOW | Plumbing | Signed-off | Copper Mechanical | 04/02/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Wharton Smith Construction NY * | 04/01/2026 |
| DOB NOW | General Construction | Permit Issued | Brick by Brick Builders | 03/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Brick by Brick Builders | 03/05/2026 |
| DOB NOW | General Construction | Signed-off | Exclusive Restoration | 02/27/2026 |
| DOB NOW | Sprinklers | Signed-off | Firequest | 01/23/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Air Cooling & Heating | 12/10/2025 |
| DOB NOW | Sprinklers | Signed-off | Firequest | 03/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Brick by Brick Builders | 01/06/2025 |
| DOB NOW | General Construction | Signed-off | Brick by Brick Builders | 01/06/2025 |
| DOB NOW | Plumbing | Signed-off | A&H Express Plumbing & Heating | 12/09/2024 |
| DOB NOW | Sprinklers | Signed-off | Firequest | 07/30/2024 |
| DOB NOW | Sprinklers | Signed-off | SKH Mechanical | 04/26/2024 |
| DOB NOW | Plumbing | Permit Issued | Metrotech Mechanical | 04/25/2024 |
| DOB NOW | Plumbing | Signed-off | Bent Mechanical | 04/03/2024 |
| DOB NOW | Sprinklers | Signed-off | Firequest | 04/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Brick by Brick Builders | 04/03/2024 |
| DOB NOW | General Construction | Signed-off | Brick by Brick Builders | 03/11/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/02/2026 | Signed-off | Donnelly Mechanical | Air Conditioning Systems | Cooling Bosch EC072-4VTC-FFTBUC 90,000 BTU · Wshp ×1 |
| 03/31/2023 | — | — | Associated Ducts and Piping | Ducts & Piping Greenheck CSP-A200 100 CFM · Ductwork ×1 |
| 03/21/2023 | Permit Issued | Brick by Brick Builders | Associated Ducts and Piping | Ducts & Piping Titus AIR DUCTS 500 CFM · Ductwork ×1 |
| 08/12/2021 | Signed-off | Platinum Carpentry | Associated Ducts and Piping | Ducts & Piping N/A NA 260 CFM ×6 |
| 02/26/2020 | Permit Issued | Gateway Builders Construction | Heating Systems | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | M&D Fire Sprinkler | — |
| 07/31/2026 | Permit Issued | M&D Fire Sprinkler | — |
| 06/02/2026 | Permit Issued | A&H Express Plumbing & Heating | 65 heads |
| 03/30/2026 | Permit Issued | Ariana Contracting | — |
| 03/16/2023 | Permit Issued | Firequest | — |
| 08/23/2022 | Signed-off | Firequest | 62 heads |
| 08/17/2022 | Signed-off | Firequest | — |
| 09/15/2021 | Permit Issued | E.M.P. Fire Sprinkler | — |
| 08/12/2021 | Signed-off | Firequest | — |
| 02/26/2020 | Permit Issued | Firequest | — |
| 02/07/2020 | Permit Issued | Firequest | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | Starlite Plumbing | Water/Sanitary |
| 07/31/2026 | Permit Issued | Starlite Plumbing | Water/Sanitary |
| 07/29/2026 | Permit Issued | Starlite Plumbing | Water/Sanitary |
| 06/02/2026 | Permit Issued | Dependable Mechanical | Water/Sanitary |
| 03/30/2026 | Signed-off | Copper Plumbing | Water/Sanitary |
| 03/31/2023 | Permit Issued | P.S.I. Mechanical | Water/Sanitary |
| 08/23/2022 | Permit Issued | Metrotech Mechanical | Water/Sanitary |
| 08/17/2022 | Permit Issued | KCM Plumbing & Heating Co | Water/Sanitary |
| 09/15/2021 | — | — | Water/Sanitary |
| 07/01/2021 | — | — | Water/Sanitary |
| 05/25/2021 | — | — | Water/Sanitary |
| 04/13/2020 | Signed-off | Access Plumbing | Water/Sanitary |
| 02/26/2020 | Permit Issued | A Plus Plumbing | Water/Sanitary |
| 02/07/2020 | Permit Issued | A Plus Plumbing | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Permit Issued | Electric Empire | General Wiring |
| 07/07/2026 | Permit Issued | Electric Empire | General Wiring |
| 07/07/2026 | Permit Issued | Electric Empire | General Wiring |
| 07/05/2026 | Permit Issued | Electric Empire | General Wiring |
| 04/07/2026 | Complete | Ultra Electric | General Wiring |
| 02/02/2026 | Complete | Electric Empire | General Wiring |
| 02/23/2023 | Complete | Control Spec Electrical System | General Wiring |
| 11/17/2021 | Complete | Citywide Electrical Wiring | General Wiring |
| 09/20/2021 | Complete | Massaro Electric | General Wiring |
| 11/17/2020 | Permit Issued | Delta Electrical Contracting | General Wiring |
| 09/15/2020 | Complete | Eastern Electrical Construction | General Wiring |
| 08/21/2020 | Permit Issued | Monforte Electirc | General Wiring |
| 07/21/2020 | Complete | Agir Electrical Ltd D/B/A | General Wiring |
| 03/19/2020 | Complete | Eastern Electrical Construction | General Wiring |
| 02/14/2020 | Permit Issued | S&F Electrical Service | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/30/2026 | Permit Issued | Wharton Smith Construction NY * | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/07/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/01/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/11/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/07/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/29/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/29/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/29/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/25/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/10/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/10/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/18/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/12/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/05/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/07/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/27/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/27/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/17/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/16/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/05/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/30/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/21/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| 08/21/2026 | Post-installed Anchors | David Bonifacic | special |
| 08/07/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| 08/07/2026 | Post-installed Anchors | David Bonifacic | special |
| 07/31/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| 07/31/2026 | Post-installed Anchors | David Bonifacic | special |
| 07/28/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| 07/28/2026 | Post-installed Anchors | David Bonifacic | special |
| 07/15/2026 | Electrical motors and elevators | David Bonifacic | energy_progress |
| 07/15/2026 | Interior lighting power | David Bonifacic | energy_progress |
| 07/15/2026 | HVAC-R and service water piping design and insulation | David Bonifacic | energy_progress |
| 07/15/2026 | Lighting controls | David Bonifacic | energy_progress |
| 07/15/2026 | Maintenance information | David Bonifacic | energy_progress |
| 07/15/2026 | HVAC-R and service water heating system controls | David Bonifacic | energy_progress |
| 07/15/2026 | Energy Code Compliance Inspections | David Bonifacic | progress |
| 07/15/2026 | Duct leakage testing, insulation and design | David Bonifacic | energy_progress |
| 06/10/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| 06/10/2026 | Energy Code Compliance Inspections | David Bonifacic | progress |
| 06/10/2026 | Post-installed Anchors | David Bonifacic | special |
| 06/05/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| 06/05/2026 | Post-installed Anchors | David Bonifacic | special |
| 06/05/2026 | Final | David Bonifacic | progress |
| 06/05/2026 | Mechanical Systems | David Bonifacic | special |
| 06/05/2026 | Final | David Bonifacic | progress |
| 05/05/2026 | HVAC-R and service water heating system controls | David Bonifacic | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Argus | Office | Floor 6 | Project M01394634 |
| AFS Intercultural | Office | Floor 11 | Project M01392099 |
| Axon | Office | Floor 6 | Project M01393238 |
| One Exchange Plaza | Office | Floor 9 | Project M01324441 |
| Vogrin & Frimet | Office | Floor 15 | Project M01115795 |
| New York Civil Liberties Union (NYCLU) | Office | Floors 10, 15 | Project M00999893 Project M00826938 Project M00826975 Project M00829211 Project M00829246 |
| UPS | Office | Cellar | Project M00829366 |
| Park Literacy | Office | Floors 16, 21 | Project M00732985 Project M00733005 Project M00732973 Project M00732711 Project M00732719 |
| Heritage Outdoormedia | Office | Floor 21 | Project M00732701 |
| HairClub | Personal services | Floor 30 | Project M00588697 Project M00588703 Project M00588707 Project M00569589 |
| Moroccan Consulate | Government / Civic | Floors 18, 19 | Project M00494396 Project M00494417 Project M00494422 Project M00494374 |
| Mila | Office | Floor 27 | Project M00563660 Project M00537730 Project M00544585 |
| Just Salad | Restaurant / Food Service | Floors 1, 2 | Project M00534421 Project M00534424 Project M00564307 Project M00564430 Project M00564316 Project M00564401 Project M00530822 Project M00530841 |
| Assurant | Office | Floor 29 | Project M00491398 Project M00492914 Project M00492963 Project M00493151 |
| YWCA Retirement Fund | Office | Floor 17 | Project M00353035 Project M00353284 Project M00353421 Project M00353486 |
| Cohen Seglias | Office | Floor 9 | Project M00322801 Project M00322808 |
| Bond Collective | Office | Floors 6, 8 | Project M00304371 Project M00306041 Project M00306056 Project M00306072 Project M00306079 Project M00306087 |
| Starbucks | Restaurant / Food Service | Floor 1 | Project M00096745 Project M00021125 |
| The Mezzanine | Retail | Floor 1 | Project M00076437 |