| Owner | Filings | Most Recent |
|---|---|---|
| NYC Department of Design and Construction | 97 | 07/19/2026 |
| Department of Gen. Services | 20 | 03/21/2026 |
| Department of Citywide Adm Services | 14 | 03/21/2026 |
| City of New York Nycddc | 13 | 10/07/2026 |
| NYC Department of Housing Preservation and Development | 8 | 03/22/2026 |
| Boileroom Rentals | 5 | 03/22/2026 |
| NYC Department of Design & Cons | 3 | 03/21/2026 |
| Department of Correction | 1 | 03/21/2026 |
| D.P. Consulting | 1 | 03/21/2026 |
| DOC | 1 | 03/21/2026 |
| DGS | 1 | 03/21/2026 |
| Nycdgs | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Jordan Parnass Digital Architect | 3 | 08/12/2026 |
| Syska Hennessy Group | 1 | 05/28/2026 |
| HOK | 2 | 05/07/2026 |
| Liro Architects + Planners | 9 | 01/21/2026 |
| Superstructures Engineering + Architects | 3 | 01/07/2026 |
| Dewberry Engineers | 5 | 12/11/2025 |
| JFK Associates | 4 | 09/30/2025 |
| Ensign Engineering | 15 | 02/18/2025 |
| New York & Company | 1 | 12/05/2023 |
| Ysrael A. Seinuk | 5 | 11/28/2023 |
| Joel Phagoo P.E | 2 | 08/09/2023 |
| Wavic Engineering | 1 | 03/22/2022 |
| New Concept Engineering | 1 | 06/24/2021 |
| Gregory L Singer, PE | 2 | 05/05/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| Municipal Building Consultants | 5 | 03/21/2026 |
| KM Associates of New York | 28 | 03/21/2026 |
| Metropolis Group | 10 | 03/21/2026 |
| Superstructures Engineering + Architects | 3 | 03/21/2026 |
| New York & Company | 2 | 03/21/2026 |
| Welkin Enterprises | 2 | 03/21/2026 |
| Noel Building Consulting | 2 | 03/21/2026 |
| Municipal Expediting | 2 | 03/21/2026 |
| Commercial Capital USA | 2 | 03/21/2026 |
| Jenny Flores Expediting | 1 | 03/21/2026 |
| K & M Associates | 28 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Gramercy Group | General Contractor | 14 | 07/08/2026 |
| Welkin Fire Protection | Fire Protection | 12 | 07/08/2026 |
| Amr Mechanical | Fire Protection | 9 | 07/08/2026 |
| Welkin Mechanical | specialty_contractor | 9 | 07/08/2026 |
| J & N Construction Group | Scaffold | 8 | 07/08/2026 |
| Welkin Enterprises | Plumbing | 5 | 07/08/2026 |
| Jobco | General Contractor | 4 | 07/08/2026 |
| Amr Mechanical | Plumbing | 4 | 03/22/2026 |
| Amr Mechanical | Plumbing | 3 | 07/08/2026 |
| Maccarone Plumbing | Plumbing | 2 | 10/07/2026 |
| Tutor Perini/ O&G A Joint | General Contractor | 2 | 07/19/2026 |
| Stalco Construction | General Contractor | 2 | 04/09/2026 |
| ACS System Associates | General Contractor | 2 | 07/08/2026 |
| Ogc Electrical Contractor | Electrical | 2 | 03/21/2026 |
| Nee Electrical | Electrical | 2 | 03/21/2026 |
| J & N Construction Group | General Contractor | 1 | 07/08/2026 |
| Atlas Electric Contractors | Electrical | 1 | 03/21/2026 |
| J. M. Electrical | Electrical | 1 | 03/21/2026 |
| Medina John | Electrical | 1 | 03/21/2026 |
| Moller & Moller Inc.d/B/A | Electrical | 1 | 03/21/2026 |
| District Attorneys Office | Electrical | 1 | 03/21/2026 |
| P & M Elect'l Contracting | Electrical | 1 | 03/22/2026 |
| R & L Systems | Electrical | 1 | 03/21/2026 |
| Richmond Electric | Electrical | 1 | 03/21/2026 |
| Paulka Plumbing & Heat | specialty_contractor | 1 | 07/08/2026 |
| Paulka Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CSA Group NY Architects A | 6928 | 5 | 08/12/2026 |
| Socotec Engineering | 4983 | 2 | 05/28/2026 |
| Bureau Veritas Na | 6902 | 4 | 12/11/2025 |
| Superstructures Engineering | 374 | 2 | 08/01/2025 |
| Tectonic Engineering Cons | 106 | 22 | 06/26/2025 |
| New York Engineering Associates | 851 | 1 | 12/05/2023 |
| New Concept Engineering | 3906 | 1 | 06/24/2021 |
| Gregory L. Singer, PE, PL | 2455 | 1 | 05/05/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | Maccarone Plumbing | 10/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Tutor Perini/ O&G A Joint | 07/17/2026 |
| DOB NOW | Structural | Permit Issued | Tutor Perini/ O&G A Joint | 07/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ACS System Associates | 04/23/2026 |
| DOB NOW | General Construction | Permit Issued | Stalco Construction | 01/22/2026 |
| DOB NOW | Standpipe | Signed-off | Amr Mechanical | 01/08/2026 |
| DOB NOW | Sprinklers | Signed-off | Amr Mechanical | 01/08/2026 |
| DOB NOW | Plumbing | Permit Issued | Maccarone Plumbing | 10/01/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | ACS System Associates | 09/22/2025 |
| DOB NOW | General Construction | Permit Issued | Stalco Construction | 09/15/2025 |
| DOB NOW | Sprinklers | Signed-off | Amr Mechanical | 05/02/2025 |
| DOB NOW | Sprinklers | Signed-off | Amr Mechanical | 01/14/2025 |
| DOB NOW | Plumbing | Signed-off | Amr Mechanical | 01/14/2025 |
| DOB NOW | Standpipe | Signed-off | Amr Mechanical | 01/13/2025 |
| DOB NOW | Sprinklers | Signed-off | Welkin Fire Protection | 11/06/2024 |
| DOB NOW | Standpipe | Signed-off | Welkin Fire Protection | 10/22/2024 |
| DOB NOW | Construction Fence | Permit Issued | J & N Construction Group | 08/09/2024 |
| DOB NOW | Structural | Signed-off | Jobco | 08/07/2024 |
| DOB NOW | General Construction | Signed-off | Gramercy Group | 07/12/2024 |
| DOB NOW | Plumbing | Signed-off | Welkin Enterprises | 07/01/2024 |
| DOB NOW | Sprinklers | Permit Issued | Welkin Fire Protection | 05/28/2024 |
| DOB NOW | Standpipe | Permit Issued | Welkin Fire Protection | 05/28/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & N Construction Group | 04/23/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Welkin Mechanical | 03/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Welkin Mechanical | 03/07/2024 |
| DOB NOW | Plumbing | Signed-off | Amr Mechanical | 03/04/2024 |
| DOB NOW | Sprinklers | Signed-off | Amr Mechanical | 02/28/2024 |
| DOB NOW | Standpipe | Signed-off | Amr Mechanical | 02/28/2024 |
| DOB NOW | Structural | Signed-off | Jobco | 01/30/2024 |
| DOB NOW | Boiler Equipment | Signed-off | Jack Piccini | 12/08/2023 |
| DOB NOW | Structural | Signed-off | Jobco | 12/06/2023 |
| DOB NOW | Standpipe | Permit Issued | Welkin Fire Protection | 09/27/2023 |
| DOB NOW | Sprinklers | Signed-off | Welkin Fire Protection | 09/27/2023 |
| DOB NOW | General Construction | Permit Issued | J & N Construction Group | 09/18/2023 |
| DOB NOW | Plumbing | Signed-off | Amr Mechanical | 08/30/2023 |
| DOB NOW | Standpipe | Signed-off | Amr Mechanical | 08/30/2023 |
| DOB NOW | Sprinklers | Signed-off | Amr Mechanical | 08/30/2023 |
| DOB NOW | Construction Fence | Permit Issued | J & N Construction Group | 08/09/2023 |
| DOB NOW | Plumbing | Signed-off | Welkin Enterprises | 07/14/2023 |
| DOB NOW | Plumbing | Signed-off | Welkin Enterprises | 07/14/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/28/2026 | Permit Issued | Tutor Perini/ O&G A Joint | Heating Systems | Heating Trane FFDB030 15,354 BTU · Unit Heater ×1 |
| 09/30/2025 | Permit Issued | ACS System Associates | Ventilation Systems | Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2025 | Signed-off | Amr Mechanical | 4 heads, 8 outlets |
| 11/27/2023 | Permit Issued | Welkin Fire Protection | 4 heads, 4 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2025 | — | — | — |
| 09/30/2025 | Permit Issued | Maccarone Plumbing | Water/Sanitary |
| 06/08/2023 | Signed-off | Amr Mechanical | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2025 | Permit Issued | Ogc Electrical Contractor | General Wiring |
| 10/07/2025 | Permit Issued | Ogc Electrical Contractor | — |
| 01/24/2025 | Complete | Smalls Electrical Construction | General Wiring |
| 01/08/2024 | Permit Issued | P & M Elect'l Contracting | — |
| 02/01/2023 | Permit Issued | Amin Electrical | — |
| 06/25/2019 | Permit Issued | Ark Systems Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | Tutor Perini/ O&G A Joint | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/09/2023 | Permit Issued | J & N Construction Group | Fence |
| 02/03/2023 | Permit Issued | J & N Construction Group | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/18/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/30/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/30/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/27/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/13/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/13/2026 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 01/09/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/21/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/21/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/21/2025 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 07/12/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/26/2024 | Certified StandPipe-SD-Piping-Underground | Certified | View ↗ |
| 11/08/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 11/04/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/11/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/11/2024 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 06/10/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 06/07/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/31/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/31/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Water Test | Certified | View ↗ |
| 01/11/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 01/02/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/02/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 12/27/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2026 | Fire-Resistant Penetrations and Joints | Luis Rivera | special |
| 08/06/2026 | Final | Luis Rivera | progress |
| 06/25/2026 | Fire-Resistant Penetrations and Joints | Luis Rivera | special |
| 06/25/2026 | Final | Luis Rivera | progress |
| 05/06/2026 | Post-installed Anchors | MARISA HARTE | special |
| 05/06/2026 | Structural Steel - High Strength Bolting | MARISA HARTE | special |
| 05/06/2026 | Mechanical Systems | MARISA HARTE | special |
| 05/06/2026 | Final | MARISA HARTE | progress |
| 05/06/2026 | Fire-Resistant Penetrations and Joints | MARISA HARTE | special |
| 05/06/2026 | Structural Steel - Details | MARISA HARTE | special |
| 05/06/2026 | Structural Steel - Welding | MARISA HARTE | special |
| 05/06/2026 | Final | Jieming Wang | progress |
| 05/06/2026 | Energy Code Compliance Inspections | MARISA HARTE | progress |
| 01/15/2026 | Fire-Resistance Rated Construction | — | progress |
| 01/15/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 12/30/2025 | Final | — | progress |
| 12/21/2025 | Standpipe Systems | IBRAHIM MOURAD | special |
| 12/21/2025 | Sprinkler Systems | IBRAHIM MOURAD | special |
| 12/15/2025 | Insulation placement and R values | — | energy_progress |
| 12/15/2025 | Masonry | — | special |
| 12/15/2025 | Final | Paul Millman | progress |
| 12/15/2025 | Wall Panels, Curtain Walls, and Veneers | — | special |
| 11/21/2025 | Standpipe Systems | IBRAHIM MOURAD | special |
| 11/21/2025 | Sprinkler Systems | IBRAHIM MOURAD | special |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | — | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| NYC Borough-Based Jalls Program - Manhattan Facility | Government / Civic | Floor 1 | Project M01340771 |
| NYC DCAS Citywide Administrative Services | Government / Civic | Floor 19 | Project M01334242 |
| New York Department of Correction | Government / Civic | Cellar, Floors 1, 3, 12, Roof | Project M01114217 Project M01006848 Project M00759162 Project M00712589 Project M00747037 Project M00747072 Project M00736987 Project M00737010 Project M00712629 Project M00712634 Project M00737075 Project M00698550 |
| Manhattan Criminal Court | Government / Civic | Cellar, Penthouse | Project M00870578 Project M00870574 Project M00460228 |