| Owner | Filings | Most Recent |
|---|---|---|
| AKAM ASSOCIATES | 9 | 09/13/2026 |
| DCGC CONTRACTING | 12 | 07/08/2026 |
| FINEST FEDERAL CREDIT UNION | 3 | 07/08/2026 |
| SHAH GROUP ENTERPRISES | 4 | 07/08/2026 |
| CHATHAM GREENE, INC | 124 | 03/22/2026 |
| PC DESIGN-BUILD ENGINEERI | 1 | 03/22/2026 |
| OWNER OF 7 MADISON STREET | 1 | 03/22/2026 |
| SHAH BUILDERS | 4 | 03/21/2026 |
| HALSTEAD MANAGEMENT COMPANY | 8 | 03/21/2026 |
| CHATHAM GREEN MANAGEMENT OFFICE | 13 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| REFORM ARCHITECTURE PLLC | 2 | 08/05/2026 |
| MW PROFESSIONAL ENGINEERING, P.C. | 12 | 07/28/2026 |
| FARHAD BASSIRI-TEHRANI | 2 | 07/21/2026 |
| ZACHARY SAPINSLEY LEWIS, R.A. | 2 | 04/22/2026 |
| SCOTT PROFETA | 1 | 10/24/2025 |
| EAST + WEST ARCHITECTURE PC | 1 | 03/03/2025 |
| YAO W GUO ARCHITECT, PC | 4 | 02/24/2025 |
| BRYAN JUG | 1 | 01/02/2025 |
| ROGER DE ELECTRIC CO. | 2 | 11/01/2024 |
| MSM ENGINEERING SERVICES, PLLC | 4 | 10/17/2024 |
| SU ARCHITECT, P.C. | 1 | 02/06/2024 |
| LONGTIN SOLUTIONS LLC | 4 | 11/01/2023 |
| JAROS BAUM & BOLLES | 2 | 05/15/2023 |
| THE RAJIV, INC. | 4 | 01/31/2023 |
| ENTHINK ENGINEERS LLC | 1 | 09/15/2022 |
| D&E BUILD EVERGREEN INC. | 2 | 01/14/2022 |
| EPOC DESIGN + ARCHITECTURE | 1 | 09/24/2021 |
| STREET CONSULTING ENGINEERING, P. . | 3 | 09/09/2021 |
| ALLEN SHINFELD, P.E. PLLC | 1 | 09/08/2021 |
| ROBERT ETTINGER, P.E, P.C. | 1 | 12/08/2020 |
| FLUSHING ENGINEERING SERVICE PC | 1 | 06/03/2020 |
| LIGHT HOUSE | 1 | 04/01/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| EAST+WEST ARCHITECTURE P C | 2 | 03/21/2026 |
| JD DESIGN ASSOCIATES INC | 14 | 03/21/2026 |
| MW PROFESSIONAL ENGINEERING P C | 4 | 03/21/2026 |
| BASIC GROUPS | 4 | 03/21/2026 |
| KTC DESIGN GROUP | 4 | 03/21/2026 |
| HAOTIAN ASSOCIATES | 2 | 03/21/2026 |
| S M EXPEDITING | 2 | 03/21/2026 |
| RICHARD LEWIS ARCHITECT | 1 | 03/21/2026 |
| PROJECT ENTRY | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DCGC CONTRACTING INC | General Contractor | 9 | 07/08/2026 |
| KALE CONSTRUCTION INC | General Contractor | 6 | 08/16/2026 |
| DAVID CONSTRUCTING NY, IN | General Contractor | 6 | 03/21/2026 |
| JD ARCH LLC | General Contractor | 5 | 07/08/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 5 | 07/08/2026 |
| INTER RENOVATION INC | General Contractor | 4 | 07/08/2026 |
| KLE CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| ABOVE REMODELING CORP | General Contractor | 3 | 03/21/2026 |
| A ELECTRICAL MAIN SVC INC | Electrical | 2 | 03/22/2026 |
| HIGH QUALITY CONSTRUCTION | General Contractor | 2 | 03/21/2026 |
| H INTERIOR DESIGN CONSTRUCTION | General Contractor | 2 | 03/21/2026 |
| AMC PLBG, HTG & CLNG, INC | Plumbing | 2 | 07/08/2026 |
| CROSSFIELD PLBG.&HTG | Plumbing | 2 | 07/08/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 2 | 07/08/2026 |
| JP & SON ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| GRZEGORZ WIDELSKI | Electrical | 1 | 03/21/2026 |
| GOTHAM WIRING LICENSED | Electrical | 1 | 03/22/2026 |
| ERIC & NG ELEC'L, INC. | Electrical | 1 | 03/22/2026 |
| ALLAN TANG | Electrical | 1 | 03/21/2026 |
| SAFETY PRO CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| SHAH GROUP ENTERPRISES IN | General Contractor | 1 | 07/08/2026 |
| SPLEN CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| STELLAR INDUSTRIES INC | General Contractor | 1 | 07/08/2026 |
| ALL DAY PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| VILLAGE P & H NY INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| REFORM ARCHITECTURE PLLC | 9444 | 2 | 08/05/2026 |
| MW PROFESSIONAL ENGINEERI | 570 | 7 | 07/28/2026 |
| EAST+WEST ARCHITECTURE, P | 3269 | 1 | 03/03/2025 |
| SALAMON ENGINEERING PLLC | 1264 | 2 | 11/01/2024 |
| MSM ENGINEERING SERVICES, | 8449 | 2 | 07/05/2024 |
| SU ARCHITECT PC | 6857 | 1 | 02/06/2024 |
| LONGTIN SOLUTIONS LLC | 8320 | 4 | 11/01/2023 |
| FRANCISCO D. PEREZ PE | 3306 | 2 | 01/31/2023 |
| BUILDTECH ENGINEERING | 6369 | 1 | 01/14/2022 |
| ALLEN SHINFELD, P.E. PLLC | 1305 | 1 | 09/08/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | KALE CONSTRUCTION INC | 08/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | KALE CONSTRUCTION INC | 08/12/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | CENTRAL CONSTRUCTION MGMT | 05/28/2026 |
| DOB NOW | General Construction | Permit Issued | KALE CONSTRUCTION INC | 03/31/2026 |
| DOB NOW | General Construction | Permit Issued | GOLIATH WOODWORKING | 03/13/2026 |
| DOB NOW | General Construction | Signed-off | KALE CONSTRUCTION INC | 12/20/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | CERINA GENERAL CONTR. INC | 11/13/2025 |
| DOB NOW | General Construction | Signed-off | SAFETY PRO CONSTRUCTION | 04/04/2025 |
| DOB NOW | General Construction | Signed-off | DCGC CONTRACTING INC | 04/01/2025 |
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 03/18/2025 |
| DOB NOW | General Construction | Signed-off | KALE CONSTRUCTION INC | 03/11/2025 |
| DOB NOW | General Construction | Signed-off | KALE CONSTRUCTION INC | 01/06/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 09/11/2024 |
| DOB NOW | General Construction | Signed-off | DCGC CONTRACTING INC | 09/09/2024 |
| DOB NOW | Plumbing | Signed-off | M. SPINELLI PLB & HTG INC | 09/03/2024 |
| DOB NOW | General Construction | Signed-off | DCGC CONTRACTING INC | 06/24/2024 |
| DOB NOW | General Construction | Signed-off | KLE CONSTRUCTION INC | 03/01/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | INTER RENOVATION INC | 01/10/2024 |
| DOB NOW | General Construction | Signed-off | DCGC CONTRACTING INC | 12/19/2023 |
| DOB NOW | General Construction | Signed-off | INTER RENOVATION INC | 11/17/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 09/14/2023 |
| DOB NOW | Plumbing | Signed-off | CROSSFIELD PLBG.&HTG | 08/04/2023 |
| DOB NOW | General Construction | Signed-off | H INTERIOR DESIGN CONSTRU | 07/28/2023 |
| DOB NOW | General Construction | Signed-off | DCGC CONTRACTING INC | 05/24/2023 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 05/02/2023 |
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 12/27/2022 |
| DOB NOW | General Construction | Signed-off | INTER RENOVATION INC | 11/10/2022 |
| DOB NOW | Plumbing | Signed-off | ALL DAY PLUMBING & HEATIN | 10/07/2022 |
| DOB NOW | General Construction | Signed-off | ABOVE REMODELING CORP | 10/03/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 09/16/2022 |
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 09/08/2022 |
| DOB NOW | General Construction | Signed-off | JD ARCH LLC | 08/16/2022 |
| DOB NOW | General Construction | Signed-off | SPLEN CONSTRUCTION INC | 06/14/2022 |
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 03/10/2022 |
| DOB NOW | General Construction | Signed-off | JD ARCH LLC | 01/05/2022 |
| DOB NOW | General Construction | Signed-off | DAVID CONSTRUCTING NY, IN | 10/27/2021 |
| DOB NOW | General Construction | Signed-off | ALCO STORE DEVELOPMENT CO | 10/13/2021 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 09/17/2021 |
| DOB NOW | Plumbing | Signed-off | CROSSFIELD PLBG.&HTG | 08/10/2021 |
| DOB NOW | General Construction | Signed-off | JD ARCH LLC | 08/05/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/28/2026 | Permit Issued | KALE CONSTRUCTION INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MCZ-3D24NL 22,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | — | — | Gas, Water/Sanitary |
| 04/22/2026 | — | — | Gas, Water/Sanitary |
| 06/26/2023 | Signed-off | CROSSFIELD PLBG.&HTG | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | Permit Issued | ABILENE ELECTRIC INC | — |
| 08/17/2026 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| 05/04/2026 | Complete | KJK ELECTRIC INC | General Wiring |
| 04/28/2026 | Permit Issued | 2AK LIGHT ELECTRIC CORP | General Wiring |
| 04/14/2026 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| 03/16/2026 | Permit Issued | BLUE SEAGULL ELECTRICAL | General Wiring |
| 05/05/2025 | Complete | AMP POWER ELECTRIC SERV | — |
| 02/07/2025 | Complete | ERIC & NG ELEC'L, INC. | — |
| 11/01/2024 | Complete | Y.S ELECTRIC | General Wiring |
| 05/08/2024 | Permit Issued | OMD ELECTRICAL CORP | 1 meters, 1 new_meters |
| 11/30/2023 | Complete | JP & SON ELECTRIC CORP | General Wiring |
| 11/30/2023 | Complete | JP & SON ELECTRIC CORP | — |
| 10/10/2023 | Complete | NELSON & TOM MAINT INC DB | — |
| 08/10/2023 | Complete | NELSON & TOM MAINT INC DB | — |
| 04/12/2023 | Complete | GOTHAM WIRING LICENSED | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2018 | Permit Issued | SHAH GROUP ENTERPRISES IN | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2026 | Permit Issued | CENTRAL CONSTRUCTION MGMT | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/13/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/12/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/29/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/30/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/05/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/05/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/22/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/02/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/26/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/13/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/12/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/12/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/19/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/14/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/14/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/19/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/28/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/22/2021 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/02/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/02/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/27/2026 | Fire-Resistant Penetrations and Joints | MING WAI WONG | special |
| 07/27/2026 | Final | MING WAI WONG | progress |
| 07/27/2026 | Mechanical Systems | MING WAI WONG | special |
| 07/27/2026 | Tenant Protection Plan Compliance | MING WAI WONG | special |
| 07/27/2026 | HVAC-R and service water heating equipment | MING WAI WONG | energy_progress |
| 07/27/2026 | Energy Code Compliance Inspections | MING WAI WONG | progress |
| 07/21/2026 | Tenant Protection Plan Compliance | — | special |
| 07/21/2026 | Tenant Protection Plan Compliance | — | special |
| 04/30/2026 | Fire-Resistant Penetrations and Joints | Dionisio Cortes Ortega | special |
| 12/16/2025 | Fire-Resistance Rated Construction | MING WAI WONG | progress |
| 12/16/2025 | Final | MING WAI WONG | progress |
| 11/05/2025 | Final | Zachary Lewis | progress |
| 02/28/2025 | Tenant Protection Plan Compliance | BARBARA HESS | special |
| 02/21/2025 | Lighting in dwelling units | Yao Guo | energy_progress |
| 02/21/2025 | Final | Yao Guo | progress |
| 02/21/2025 | Energy Code Compliance Inspections | Yao Guo | progress |
| 02/13/2025 | Final | BARBARA HESS | progress |
| 12/04/2024 | Final | Bryan Jug | progress |
| 11/04/2024 | Masonry | David Salamon | special |
| 11/04/2024 | Final | David Salamon | progress |
| 10/29/2024 | Tenant Protection Plan Compliance | MOHAMED MAHMOUD | special |
| 10/17/2024 | Final | MOHAMED MAHMOUD | progress |
| 10/17/2024 | Tenant Protection Plan Compliance | — | special |
| 10/17/2024 | Final | MOHAMED MAHMOUD | progress |
| 10/17/2024 | Tenant Protection Plan Compliance | MOHAMED MAHMOUD | special |