| Owner | Filings | Most Recent |
|---|---|---|
| Northwell Health Lenox Hill Hospita | 78 | 10/13/2026 |
| North Shore Lij Health System | 10 | 03/21/2026 |
| Lenox Hilll Hospital | 9 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Always Fast Services | 1 | 09/25/2026 |
| Lizardos Engineering | 13 | 07/28/2026 |
| Tohfaz Uddin PE | 1 | 06/19/2026 |
| Merritt Engineering Consultants | 1 | 06/08/2026 |
| Pamela A. Smith | 2 | 11/12/2025 |
| Gilsanz Murray Steficek | 2 | 11/05/2025 |
| Mascioni & Behrmann, Architecture | 1 | 08/01/2025 |
| Icor Associates | 2 | 07/30/2025 |
| The McGuire Group Architects | 2 | 07/29/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Upright Expediters | 40 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| The Whiting-Turner Contracting | General Contractor | 9 | 07/08/2026 |
| Sirina Fire Protection | Fire Protection | 6 | 07/08/2026 |
| Boilermatic Welding Industries | specialty_contractor | 5 | 07/08/2026 |
| Central Consulting & Cont | General Contractor | 5 | 08/08/2026 |
| Hatzel and Buehler | Electrical | 2 | 03/22/2026 |
| Eagle Scaffolding Services | Scaffold | 1 | 07/10/2026 |
| Alliance Plumbing | Plumbing | 1 | 06/28/2026 |
| Archer Consultants Group | Fire Protection | 1 | 07/08/2026 |
| Capital Contracting P&H | Plumbing | 1 | 06/27/2026 |
| Diane Electric | Electrical | 1 | 03/22/2026 |
| Vanguard Fire Supp | Fire Protection | 1 | 07/08/2026 |
| Michael Mazzeo Electric | Electrical | 1 | 03/21/2026 |
| B & A Restoration Contracting | specialty_contractor | 1 | 06/27/2026 |
| Consigli Construction Co | General Contractor | 1 | 07/30/2026 |
| Andamio Scaffolding | Scaffold | 1 | 09/26/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CC@A Engineering | 1854 | 20 | 07/28/2026 |
| Leo Y Lee Associates | 2481 | 1 | 07/02/2026 |
| Merritt Engineering Consulting | 460 | 1 | 06/08/2026 |
| Gilsanz Murray Steficek | 240 | 2 | 11/05/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | Andamio Scaffolding | 09/25/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | B&A Restoration Contracting | 09/04/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Central Consulting & Cont | 08/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Consigli Construction Co | 07/29/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Eagle Scaffolding Services | 07/09/2026 |
| DOB NOW | General Construction | Permit Issued | B & A Restoration Contracting | 06/25/2026 |
| DOB NOW | General Construction | Signed-off | The Whiting-Turner Contracting | 05/06/2026 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 05/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 05/04/2026 |
| DOB NOW | Standpipe | Permit Issued | Sirina Fire Protection | 05/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 05/01/2026 |
| DOB NOW | Sprinklers | Signed-off | Archer Consultants Group | 04/02/2026 |
| DOB NOW | General Construction | Signed-off | The Whiting-Turner Contracting | 01/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Boilermatic Welding Industries | 11/03/2025 |
| DOB NOW | Boiler Equipment | Signed-off | Boilermatic Weldng Inds I | 11/03/2025 |
| DOB NOW | Structural | Permit Issued | The Whiting-Turner Contracting | 10/02/2025 |
| DOB NOW | Sprinklers | Signed-off | Vanguard Fire Supp | 10/01/2025 |
| DOB NOW | Plumbing | Signed-off | Capital Contracting P&H | 09/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | The Whiting-Turner Contracting | 09/09/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Central Consulting & Cont | 09/05/2025 |
| DOB NOW | General Construction | Signed-off | Central Consulting & Cont | 08/14/2025 |
| DOB NOW | Boiler Equipment | Signed-off | Boilermatic Weldng Inds I | 07/22/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Boilermatic Welding Industries | 07/22/2025 |
| DOB NOW | General Construction | Signed-off | The Whiting-Turner Contracting | 12/19/2024 |
| DOB NOW | Boiler Equipment | Signed-off | Boilermatic Weldng Inds I | 11/27/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | Boilermatic Welding Industries | 11/13/2024 |
| DOB NOW | Structural | Permit Issued | The Whiting-Turner Contracting | 10/28/2024 |
| DOB NOW | Mechanical Systems | Signed-off | The Whiting-Turner Contracting | 10/08/2024 |
| DOB NOW | Plumbing | Signed-off | Cardoza Plumbing Wmbe | 11/30/2023 |
| DOB NOW | Standpipe | Signed-off | Sirina Fire Protection | 10/23/2023 |
| DOB NOW | Sprinklers | Signed-off | Sirina Fire Protection | 10/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Central Consulting & Cont | 07/18/2023 |
| DOB NOW | General Construction | Signed-off | Central Consulting & Cont | 07/10/2023 |
| BIS | SP | ISSUED | Aggressive Fire Protection | 06/11/2019 |
| BIS | SP | ISSUED | NYC Fire Sprinkler | 03/22/2019 |
| BIS | OT | RE-ISSUED | L.F. Driscoll Company | 03/12/2019 |
| BIS | PL | ISSUED | J.M. Botto | 03/06/2019 |
| BIS | PL | ISSUED | J.M. Botto | 03/06/2019 |
| BIS | SP | ISSUED | NYC Fire Sprinkler | 02/08/2019 |
| BIS | OT | ISSUED | Axis Construction | 01/31/2019 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/23/2026 | Permit Issued | Consigli Construction Co | Air Conditioning Systems, Heating Systems | Cooling Baikal Custom 20,500 CFM · Ahu ×2 |
| 09/23/2025 | Signed-off | Central Consulting & Cont | Air Conditioning Systems, Ventilation Systems | |
| 10/15/2024 | Permit Issued | Boilermatic Welding Industries | Air Conditioning Systems | Cooling Trane AC-0-1: TPKA0A0361KA70A; ACCU-3-1: TRUYA0361KA70NA 36,000 BTU · Split System ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2026 | Signed-off | Archer Consultants Group | 18 heads |
| 07/30/2025 | Permit Issued | Sirina Fire Protection | 89 heads, 2 outlets |
| 06/10/2025 | Permit Issued | Sirina Fire Protection | 5 heads, 4 outlets |
| 10/16/2024 | Permit Issued | Sirina Fire Protection | 10 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2026 | Signed-off | Capital Contracting P&H | Water/Sanitary |
| 07/30/2025 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2026 | Permit Issued | Borowide Elect'l Contractors | — |
| 06/19/2026 | Permit Issued | Corporate Electric Group | — |
| 02/25/2026 | Permit Issued | Hatzel and Buehler | General Wiring |
| 06/14/2024 | Permit Issued | Hatzel and Buehler | General Wiring |
| 05/23/2019 | Complete | Diane Electric | General Wiring, Lighting |
| 03/12/2019 | Permit Issued | Hatzel and Buehler | 1 meters |
| 03/06/2019 | Permit Issued | Hatzel and Buehler | General Wiring |
| 02/06/2019 | Permit Issued | Hatzel and Buehler | General Wiring |
| 07/05/2018 | Complete | B.P. Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/05/2025 | Permit Issued | The Whiting-Turner Contracting | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2026 | Permit Issued | Andamio Scaffolding | Sidewalk Shed |
| 06/19/2026 | Permit Issued | Eagle Scaffolding Services | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Permit Issued | B&A Restoration Contracting | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/09/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/03/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/02/2025 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 10/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/07/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/24/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/24/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 07/17/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/17/2026 | Fuel-Oil Storage and Fuel-Oil Piping Systems | CHAROULIS CHARALAMBOUS | special |
| 07/28/2026 | Fuel-Oil Storage and Fuel-Oil Piping Systems | CHAROULIS CHARALAMBOUS | special |
| 07/21/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Leo Lee | special |
| 07/21/2026 | Post-installed Anchors | Leo Lee | special |
| 05/14/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 05/14/2026 | Duct leakage testing, insulation and design | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/04/2026 | Mechanical Systems | CHAROULIS CHARALAMBOUS | special |
| 05/04/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 02/25/2026 | Fuel-Oil Storage and Fuel-Oil Piping Systems | CHAROULIS CHARALAMBOUS | special |
| 01/17/2026 | Sprinkler Systems | CHAROULIS CHARALAMBOUS | special |
| 01/17/2026 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| 12/17/2025 | Sprinkler Systems | CHAROULIS CHARALAMBOUS | special |
| 12/17/2025 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| 11/06/2025 | Structural Steel - Details | Philip Murray | special |
| 11/06/2025 | Sprayed fire-resistant materials | Philip Murray | special |
| 11/06/2025 | Concrete - Cast-In-Place | Philip Murray | special |
| 11/06/2025 | Post-installed Anchors | Philip Murray | special |
| 11/06/2025 | Designated Seismic System | — | special |
| 11/06/2025 | Structural Steel - Welding | Philip Murray | special |
| 11/06/2025 | Structural Steel - High Strength Bolting | Philip Murray | special |
| 11/06/2025 | Final | CHAROULIS CHARALAMBOUS | progress |
| 11/03/2025 | Designated Seismic System | — | special |
| 11/03/2025 | Concrete - Cast-In-Place | Philip Murray | special |
| 11/03/2025 | Post-installed Anchors | Philip Murray | special |
| 11/03/2025 | Sprayed fire-resistant materials | Philip Murray | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Lenox Hill/Meeth | Medical / Healthcare | Floors 1–3, 7, 8, Roof | Project M01428972 Project M01416490 Project M01396745 Project M01402377 Project M01209926 Project M01230963 Project M01210868 Project M01106562 Project M00872302 |
| Northwell Health | Medical / Healthcare | Cellar, Floors 1–5, 8, Roof | Project M01416504 Project M01103377 Project M01105557 Project M01102545 Project M01102596 Project M01106572 Project M00908219 Project M00873518 Project M00872327 |