| Owner | Filings | Most Recent |
|---|---|---|
| ORSID NEW YORK | 11 | 09/18/2026 |
| 260 APARTMENTS | 94 | 09/13/2026 |
| ROCK GROUP NY | 13 | 07/08/2026 |
| UPTOWN CONSTRUCTION SERVICE GROUP I | 3 | 07/08/2026 |
| KOSSARS 72 | 14 | 07/04/2026 |
| MIDBORO MANAGEMENT | 14 | 03/22/2026 |
| 260 APTS CORP MIDBORO MAN | 2 | 03/22/2026 |
| 260 APTS CORP MIDBORO MGM | 2 | 03/22/2026 |
| TO OWNER OF 260 WEST END | 1 | 03/22/2026 |
| HARTMAN | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GNE ARCHITECTURE | 6 | 06/05/2026 |
| LOMBARDO PROFESSIONAL ENGINEERING | 2 | 05/18/2026 |
| HLZAE, INC. | 2 | 03/13/2026 |
| SARAH CARPENTER | 1 | 12/12/2025 |
| YAO W GUO ARCHITECT, PC | 23 | 07/21/2025 |
| MATTHEW RUOPOLI, AIA | 1 | 01/02/2025 |
| EP ENGINEERING LLC | 1 | 01/02/2025 |
| BLACK BOX ENGINEERING | 1 | 01/02/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 11/12/2024 |
| MUNYC ARCHITECTURE PLLC | 13 | 08/21/2024 |
| LAWP ARCHITECTURE P.C. | 2 | 01/24/2024 |
| SY ENGINEERING PLLC | 2 | 10/11/2023 |
| THE NEW BLACK ARCHITECTURE & DESIGN | 4 | 09/20/2022 |
| ASIF JAMIL, RA | 2 | 08/03/2021 |
| FEINGOLD AND GREGORY ARCH. | 2 | 03/22/2021 |
| ERIC ANDREASEN ARCHITECT, PLLC | 1 | 03/17/2020 |
| CHAPMAN ARCHITECTS | 1 | 10/02/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| BOUTIQKEY | 10 | 03/21/2026 |
| BREND RESTORATION SERVICES | 2 | 03/21/2026 |
| HLZAE | 2 | 03/21/2026 |
| LAWP ARCHITECTURE | 4 | 03/21/2026 |
| GREEN STUDIO | 4 | 03/21/2026 |
| PAUL FUSCO CONSULTING | 6 | 03/21/2026 |
| OUTHERE SPACE | 4 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 3 | 03/21/2026 |
| W J PROFESSIONAL EXPEDITING COMPANY | 8 | 03/21/2026 |
| GRAMERCY RENOVATION & RESTORATION L | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GLOBAL DESIGN CONCEPT COR | General Contractor | 23 | 07/08/2026 |
| QMB PLUMBING & HEATING INC | Plumbing | 9 | 07/08/2026 |
| ROCK GROUP NY CORP | General Contractor | 7 | 07/08/2026 |
| PROFESSIONAL CONSTRUCTION | General Contractor | 6 | 07/08/2026 |
| BREND RESTORATION SRVC | General Contractor | 4 | 09/17/2026 |
| INTELOGIC ELECTRIC, INC. | Electrical | 3 | 03/22/2026 |
| HAMILTON AIR COMPANY, INC. | General Contractor | 3 | 07/08/2026 |
| BREND RESTORATION LLC | General Contractor | 3 | 09/18/2026 |
| YH DESIGN INC | General Contractor | 3 | 03/21/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 2 | 07/08/2026 |
| AMC CONSTRUCTION AND DESIGN | General Contractor | 2 | 03/21/2026 |
| ANGELOS'S HOME IMPROVEMEN | General Contractor | 2 | 07/08/2026 |
| GEC DESIGN GROUP LTD | General Contractor | 2 | 03/21/2026 |
| ARTISTIC DETAIL CONTRACT | General Contractor | 1 | 07/08/2026 |
| ORBIT SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| SCHONDORF MICHAEL | Electrical | 1 | 03/21/2026 |
| SANDHA GENERAL CONTRACTIN | Electrical | 1 | 03/21/2026 |
| REDGRAVE ELECTL MAINTNCE | Electrical | 1 | 03/22/2026 |
| TERRA DEVELOPERS, LLC | General Contractor | 1 | 07/04/2026 |
| UPTOWN CONSTRUCTION SERV | General Contractor | 1 | 07/08/2026 |
| MOTTES, STEVE | Electrical | 1 | 03/21/2026 |
| ZACCO BUILDING CORP | General Contractor | 1 | 04/09/2026 |
| ARIEL SERVICES INC | Plumbing | 1 | 07/08/2026 |
| BENT MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| M C M PLBG & HTG, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AG ENGINEERING PLLC | 8899 | 6 | 06/05/2026 |
| HOWARD L ZIMMERMAN ARCHIT | 1712 | 2 | 03/13/2026 |
| CEYLAN DESIGN AND CONSULT | 8422 | 4 | 12/12/2025 |
| YAO W GUO ARCHITECT P.C. | 1754 | 18 | 06/10/2025 |
| WORLD DESIGN ARCHITECTURE | 9323 | 4 | 01/02/2025 |
| MUNYC ARCHITECTURE PLLC | 5224 | 11 | 07/17/2024 |
| RHL ENGINEERING, LLC | 712 | 1 | 07/17/2024 |
| SY ENGINEERING PLLC | 5149 | 2 | 10/11/2023 |
| LAWP ARCHITECTURE | 3782 | 1 | 09/15/2023 |
| THE NEW BLACK ARCHITECTUR | 5899 | 4 | 09/20/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | BREND RESTORATION LLC | 09/17/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | BREND RESTORATION SRVC | 09/16/2026 |
| DOB NOW | Structural | Permit Issued | BREND RESTORATION SRVC | 07/21/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | BREND RESTORATION LLC | 06/23/2026 |
| DOB NOW | General Construction | Permit Issued | BREND RESTORATION SRVC | 05/29/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | BREND RESTORATION SRVC | 05/18/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | BREND RESTORATION LLC | 03/31/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | BREND RESTORATION LLC | 03/13/2026 |
| DOB NOW | General Construction | Permit Issued | AMC CONSTRUCTION DESI | 01/16/2026 |
| DOB NOW | Plumbing | Signed-off | M C M PLBG & HTG, INC | 09/19/2025 |
| DOB NOW | General Construction | Signed-off | ZACCO BUILDING CORP | 09/17/2025 |
| DOB NOW | Plumbing | Permit Issued | WYNNE PLBG & HTG CORP | 05/01/2025 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 04/24/2025 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 04/09/2025 |
| DOB NOW | Structural | Permit Issued | ANGELOSS HOME IMPROVEMEN | 03/17/2025 |
| DOB NOW | General Construction | Permit Issued | ANGELOSS HOME IMPROVEMEN | 03/03/2025 |
| DOB NOW | General Construction | Signed-off | HAMILTON AIR COMPANY, INC. | 02/13/2025 |
| DOB NOW | Supported Scaffold | Signed-off | UPTOWN CONSTRUCTION SERV | 11/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HAMILTON AIR COMPANY, INC. | 10/23/2024 |
| DOB NOW | Plumbing | Signed-off | PROSTAR PLUMBING AND HEAT | 09/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ARTISTIC DETAIL CONTRACT | 09/03/2024 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 08/08/2024 |
| DOB NOW | General Construction | Signed-off | CONSOLIDATED SCAFFOLDING | 08/07/2024 |
| DOB NOW | Sprinklers | Permit Issued | ORBIT SPRINKLER CORP | 02/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | GLOBAL DESIGN CONCEPT COR | 12/08/2023 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 11/17/2023 |
| DOB NOW | Sprinklers | Signed-off | ORBIT PLBG & HTG INC | 11/13/2023 |
| DOB NOW | General Construction | Signed-off | TERRA DEVELOPERS, LLC | 10/19/2023 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 08/03/2023 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 07/26/2023 |
| DOB NOW | Mechanical Systems | Signed-off | GLOBAL DESIGN CONCEPT COR | 06/15/2023 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 06/14/2023 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 06/05/2023 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 02/24/2023 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 01/31/2023 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 09/12/2022 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 09/08/2022 |
| DOB NOW | General Construction | Signed-off | PROFESSIONAL CONSTRUCTION | 08/08/2022 |
| DOB NOW | General Construction | Signed-off | GLOBAL DESIGN CONCEPT COR | 08/02/2022 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HEATING INC | 08/02/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/11/2023 | — | — | Air Conditioning Systems | Cooling Skypeak SKY-CU-SH120 10 tons · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/11/2023 | Permit Issued | ORBIT SPRINKLER CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2026 | Signed-off | M C M PLBG & HTG, INC | Water/Sanitary |
| 01/02/2025 | Permit Issued | WYNNE PLBG & HTG CORP | Water/Sanitary |
| 10/11/2023 | Signed-off | ORBIT PLBG & HTG INC | Water/Sanitary |
| 03/22/2021 | Permit Issued | BENT MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/31/2026 | Permit Issued | TOP SHELF ELECTRIC CORP | — |
| 09/21/2025 | Complete | INDY ELECTRIC CORP. | General Wiring |
| 04/24/2025 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 03/21/2025 | Permit Issued | ASSET ELECTRIC CORP | General Wiring |
| 03/05/2025 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 12/30/2024 | Permit Issued | GMJ ELECTRIC CORP | General Wiring |
| 09/11/2024 | Complete | NION ELECTRIC CORP | General Wiring |
| 07/03/2024 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 01/16/2024 | Complete | GMJ ELECTRIC CORP | General Wiring |
| 10/03/2023 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 10/03/2023 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 10/03/2023 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 08/07/2023 | Complete | NION ELECTRIC CORP | General Wiring |
| 06/28/2023 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| 05/23/2023 | Complete | VOLVIE HERMAN CONTRG CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Permit Issued | BREND RESTORATION SRVC | 1 scope_items |
| 01/02/2025 | Permit Issued | WYNNE PLBG & HTG CORP | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2026 | Permit Issued | BREND RESTORATION SRVC | Scaffold |
| 03/31/2026 | Permit Issued | BREND RESTORATION LLC | Sidewalk Shed |
| 01/24/2024 | — | — | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2026 | Signed-off | M C M PLBG & HTG, INC | Tenant Protection Plan 72 Hour |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2026 | Permit Issued | BREND RESTORATION LLC | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/21/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/07/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/03/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/25/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/20/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/19/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/12/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/03/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/21/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/18/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/18/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/18/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/17/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/26/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/08/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/12/2026 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 06/01/2026 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 05/22/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Michael Lombardo | special |
| 05/18/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Michael Lombardo | special |
| 03/11/2026 | Post-installed Anchors | Jon Colatrella | special |
| 03/11/2026 | Structural Steel - High Strength Bolting | Jon Colatrella | special |
| 03/11/2026 | Masonry | Jon Colatrella | special |
| 03/11/2026 | Structural Steel - Welding | Jon Colatrella | special |
| 03/11/2026 | Tenant Protection Plan Compliance | Jon Colatrella | special |
| 03/11/2026 | Structural Steel - Details | Jon Colatrella | special |
| 03/03/2026 | Structural Stability – Alterations of existing buildings | Jon Colatrella | special |
| 03/03/2026 | Final | Jon Colatrella | progress |
| 01/28/2026 | Energy Code Compliance Inspections | Greg Epstein | progress |
| 01/28/2026 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 01/28/2026 | Final | Greg Epstein | progress |
| 01/28/2026 | Lighting controls | Greg Epstein | energy_progress |
| 01/28/2026 | Lighting in dwelling units | Greg Epstein | energy_progress |
| 12/24/2025 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 12/24/2025 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 12/24/2025 | Energy Code Compliance Inspections | Greg Epstein | progress |
| 12/24/2025 | Final | Greg Epstein | progress |
| 12/24/2025 | Lighting in dwelling units | Greg Epstein | energy_progress |
| 12/24/2025 | Lighting controls | Greg Epstein | energy_progress |
| 09/08/2025 | Energy Code Compliance Inspections | Greg Epstein | progress |
| 08/20/2025 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |