| Owner | Filings | Most Recent |
|---|---|---|
| GID | 29 | 07/08/2026 |
| GID PROPERTY MGMT | 6 | 03/22/2026 |
| MYRIAD CONSTRUCTION SERVI | 4 | 03/22/2026 |
| TISHMAN CONSTRUCTION | 17 | 03/22/2026 |
| PINNACLE INDUSTRIES LLC | 4 | 03/22/2026 |
| INF ASSOCIATES | 1 | 03/22/2026 |
| RCB 4 NOMINEE LLC A DELAWARE | 13 | 03/21/2026 |
| RCB1 NOMINEE LLC A DELAWARE LIM | 49 | 03/21/2026 |
| RCB1 NOMINEE | 27 | 03/21/2026 |
| RCB1 NOMINEE LLC C O GID DEV GRP | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| WELLWORTH CONSULTING LLC | 1 | 04/06/2026 |
| FREYER COLLABORATIVE ARCHITECTS | 2 | 03/29/2024 |
| CES ENGINEERING LLC | 6 | 03/08/2024 |
| ARNOLD MONTAG ARCHITECT AM/PM DESI | 1 | 08/29/2023 |
| MOHAMMAD AHEAD, PE | 1 | 03/21/2023 |
| ARCHINET NY | 2 | 04/29/2022 |
| BRYAN M BROWN ARCHITECTS LLC | 2 | 04/28/2022 |
| A&D ASSOCIATES, INC. | 5 | 04/19/2022 |
| GARRETT GOURLAY, RA | 1 | 04/12/2022 |
| HUSTVEDT CUTLER ARCHITECTS | 2 | 03/04/2022 |
| NEW PRACTICE STUDIO LLC | 3 | 02/04/2022 |
| GREYBAR ARCHITECTURE PLLC | 3 | 09/16/2021 |
| WSP | 4 | 07/27/2021 |
| F.P.VILLANO CONSULTING ENGINEER LLC | 4 | 05/18/2021 |
| G. BLINN CONSULTING, LLC | 1 | 09/19/2019 |
| C3D ARCHITECTURE PLLC | 1 | 05/31/2019 |
| SAFWAY ATLANTIC LLC | 4 | 06/15/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| LOUIS STRIAR | 10 | 03/21/2026 |
| NYCCODE | 16 | 03/21/2026 |
| METROPOLIS GROUP INC | 14 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 4 | 03/21/2026 |
| JM ZONING, LLC. | 14 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 2 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 10 | 03/21/2026 |
| WM ARCH | 6 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAFWAY ATLANTIC, LLC | General Contractor | 17 | 07/08/2026 |
| MYRIAD CONSTRUCTION SERVI | General Contractor | 12 | 07/08/2026 |
| CLINTON CONST INC | General Contractor | 6 | 03/21/2026 |
| S&E BRIDGE & SCAFFOLD LLC. | General Contractor | 6 | 03/21/2026 |
| DVE CONSTRUCTION INC | General Contractor | 6 | 03/21/2026 |
| ROUNDSQUARE BUILDERS,LLC | General Contractor | 5 | 07/08/2026 |
| CITY SIGNS | Scaffold | 3 | 07/08/2026 |
| HIGHLINE CONSTRUCTION GR | General Contractor | 3 | 07/08/2026 |
| RRP PLUMBING CORP | Fire Protection | 2 | 07/08/2026 |
| METROTECH MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| KAPNAG HEATING & PLBG COR | Fire Protection | 2 | 07/08/2026 |
| FRED GELLER ELEC'L INC. | Electrical | 2 | 03/22/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 2 | 07/10/2026 |
| FORTE EXPRESS P & H INC | Plumbing | 2 | 07/08/2026 |
| JP GENERAL CONTRACTOR & | General Contractor | 1 | 07/08/2026 |
| GLENDALE ELECTL CONTNG IN | Electrical | 1 | 03/22/2026 |
| KNIGHT ELEC'L SERV. CORP. | Electrical | 1 | 03/22/2026 |
| OMD ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| SPIRELLI ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| J. CAIAZZO PLBG & HTG CORP | Fire Protection | 1 | 07/08/2026 |
| ALL CITY REMODELING, INC | General Contractor | 1 | 07/08/2026 |
| CRESCO ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| SUCCESS CONTACT INC | General Contractor | 1 | 07/08/2026 |
| ACCESS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FREYER COLLABORATIVE ARCH | 2198 | 2 | 03/29/2024 |
| METRIC CONSULTING AND INS | 1803 | 5 | 03/08/2024 |
| ARNOLD MONTAG ARCHITECT, | 4599 | 1 | 08/29/2023 |
| LINEA LLP | 3155 | 7 | 04/19/2022 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 03/10/2022 |
| DY SPECIAL INSPECTION LLC | 7210 | 3 | 02/04/2022 |
| TECTONIC ENGINEERING CONS | 106 | 5 | 07/27/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | SPRING SCAFFOLDING LLC | 07/08/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | STRUCTURAL PRESERVATION S | 05/04/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | SPRING SCAFFOLDING LLC | 04/06/2026 |
| DOB NOW | General Construction | Signed-off | CLINTON CONST INC | 11/16/2023 |
| DOB NOW | General Construction | Signed-off | CLINTON CONST INC | 09/19/2023 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 04/06/2023 |
| DOB NOW | Plumbing | Signed-off | FORTE EXPRESS P & H INC | 11/01/2022 |
| DOB NOW | Mechanical Systems | Signed-off | MYRIAD CONSTRUCTION SERVI | 10/19/2022 |
| DOB NOW | General Construction | Signed-off | MYRIAD CONSTRUCTION SERVI | 10/19/2022 |
| DOB NOW | General Construction | Signed-off | ALL CITY REMODELING, INC | 09/06/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HIGHLINE CONSTRUCTION GR | 08/19/2022 |
| DOB NOW | General Construction | Signed-off | HIGHLINE CONSTRUCTION GR | 08/19/2022 |
| DOB NOW | General Construction | Signed-off | HIGHLINE CONSTRUCTION GR | 08/19/2022 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 08/18/2022 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 08/18/2022 |
| DOB NOW | Sprinklers | Signed-off | KAPNAG HEATING & PLBG COR | 08/15/2022 |
| DOB NOW | Sprinklers | Signed-off | KAPNAG HEATING & PLBG COR | 08/15/2022 |
| DOB NOW | General Construction | Signed-off | JP GENERAL CONTRACTOR & | 05/24/2022 |
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 05/24/2022 |
| DOB NOW | Mechanical Systems | Signed-off | MYRIAD CONSTRUCTION SERVI | 01/06/2022 |
| DOB NOW | General Construction | Signed-off | MYRIAD CONSTRUCTION SERVI | 01/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | MYRIAD CONSTRUCTION SERVI | 11/30/2021 |
| DOB NOW | Plumbing | Signed-off | FORTE EXPRESS P & H INC | 10/27/2021 |
| DOB NOW | General Construction | Signed-off | MYRIAD CONSTRUCTION SERVI | 10/26/2021 |
| DOB NOW | General Construction | Signed-off | MYRIAD CONSTRUCTION SERVI | 10/06/2021 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 08/18/2021 |
| DOB NOW | Plumbing | Signed-off | RALPH W. LANDOLFI JR. | 08/18/2021 |
| DOB NOW | Plumbing | Signed-off | KAPNAG HTG & PLBG CORP. | 07/27/2021 |
| DOB NOW | General Construction | Signed-off | SUCCESS CONTACT INC | 07/20/2021 |
| DOB NOW | Sprinklers | Signed-off | RALPH W. LANDOLFI JR. | 06/24/2021 |
| DOB NOW | General Construction | Signed-off | DVE CONSTRUCTION INC | 06/02/2021 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 05/18/2021 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 05/18/2021 |
| DOB NOW | Sprinklers | Signed-off | RRP PLUMBING CORP | 05/18/2021 |
| DOB NOW | General Construction | Signed-off | DVE CONSTRUCTION INC | 05/06/2021 |
| DOB NOW | Mechanical Systems | Signed-off | ROUNDSQUARE BUILDERS,LLC | 03/07/2021 |
| DOB NOW | Mechanical Systems | Signed-off | ROUNDSQUARE BUILDERS,LLC | 02/13/2021 |
| DOB NOW | Mechanical Systems | Signed-off | ROUNDSQUARE BUILDERS,LLC | 02/01/2021 |
| DOB NOW | Plumbing | Signed-off | ANTHONY CAIAZZO | 01/21/2021 |
| DOB NOW | Plumbing | Signed-off | ACCESS PLUMBING CORP | 12/18/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2021 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/30/2026 | Permit Issued | TOP SHELF ELECTRIC CORP | — |
| 04/16/2025 | Complete | GLENDALE ELECTL CONTNG IN | — |
| 04/19/2024 | Complete | SCHLESINGER ELECT'L CONTR | General Wiring |
| 06/14/2023 | Complete | KNIGHT ELEC'L SERV. CORP. | General Wiring |
| 06/09/2023 | Complete | CRESCO ELECTRICAL CORP | General Wiring |
| 02/20/2023 | Complete | OMD ELECTRICAL CORP | 1 meters, 1 new_meters |
| 02/15/2023 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 10/06/2022 | Complete | V.I.P. ELECTL CONTR CORP | General Wiring |
| 04/19/2022 | Complete | FRED GELLER ELEC'L INC. | General Wiring |
| 03/03/2022 | Complete | ATTRACTIVE LIGHTING ELECL | — |
| 12/02/2021 | Complete | KNIGHT ELEC'L SERV. CORP. | General Wiring |
| 09/15/2021 | Complete | LIPPOLIS ELECTRIC, INC. | General Wiring |
| 08/06/2021 | Complete | STELLMANN ELECTRICAL CORP | General Wiring |
| 06/23/2021 | Cancelled | GSA ELECTRIC CORP. | General Wiring |
| 06/21/2021 | Complete | SPIRELLI ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/21/2026 | Permit Issued | STRUCTURAL PRESERVATION S | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/17/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/31/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/06/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/06/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/17/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/09/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/30/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/22/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/22/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/22/2022 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 06/09/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/22/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/03/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/28/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/25/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/20/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/20/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/29/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/26/2024 | Final | Warren Freyer | progress |
| 03/26/2024 | Fire-Resistant Penetrations and Joints | Warren Freyer | special |
| 03/22/2024 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 03/07/2024 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 08/23/2023 | Final | Arnold Montag | progress |
| 08/01/2023 | Fire-Resistance Rated Construction | Arnold Montag | progress |
| 08/01/2023 | Energy Code Compliance Inspections | Arnold Montag | progress |
| 08/01/2023 | Fire-Resistant Penetrations and Joints | Arnold Montag | special |
| 06/08/2022 | HVAC-R and service water heating system controls | SAMI HAJJAR P.E | energy_progress |
| 06/08/2022 | Ventilation and air distribution system | SAMI HAJJAR P.E | energy_progress |
| 06/08/2022 | HVAC-R and service water heating equipment | SAMI HAJJAR P.E | energy_progress |
| 06/08/2022 | HVAC-R and service water piping design and insulation | SAMI HAJJAR P.E | energy_progress |
| 06/06/2022 | Energy Code Compliance Inspections | SAMI HAJJAR P.E | progress |
| 05/17/2022 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 05/17/2022 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 05/17/2022 | Final | SAMI HAJJAR P.E | progress |
| 04/25/2022 | Fire-Resistant Penetrations and Joints | Lisa Vangelas | special |
| 04/25/2022 | Energy Code Compliance Inspections | Lisa Vangelas | progress |
| 04/25/2022 | Post-installed Anchors | Lisa Vangelas | special |
| 04/21/2022 | Final | WEN-HAU HSU | progress |
| 04/13/2022 | Final | SAMI HAJJAR P.E | progress |
| 04/13/2022 | Final | SAMI HAJJAR P.E | progress |
| 04/08/2022 | Final | Garrett Gourlay | progress |
| 03/14/2022 | Energy Code Compliance Inspections | Lisa Vangelas | progress |
| 03/14/2022 | Final | Axay Patel | progress |