| Owner | Filings | Most Recent |
|---|---|---|
| 32 West 20th Street | 26 | 03/21/2026 |
| Thirt Two West 20 St | 22 | 03/22/2026 |
| 32 W 20 Condominium | 9 | 03/21/2026 |
| Thirty Two | 6 | 03/21/2026 |
| Ziehersmith | 3 | 03/21/2026 |
| Pure Obgyn | 2 | 03/21/2026 |
| 32 West 20 | 2 | 03/21/2026 |
| Cooper SQ Realty | 1 | 03/21/2026 |
| Carolyn Dicarlo Group | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Level-Up Engineering | 3 | 09/02/2026 |
| Suntect | 1 | 08/28/2026 |
| Rauch Architecture | 1 | 07/08/2025 |
| Ssuperette Design | 2 | 11/19/2024 |
| CES Engineering | 1 | 01/30/2024 |
| Brendan Canning | 1 | 11/28/2023 |
| CL Engineering | 2 | 03/29/2022 |
| Jacobson Shinoda Architects | 2 | 09/27/2021 |
| Anz Consulting Engineering | 9 | 02/16/2021 |
| Andrew Franz Architect | 3 | 01/11/2021 |
| Judge Architecture | 3 | 12/06/2019 |
| Haider Engineering, P.E | 1 | 08/03/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB Building Consulting | 4 | 03/21/2026 |
| Michael Zenreich Architect | 4 | 03/21/2026 |
| H J Building Consulting | 4 | 03/21/2026 |
| Anzalone Architecture | 18 | 03/21/2026 |
| Rite One Expediting | 2 | 03/21/2026 |
| Codegreen | 3 | 03/21/2026 |
| Haider Engineering, P.E | 1 | 03/21/2026 |
| Haider Engineering P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Reis EY | General Contractor | 4 | 04/09/2026 |
| Gma Air Cooling & Heating | specialty_contractor | 3 | 03/21/2026 |
| Knockout Construction | General Contractor | 3 | 07/08/2026 |
| Mr. Air NYC | General Contractor | 3 | 03/21/2026 |
| Bednarz Construction | General Contractor | 3 | 03/21/2026 |
| Donato Plumbing | Plumbing | 3 | 07/08/2026 |
| Overall Renovation | General Contractor | 3 | 03/21/2026 |
| John Trani Plumbing and Heating | Plumbing | 3 | 07/08/2026 |
| McManus Mechanical Maintenance P&H Co | Fire Protection | 2 | 07/08/2026 |
| Branch Plumbing | Plumbing | 2 | 07/08/2026 |
| C.W.C. Fire Suppression | Plumbing | 2 | 07/08/2026 |
| Mark Contracting NY | Scaffold | 2 | 03/21/2026 |
| Urban Standard General Co | General Contractor | 1 | 09/17/2026 |
| VCS Mechanical | specialty_contractor | 1 | 10/01/2026 |
| Knockout Construction | Scaffold | 1 | 07/08/2026 |
| Arcon Plumbing Solutions | Plumbing | 1 | 07/08/2026 |
| DPH Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Bass Electrical | Electrical | 1 | 03/22/2026 |
| Nice Plumbing | Plumbing | 1 | 09/30/2026 |
| Star Electrical Contractors | Electrical | 1 | 03/21/2026 |
| JLC Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Big Shot Electric | Electrical | 1 | 03/21/2026 |
| Maor Electr'l Service | Electrical | 1 | 03/21/2026 |
| Flemington Electrical Maintenance I | Electrical | 1 | 03/21/2026 |
| Prudent Electric | Electrical | 1 | 03/22/2026 |
| BLH Elect'l Contractors | Electrical | 1 | 03/21/2026 |
| Silverman Robert | Electrical | 1 | 03/21/2026 |
| Apollo Electric NYG | Electrical | 1 | 03/21/2026 |
| Warren Ostroff Electric | Electrical | 1 | 03/21/2026 |
| Level Up Plumbing | Fire Protection | 1 | 09/30/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Level-Up Engineering, PLL | 9616 | 3 | 09/02/2026 |
| Suntect | 4788 | 1 | 08/28/2026 |
| Rauch Architecture | 7888 | 1 | 07/08/2025 |
| SD Testing & Inspection S | 7010 | 1 | 11/19/2024 |
| Michael Zenreich Architects | 1724 | 2 | 01/30/2024 |
| CL Engineering | 6781 | 2 | 03/29/2022 |
| Anz Consulting Engineering | 3946 | 9 | 02/16/2021 |
| Andrew Franz Architect, P | 2384 | 1 | 01/06/2020 |
| Judge Architecture | 748 | 3 | 12/06/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | VCS Mechanical | 09/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | Level Up Plumbing | 09/29/2026 |
| DOB NOW | Plumbing | Permit Issued | Nice Plumbing | 09/29/2026 |
| DOB NOW | General Construction | Permit Issued | Urban Standard General Co | 09/16/2026 |
| DOB NOW | Plumbing | Permit Issued | Donato Plumbing | 05/05/2026 |
| DOB NOW | General Construction | Permit Issued | Reis EY | 12/10/2025 |
| DOB NOW | Plumbing | Permit Issued | Donato Plumbing | 04/04/2025 |
| DOB NOW | General Construction | Permit Issued | Reis EY | 12/18/2024 |
| DOB NOW | Plumbing | Signed-off | DPH Plumbing & Heating | 12/17/2024 |
| DOB NOW | General Construction | Signed-off | Overall Renovation | 12/10/2024 |
| DOB NOW | Plumbing | Permit Issued | Donato Plumbing | 04/08/2024 |
| DOB NOW | Plumbing | Permit Issued | Arcon Plumbing Solutions | 02/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Mr. Air NYC | 01/29/2022 |
| DOB NOW | General Construction | Signed-off | Knockout Construction | 10/25/2021 |
| DOB NOW | Construction Fence | Signed-off | Knockout Construction | 08/16/2021 |
| DOB NOW | Sprinklers | Signed-off | McManus Mechanical Maintenance P&H Co | 08/02/2021 |
| DOB NOW | Plumbing | Signed-off | John Trani Plumbing and Heating | 11/05/2020 |
| DOB NOW | Plumbing | Signed-off | John Trani Plumbing and Heating | 11/04/2020 |
| DOB NOW | Sprinklers | Signed-off | McManus Mechanical Maintenance P&H Co | 10/30/2020 |
| DOB NOW | Plumbing | Signed-off | John Trani Plumbing and Heating | 09/28/2020 |
| DOB NOW | Plumbing | Signed-off | Branch Plumbing | 07/24/2020 |
| DOB NOW | Mechanical Systems | Signed-off | Knockout Construction | 07/08/2020 |
| DOB NOW | Plumbing | Signed-off | C.W.C. Fire Suppression | 03/06/2020 |
| DOB NOW | Mechanical Systems | Signed-off | Bednarz Construction | 02/27/2020 |
| DOB NOW | Plumbing | Signed-off | C.W.C. Fire Suppression | 02/24/2020 |
| DOB NOW | Mechanical Systems | Signed-off | Gma Air Cooling & Heating | 11/06/2019 |
| DOB NOW | Plumbing | Signed-off | Branch Plumbing | 10/15/2019 |
| DOB NOW | Construction Fence | Signed-off | Mark Contracting NY | 08/07/2018 |
| BIS | SP | ISSUED | Fred Smith Plumbing & Heating Co | 06/01/2023 |
| BIS | PL | ISSUED | Fred Smith P&H Co | 06/01/2023 |
| BIS | SP | ISSUED | Fred Smith Plumbing & Heating Co | 06/01/2023 |
| BIS | OT | ISSUED | Five Stars Awnings & Sign | 01/30/2023 |
| BIS | OT | ISSUED | Lco Construction Management | 07/19/2020 |
| BIS | OT | ISSUED | Knockout Construction | 07/07/2020 |
| BIS | OT | ISSUED | Lco Construction Management | 07/07/2020 |
| BIS | OT | ISSUED | Bednarz Construction | 02/06/2020 |
| BIS | OT | ISSUED | Lco Construction Management | 10/09/2019 |
| BIS | FS | ISSUED | Rockway Fuel Oil | 06/27/2019 |
| BIS | PL | ISSUED | S & L Plumbing | 04/23/2019 |
| BIS | OT | ISSUED | Mark Contracting NY | 04/10/2019 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/30/2024 | Permit Issued | Reis EY | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Permit Issued | Level Up Plumbing | Sprinkler System |
| 01/30/2024 | — | — | 48 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Permit Issued | Level Up Plumbing | Gas, Water/Sanitary |
| 01/30/2024 | Permit Issued | Donato Plumbing | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/23/2026 | Permit Issued | W 8 Electric | General Wiring |
| 04/07/2025 | Permit Issued | Warren Ostroff Electric | — |
| 12/10/2024 | Permit Issued | Blue Seagull Electrical | General Wiring |
| 03/22/2022 | Complete | Intelogic Electric | HVAC Wiring |
| 10/01/2020 | Permit Issued | Power Surge Electric | — |
| 09/27/2020 | Permit Issued | Power Surge Electric | General Wiring |
| 02/19/2020 | Complete | Jumper Electric | General Wiring |
| 10/24/2019 | Complete | Prudent Electric | General Wiring |
| 08/30/2018 | Complete | Bass Electrical | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/01/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 09/01/2026 | Energy Code Compliance Inspections | — | progress |
| 09/01/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 09/01/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 09/01/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 09/01/2026 | Maintenance information | — | energy_progress |
| 08/26/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 08/26/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/26/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 08/26/2026 | Maintenance information | — | energy_progress |
| 08/26/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/26/2026 | Post-installed Anchors | — | special |
| 08/25/2026 | Fire-Resistant Penetrations and Joints | David Haner | special |
| 08/25/2026 | Lighting in dwelling units | David Haner | energy_progress |
| 08/25/2026 | Post-installed Anchors | David Haner | special |
| 06/19/2026 | Sprinkler Systems | — | special |
| 06/18/2026 | Final | — | progress |
| 06/18/2026 | Final | David Haner | progress |
| 06/18/2026 | Mechanical Systems | — | special |
| 07/08/2025 | Fire-Resistance Rated Construction | Matthew Rauch | progress |
| 07/08/2025 | Tenant Protection Plan Compliance | Matthew Rauch | special |
| 07/08/2025 | Energy Code Compliance Inspections | Matthew Rauch | progress |
| 07/08/2025 | Post-installed Anchors | Matthew Rauch | special |
| 07/08/2025 | Fire-Resistant Penetrations and Joints | Matthew Rauch | special |
| 06/23/2025 | Final | Matthew Rauch | progress |