| Owner | Filings | Most Recent |
|---|---|---|
| Vornado Realty Trust | 524 | 09/13/2026 |
| 330 West 34th St | 24 | 03/21/2026 |
| Mendik Realty Co | 14 | 03/21/2026 |
| MRC Mngmnt LLC Division Vornd RE | 4 | 03/21/2026 |
| Northeast Service Group | 2 | 03/22/2026 |
| RW Dake & Co | 2 | 03/22/2026 |
| 330 West 34th Owner | 1 | 03/22/2026 |
| Goldman Copeland Associates | 1 | 03/22/2026 |
| DGC Contracting | 1 | 03/22/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| Gilman Consultant | 44 | 03/21/2026 |
| Archetype Consultants | 126 | 03/21/2026 |
| City Building NY Architect P | 6 | 03/21/2026 |
| New York Sign Consultants | 4 | 03/21/2026 |
| Building Brothers | 4 | 03/21/2026 |
| BAC Developers Group | 3 | 03/21/2026 |
| Green Studio | 2 | 03/21/2026 |
| Milrose Consultants | 2 | 03/21/2026 |
| Cherico King Architect P | 6 | 03/21/2026 |
| Patuxent Engineering | 2 | 03/21/2026 |
| All in Permit Consultants | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Vanguard Construction and | General Contractor | 23 | 07/08/2026 |
| Structure Tone | General Contractor | 22 | 07/08/2026 |
| Andamio Scaffolding | Scaffold | 19 | 07/08/2026 |
| JRM Construction Management | General Contractor | 14 | 07/08/2026 |
| W5 Group | General Contractor | 11 | 07/08/2026 |
| John Gallin & Son | General Contractor | 8 | 07/08/2026 |
| Lhotse | General Contractor | 7 | 07/08/2026 |
| Everest Scaffolding | Scaffold | 6 | 07/08/2026 |
| Skyline Fire Sprinkler Co | Fire Protection | 5 | 07/08/2026 |
| Five Horsemen | General Contractor | 5 | 04/09/2026 |
| Mill Brook Fire Protection | Fire Protection | 4 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 4 | 07/08/2026 |
| Marlin Mechanical | specialty_contractor | 4 | 07/08/2026 |
| Bedrock Plumbing & Heating | Plumbing | 4 | 07/08/2026 |
| Icon Interiors | General Contractor | 3 | 07/17/2026 |
| A&A Plumbing | Plumbing | 3 | 07/08/2026 |
| Sirina Fire Protection | Fire Protection | 3 | 07/08/2026 |
| PSI Partners | Fire Protection | 3 | 07/08/2026 |
| Tristate Plumbing Services | Plumbing | 2 | 07/08/2026 |
| S. J. Electric | Electrical | 2 | 03/21/2026 |
| Corp Electrical Technologies | Electrical | 2 | 03/22/2026 |
| Patriot Electric | Electrical | 2 | 03/22/2026 |
| Polo Electric Corp D/B/A | Electrical | 2 | 03/21/2026 |
| Ambassador Construction | General Contractor | 2 | 03/21/2026 |
| New York Ladder & Scaffold | Scaffold | 2 | 07/08/2026 |
| Going Sign & Servicing Co | Sign hanger | 2 | 10/04/2026 |
| Paul Signs | Sign hanger | 2 | 07/08/2026 |
| S.B.A. Plumbing | Plumbing | 2 | 07/08/2026 |
| Department of Social Services | Electrical | 2 | 03/21/2026 |
| Nychra | Electrical | 2 | 03/21/2026 |
| Signs Cad | Sign hanger | 1 | 07/08/2026 |
| Going Sign Servicing | General Contractor | 1 | 03/21/2026 |
| A & M Warshaw Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| A + Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Going Kevin | General Contractor | 1 | 03/21/2026 |
| Capitol Fire Sprinkler Co | Fire Protection | 1 | 07/08/2026 |
| N.Y.C. Police Department | Electrical | 1 | 03/21/2026 |
| Northeast Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Cintron Electrical Services & Ligt | Electrical | 1 | 03/21/2026 |
| Safepipe Plumbing | Fire Protection | 1 | 07/08/2026 |
| Safepipe Plumbing | Plumbing | 1 | 07/08/2026 |
| MC Superstructure | Scaffold | 1 | 07/08/2026 |
| Acm Electric | Electrical | 1 | 03/22/2026 |
| Shamrock Mechanical | Fire Protection | 1 | 07/08/2026 |
| National Maintenance | Sign hanger | 1 | 07/08/2026 |
| Neptune Signs & Awnings | Sign hanger | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| New York Engineering Associates | 851 | 1 | 08/03/2026 |
| Hansen Engineering | 8174 | 15 | 07/06/2026 |
| City Building NY Architects | 1394 | 2 | 04/10/2025 |
| Prudigm Engineering Llcu | 4304 | 2 | 04/10/2025 |
| Milrose Consultants | 2003 | 2 | 10/29/2024 |
| Skyline Engineering | 267 | 21 | 04/10/2024 |
| Alan D Marcus, PE | 1761 | 11 | 05/04/2023 |
| Becker Engineering | 633 | 21 | 01/23/2023 |
| TSF Engineering | 1274 | 3 | 12/02/2021 |
| G&G Sprinkler Services | 2782 | 3 | 03/24/2021 |
| Tan Engineering | 1291 | 3 | 12/16/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Permit Issued | East Coast Petroleum | 08/04/2026 |
| DOB NOW | Structural | Permit Issued | Icon Interiors | 07/16/2026 |
| DOB NOW | General Construction | Permit Issued | Icon Interiors | 04/07/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 04/03/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Icon Interiors | 04/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | Mora Fire Protection | 04/02/2026 |
| DOB NOW | Sign | Signed-off | Signs Cad | 03/23/2026 |
| DOB NOW | Sprinklers | Permit Issued | Mora Fire Protection | 01/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | Mora Fire Protection | 01/28/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 01/16/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 01/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM Construction Management | 01/09/2026 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 01/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM Construction Management | 01/09/2026 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 01/09/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Five Horsemen | 12/17/2025 |
| DOB NOW | Sprinklers | Signed-off | Bellerose Plumbing & Heating | 08/08/2025 |
| DOB NOW | General Construction | Permit Issued | Five Horsemen | 07/25/2025 |
| DOB NOW | Plumbing | Signed-off | Bellerose Plumbing & Heating | 07/23/2025 |
| DOB NOW | General Construction | Permit Issued | Five Horsemen | 06/17/2025 |
| DOB NOW | Sign | Permit Issued | Polsinelli, Henry | 12/18/2024 |
| DOB NOW | General Construction | Signed-off | Structure Tone | 11/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Structure Tone | 11/06/2024 |
| DOB NOW | Sign | Signed-off | Paul Signs | 01/31/2024 |
| DOB NOW | Sign | Signed-off | Paul Signs | 01/31/2024 |
| DOB NOW | General Construction | Permit Issued | Vanguard Construction and | 01/29/2024 |
| DOB NOW | Structural | Signed-off | Vanguard Construction and | 01/29/2024 |
| DOB NOW | General Construction | Signed-off | Vanguard Construction and | 01/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Vanguard Construction and | 01/29/2024 |
| DOB NOW | General Construction | Signed-off | Vanguard Construction and | 01/29/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Andamio Scaffolding | 11/14/2023 |
| DOB NOW | General Construction | Signed-off | Lhotse | 11/03/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 10/25/2023 |
| DOB NOW | General Construction | Permit Issued | Vanguard Construction and | 10/19/2023 |
| DOB NOW | Supported Scaffold | Signed-off | Andamio Scaffolding | 08/11/2023 |
| DOB NOW | Construction Fence | Permit Issued | MC Superstructure | 07/26/2023 |
| DOB NOW | Structural | Signed-off | Vanguard Construction and | 06/27/2023 |
| DOB NOW | Structural | Signed-off | Vanguard Construction and | 06/13/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Vanguard Construction and | 06/13/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Vanguard Construction and | 06/13/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/25/2026 | Permit Issued | Icon Interiors | Air Conditioning Systems | Cooling Above Air MCW-007D-7-HGH0 1,200 CFM · Wshp ×3 |
| 04/10/2025 | Signed-off | Five Horsemen | Air Conditioning Systems, Refrigeration Systems, Ventilation Systems | |
| 03/19/2024 | Signed-off | Vanguard Construction and | Air Conditioning Systems, Associated Ducts and Piping, Heating and Air Conditioning Systems | Cooling Hitachi HITACHI/TVAHP120B32S 10 tons · Vrf Outdoor ×4 HITACH/TVAHR144B32S 12 tons · Vrf Outdoor ×2 HITACHI/TVAHR168B32S 14 tons · Vrf Outdoor ×2 TIDH036B23S 3 tons · Split System ×2 Technical Systems TECHNICAL SYSTEMS/20A0LD10-1 10 tons · Condensing Unit ×2 Heat / Cool Hitachi HITACHI / TIC4012B21S 2 tons · Split System ×10 HITACHI / TIDH036B23S 3 tons · Split System ×5 HITACHI / TIDH048B23S 4 tons · Split System ×4 HITACHI /TIDH048B23S 4 tons · Vrf Outdoor ×4 HITACHI / TIC4024B21S 2 tons · Split System ×2 HITACHI / TIDH015B23S 1 tons · Split System ×2 HITACHI / TIWM024B22S 2 tons · Split System ×2 HITACHI /TIDH024B23S 2 tons · Split System ×2 TIDH024B23S 2 tons · Vrf Indoor ×2 TIDH036B23S 3 tons · Split System ×2 Ducts & Piping N/A N/A 1 BTU · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/24/2026 | Permit Issued | PSI Partners | 1,163 heads |
| 04/10/2025 | Signed-off | Safepipe Plumbing | 9 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/24/2026 | Permit Issued | A&A Plumbing | Water/Sanitary |
| 03/24/2026 | — | — | — |
| 12/01/2025 | Permit Issued | A&A Plumbing | Water/Sanitary |
| 04/10/2025 | Signed-off | Safepipe Plumbing | Water/Sanitary |
| 04/10/2024 | Signed-off | Bedrock Plumbing & Heating | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Complete | Jem Electrical Contracting | General Wiring |
| 04/07/2026 | Complete | Metropolis Electric | General Wiring |
| 01/30/2026 | Permit Issued | Cintron Electrical Services & Ligt | General Wiring |
| 05/26/2024 | Complete | Acm Electric | General Wiring |
| 02/09/2024 | Permit Issued | Limitless Electric Resources | General Wiring |
| 02/09/2024 | Permit Issued | Limitless Electric Resources | General Wiring |
| 08/29/2023 | Complete | Live Wire Electric 1 | General Wiring |
| 05/14/2023 | Complete | Zerem Electric | General Wiring |
| 09/07/2022 | Permit Issued | Polo Electric Corp D/B/A | 2 meters, 2 new_meters |
| 07/14/2022 | Complete | Live Wire Electric 1 | General Wiring |
| 04/07/2022 | Complete | Zerem Electric | — |
| 10/08/2021 | Complete | Live Wire Electric 1 | General Wiring |
| 08/06/2021 | Permit Issued | Inter Connection Eletric | — |
| 06/11/2021 | Complete | Corp Electrical Technologies | General Wiring |
| 04/07/2021 | Complete | OM Electrical Contracting | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/06/2026 | Permit Issued | Icon Interiors | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/26/2023 | Permit Issued | MC Superstructure | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/16/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/24/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/21/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/21/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/18/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/26/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/24/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/26/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/21/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/21/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/19/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 03/12/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/08/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/20/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/20/2023 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 12/12/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/12/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 09/19/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/01/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/20/2026 | Fuel-Oil Storage and Fuel-Oil Piping Systems | LOUIS ARENA | special |
| 05/29/2026 | Structural Steel - High Strength Bolting | Ryan Hansen | special |
| 05/29/2026 | Structural Steel - Details | Ryan Hansen | special |
| 05/29/2026 | Final | Ryan Hansen | progress |
| 05/29/2026 | Structural Steel - Welding | Ryan Hansen | special |
| 05/29/2026 | Concrete - Cast-In-Place | Ryan Hansen | special |
| 03/18/2026 | Post-installed Anchors | Ryan Hansen | special |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 03/17/2026 | Final | Ryan Hung | progress |
| 03/06/2026 | Final | Ryan Hansen | progress |
| 03/06/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 03/06/2026 | Fire-Resistance Rated Construction | Ryan Hansen | progress |
| 03/06/2026 | Sprinkler Systems | Ryan Hansen | special |
| 03/06/2026 | Sprayed fire-resistant materials | Ryan Hansen | special |
| 03/06/2026 | Post-installed Anchors | Ryan Hansen | special |
| 11/13/2025 | Interior lighting power | Ryan Hansen | energy_progress |
| 11/13/2025 | Energy Code Compliance Inspections | Ryan Hansen | progress |
| 11/13/2025 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 11/13/2025 | HVAC-R and service water piping design and insulation | Ryan Hansen | energy_progress |
| 11/13/2025 | Energy Code Compliance Inspections | Ryan Hansen | progress |
| 11/13/2025 | Lighting controls | Ryan Hansen | energy_progress |
| 11/13/2025 | Interior lighting power | Ryan Hansen | energy_progress |
| 11/13/2025 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 11/13/2025 | Lighting controls | Ryan Hansen | energy_progress |
| 11/13/2025 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Rippling | Office | Floors 7–9 | Project M01368386 Project M01368392 Project M01368399 Project M01368404 |
| Barney Brown | Restaurant / Food Service | Floor 1 | Project M01368175 Project M01196910 Project M01196914 Project M01196933 Project M01196902 |
| Stobg Innovation Lab | Office | Floor 12 | Project M01114295 Project M01096517 |
| Bar Primi | Restaurant / Food Service | Cellar, Sub-basement, Floor 1, Mezzanine | Project M00984326 Project M00984342 Project M08028415 Project M08028305 Project M08028332 Project M08029850 Project M00764780 Project M00764810 Project M00764848 Project M00762716 Project M00764745 |
| MedRite | Medical / Healthcare | Cellar, Floor 1 | Project M00620052 Project M00619819 Project M00620074 |
| Dokaworks | Restaurant / Food Service | Floor 1 | Project M00265915 Project M00265983 Project M00267496 |
| Just Salad | Restaurant / Food Service | Floor 1 | Project M00203905 |
| Starbucks | Restaurant / Food Service | Floor 1 | Project M00109163 |