| Owner | Filings | Most Recent |
|---|---|---|
| 410 PARK AVENUE ASSOCIATES | 469 | 07/08/2026 |
| GLOBAL HOLDINGS MANAGEMENT GROUP | 28 | 07/08/2026 |
| PLATINUM SERVICES NY | 5 | 03/22/2026 |
| CHASE 410 ASSOC | 1 | 03/22/2026 |
| CAHSE 410 ASSOC | 1 | 03/22/2026 |
| GALBREATH | 7 | 03/22/2026 |
| CHARTER COMMUNICATIONS | 1 | 03/22/2026 |
| GHM INC(US) | 5 | 03/21/2026 |
| 410 PARK ASSOCIATES | 194 | 03/21/2026 |
| 875 THIRD AVENUE | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PATUXENT ENGINEERING LLC | 1 | 08/14/2024 |
| ASHRAF CORP | 1 | 07/28/2024 |
| CANY ARCHITECTURE & ENGINEERING DPC | 1 | 06/03/2024 |
| PATTI & ANTHES CONSULTING ENGINEERS | 38 | 12/18/2023 |
| GARO GUMUSYAN | 16 | 11/07/2023 |
| THREE STUDIO ARCHITECTURE, D.P.C. | 2 | 03/20/2023 |
| LILKER ASSOCIATES CONSULTING ENGINE | 9 | 01/05/2023 |
| SPECTOR GROUP II LLP | 1 | 01/04/2023 |
| DESIMONE CONSULTING ENGINEERS | 2 | 01/03/2023 |
| HNY CONSULTING ENGINEERS LLC | 7 | 06/18/2021 |
| ABCO-PEERLESS ENGINEERING, P.C. | 1 | 06/07/2021 |
| HC ARCHITECT, PC | 4 | 06/03/2021 |
| METHOD ARCHITECTS PLLC | 1 | 04/21/2021 |
| COLOMBO ARCHITECTURAL STUDIO PC | 1 | 04/12/2021 |
| M. CHETRIT CONSULTING ENGINEERS P.C | 2 | 06/25/2020 |
| SAFWAY ATLANTIC LLC | 1 | 04/23/2020 |
| TPG ARCHITECTURE, LLP | 1 | 09/12/2019 |
| DOOLING & COMPANY ARCHITECTS | 1 | 07/26/2019 |
| GREGORY V. PEROTTO, P.E. | 1 | 03/06/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| GARO GUMUSYAN | 63 | 03/21/2026 |
| LMS-ACE SERVICES | 16 | 03/21/2026 |
| SMEP DESIGN & CONSULTATION LLC | 4 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| JP EXPEDITE | 8 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 2 | 03/21/2026 |
| EMPIRE CITY CONSULTANTS, INC. | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| PEROTTO CONSULTING MANAGEMENT | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRIME CONSTRUCTION MGMT | General Contractor | 50 | 07/08/2026 |
| HARLAND MECHANICAL INC | General Contractor | 9 | 03/21/2026 |
| V. CLOUD PAINTING AND CON | Electrical | 8 | 03/21/2026 |
| SEAN COAKLEY P & H INC | Plumbing | 7 | 07/08/2026 |
| SEAN COAKLEY P & H INC | Fire Protection | 7 | 07/08/2026 |
| INTERSTATE INTERIORS INC | General Contractor | 7 | 07/08/2026 |
| ICON INTERIORS INC | General Contractor | 5 | 07/08/2026 |
| FULL CAPACITY FIRE CORP | Fire Protection | 4 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 4 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 3 | 03/21/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 3 | 07/08/2026 |
| STRUCTURAL PRESERV SYSTEM | General Contractor | 3 | 07/08/2026 |
| URBAN INTELLIGENCE, INC | General Contractor | 3 | 03/21/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 3 | 07/08/2026 |
| F1 MECHANICAL INC | Plumbing | 3 | 07/08/2026 |
| CAD SIGNS NYC | Scaffold | 3 | 07/08/2026 |
| DEVO FIRE PROTECTION INC | Fire Protection | 2 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Fire Protection | 2 | 07/08/2026 |
| JRM CONSTRUCTION MGMT LLC | General Contractor | 2 | 03/21/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 2 | 07/08/2026 |
| SIGNS CAD | Scaffold | 1 | 07/08/2026 |
| PAUL BOCCIA | Electrical | 1 | 03/21/2026 |
| ROBERT CHIMENTI | Electrical | 1 | 03/22/2026 |
| ROBERT LOGOZIO | Electrical | 1 | 03/21/2026 |
| PSI PARTNERS, LLC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONSULTING AND TESTING SE | 6152 | 12 | 06/03/2024 |
| SARO GUMUSYAN ARCHITECT | 6437 | 42 | 12/18/2023 |
| AK ENGINEERING PC | 678 | 7 | 03/20/2023 |
| DELTA TESTING LABS | 687 | 15 | 07/01/2021 |
| SKYLINE ENGINEERING, PLLC | 267 | 1 | 06/07/2021 |
| JOSE A SANTOS PE, PC | 3292 | 1 | 04/12/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 05/19/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 05/19/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | URBAN INTELLIGENCE, INC | 08/14/2024 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 07/29/2024 |
| DOB NOW | General Construction | Signed-off | STRUCTURAL PRESERV SYSTEM | 07/10/2024 |
| DOB NOW | General Construction | Signed-off | STRUCTURAL PRESERV SYSTEM | 07/10/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 05/28/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 05/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HVAC CONSTRUCTION INC | 01/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PRIME CONSTRUCTION MGMT | 10/20/2023 |
| DOB NOW | Plumbing | Signed-off | SEAN COAKLEY P & H INC | 10/19/2023 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 10/19/2023 |
| DOB NOW | General Construction | Signed-off | PRIME CONSTRUCTION MGMT | 10/17/2023 |
| DOB NOW | Plumbing | Signed-off | SEAN COAKLEY P & H INC | 05/30/2023 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 05/30/2023 |
| DOB NOW | General Construction | Signed-off | ICON INTERIORS INC | 05/15/2023 |
| DOB NOW | Mechanical Systems | Signed-off | PRIME CONSTRUCTION MGMT | 05/02/2023 |
| DOB NOW | General Construction | Signed-off | PRIME CONSTRUCTION MGMT | 05/02/2023 |
| DOB NOW | Sprinklers | Signed-off | MORA FIRE PROTECTION LLC | 02/03/2023 |
| DOB NOW | Plumbing | Signed-off | WILLIAM C. GERAKARIS P&H | 02/01/2023 |
| DOB NOW | General Construction | Signed-off | ICON INTERIORS INC | 01/10/2023 |
| DOB NOW | Structural | Signed-off | ICON INTERIORS INC | 01/06/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ICON INTERIORS INC | 01/06/2023 |
| DOB NOW | Plumbing | Signed-off | SEAN COAKLEY P & H INC | 11/18/2022 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 11/18/2022 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 09/15/2022 |
| DOB NOW | Plumbing | Signed-off | SEAN COAKLEY P & H INC | 09/15/2022 |
| DOB NOW | General Construction | Signed-off | PRIME CONSTRUCTION MGMT | 09/14/2022 |
| DOB NOW | General Construction | Signed-off | PRIME CONSTRUCTION MGMT | 09/13/2022 |
| DOB NOW | Mechanical Systems | Signed-off | PRIME CONSTRUCTION MGMT | 09/12/2022 |
| DOB NOW | Mechanical Systems | Signed-off | PRIME CONSTRUCTION MGMT | 09/12/2022 |
| DOB NOW | General Construction | Signed-off | PRIME CONSTRUCTION MGMT | 06/15/2022 |
| DOB NOW | Sprinklers | Signed-off | ABCO-PEERLESS SPRKLR CORP | 06/03/2022 |
| DOB NOW | Mechanical Systems | Signed-off | PRIME CONSTRUCTION MGMT | 05/06/2022 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 05/06/2022 |
| DOB NOW | Plumbing | Signed-off | SEAN COAKLEY P & H INC | 05/06/2022 |
| DOB NOW | General Construction | Signed-off | PRIME CONSTRUCTION MGMT | 05/06/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HARLAND MECHANICAL INC | 04/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HARLAND MECHANICAL INC | 04/15/2022 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 04/12/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2022 | Permit Issued | SEAN COAKLEY P & H INC | — |
| 07/01/2021 | Permit Issued | SEAN COAKLEY P & H INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2022 | Permit Issued | SEAN COAKLEY P & H INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/30/2024 | Complete | 5 J'S ELECTL CONTS CORP | — |
| 04/08/2024 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 03/18/2024 | Complete | AMERGY ELECTRIC OF NY INC | General Wiring |
| 11/07/2023 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 08/25/2023 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 04/18/2023 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 04/13/2023 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 04/13/2023 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 01/30/2023 | Complete | PATRIOT ELECTRIC CORP | — |
| 07/26/2022 | Permit Issued | ROBERT CHIMENTI | 4 meters, 1 new_meters |
| 12/14/2021 | Permit Issued | CONDUCTOR ELECL SVCS INC | General Wiring |
| 05/17/2021 | Complete | RAIDEN ELECTRIC LLC | General Wiring |
| 03/16/2021 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 01/06/2021 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 11/18/2020 | Complete | ELPO ELECTRICAL CONTG INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2024 | Signed-off | STRUCTUAL PRESV SYSTEM | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/17/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/11/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/08/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/04/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/04/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/23/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/07/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/06/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/30/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/26/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/09/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/18/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/21/2023 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 05/30/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/17/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/21/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/20/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/03/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/31/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/28/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/15/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/15/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/22/2024 | Structural Stability – Alterations of existing buildings | DANIEL CREIGHTON | special |
| 04/22/2024 | Structural Steel - Welding | DANIEL CREIGHTON | special |
| 04/22/2024 | Final | Nathanael Morejon | progress |
| 04/22/2024 | Masonry | DANIEL CREIGHTON | special |
| 04/22/2024 | Post-installed Anchors | DANIEL CREIGHTON | special |
| 12/06/2023 | Mechanical Systems | Saro Gumusyan | special |
| 12/06/2023 | HVAC-R and service water piping design and insulation | Saro Gumusyan | energy_progress |
| 12/06/2023 | Final | Saro Gumusyan | progress |
| 12/06/2023 | Fire-Resistant Penetrations and Joints | Saro Gumusyan | special |
| 12/06/2023 | HVAC-R and service water heating system controls | Saro Gumusyan | energy_progress |
| 12/06/2023 | Maintenance information | Saro Gumusyan | energy_progress |
| 11/13/2023 | Final | Saro Gumusyan | progress |
| 11/13/2023 | Fire-Resistant Penetrations and Joints | Saro Gumusyan | special |
| 11/13/2023 | Mechanical Systems | Saro Gumusyan | special |
| 11/13/2023 | HVAC-R and service water piping design and insulation | Saro Gumusyan | energy_progress |
| 11/13/2023 | Duct leakage testing, insulation and design | Saro Gumusyan | energy_progress |
| 11/13/2023 | Metering | Saro Gumusyan | energy_progress |
| 11/13/2023 | Maintenance information | Saro Gumusyan | energy_progress |
| 11/09/2023 | Final | Saro Gumusyan | progress |
| 11/09/2023 | Fire-Resistant Penetrations and Joints | Saro Gumusyan | special |
| 11/09/2023 | Maintenance information | Saro Gumusyan | energy_progress |
| 11/09/2023 | Lighting controls | Saro Gumusyan | energy_progress |
| 11/09/2023 | Interior lighting power | Saro Gumusyan | energy_progress |
| 11/06/2023 | Maintenance information | Saro Gumusyan | energy_progress |
| 11/06/2023 | Lighting controls | Saro Gumusyan | energy_progress |