1964Year Built
19Stories
D4Building Class
C1-6Zoning
262,297 sfGross Floor Area
261Units
LL97 CoveredRent Stabilized56 Active Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: 61 Jane St Tenants · 16,682 sf lot · 15.72 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofFacade, roof, and terrace restoration16p · 4 filings · 20 docs
PenthouseFacade, roof, and terrace restoration12p · 1 filing · 19 docs
Floor 18Unit 18A, Unit 18B, Unit 18F +2Under Construction19p · 5 filings · 20 docs
Floor 17Unit 17M3p · 2 filings · 12 docs
Floor 16Unit 16E, Unit 16F, Unit 16G7p · 4 filings · 20 docs
Floor 15Unit 15G8p · 1 filing · 14 docs
Floor 14Unit 14J, Unit 14K7p · 6 filings · 20 docs
Floor 13
Floor 12Unit 12G, Unit 12H, Unit 12JUnder Construction7p · 3 filings · 20 docs
Floor 11Unit 11H, Unit 11K6p · 2 filings · 18 docs
Floor 10Unit 10C, Unit 10E, Unit 10M +122p · 6 filings · 20 docs
Floor 9Unit 9G, Unit 9J, Unit 9L +129p · 5 filings · 20 docs
Floor 8Unit 8A, Unit 8E, Unit 8F +3Under Construction13p · 6 filings · 20 docs
Floor 7
Floor 6
Floor 5
Floor 4Unit 4E, Unit 4J, Unit 4K +2Under Construction22p · 6 filings · 20 docs
Floor 3
Floor 2Unit 2E, Unit 2H21p · 2 filings · 20 docs
Floor 1Unit 1C6p · 3 filings · 20 docs
CellarDouglas Elliman Property Management work4p · 2 filings · 20 docs
Site & exteriorCentral Const Management36p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
61 Jane St Tenants19503/22/2026
61 Jane St1803/21/2026
Giovanni Martini Contractor203/22/2026
Tenants103/22/2026
FPS103/22/2026
Gansevoort Coop103/21/2026
Key Real Estate Associates103/21/2026
Inspeco103/21/2026
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Freedom GSGeneral Contractor1807/08/2026
Renwood InteriorsGeneral Contractor1007/08/2026
Accurate MechanicalPlumbing1007/08/2026
Central Construction ManagementGeneral Contractor707/08/2026
Nest Inc Interior ContractingGeneral Contractor607/08/2026
Central Construction ManagementScaffold610/04/2026
Star Renovations NYGeneral Contractor603/21/2026
Bindela ConstructionGeneral Contractor407/08/2026
Pepaj ConstructionGeneral Contractor406/27/2026
Asa Building MaintenanceGeneral Contractor409/18/2026
Sac WirelessGeneral Contractor407/08/2026
Hydrokinetic Plumbing & Heating IPlumbing307/08/2026
BMV MechanicalPlumbing307/08/2026
Aqua Plumbing & HeatingPlumbing307/08/2026
Squan Construction ServicesGeneral Contractor307/08/2026
Overland ContractingGeneral Contractor303/21/2026
L.I. Newman ConsultingGeneral Contractor303/21/2026
A Plus PlumbingPlumbing207/08/2026
A+ Electric of Greater NYElectrical203/22/2026
Argon ElectricalElectrical203/22/2026
Arma ElectricElectrical203/22/2026
Omd ElectricalElectrical203/22/2026
Agalliu ContractingGeneral Contractor207/10/2026
Ceko ContractingGeneral Contractor207/08/2026
DKCGeneral Contractor203/21/2026
FJB ContractingGeneral Contractor210/07/2026
Metro Mechanicalspecialty_contractor203/21/2026
BT's Plumbing and HeatingPlumbing207/04/2026
Superior Plumbing & HeatingPlumbing207/08/2026
ZFMPlumbing209/18/2026
Orbit Plumbing & HeatingPlumbing107/08/2026
R & T ElectricalElectrical103/22/2026
Prudent ElectricElectrical103/22/2026
Plumbing P & HPlumbing107/08/2026
Meir Electric CoElectrical103/21/2026
L.J.F. & Sons Electrical ContsElectrical103/22/2026
K & G Electric CoElectrical103/21/2026
P.S.R. Construction/RenovationGeneral Contractor107/08/2026
All Ways Electric Corp.wElectrical103/21/2026
RST RenovationGeneral Contractor107/25/2026
Elpo Electrical ContgElectrical103/21/2026
Arma ElectricElectrical103/21/2026
Gotham Wiring LicensedElectrical103/22/2026
Total Builder ConstructionGeneral Contractor108/14/2026
Tri-State Marble & TileGeneral Contractor107/08/2026
FSM ElectricalElectrical103/22/2026
Elpo Electrical ContgElectrical103/22/2026
A.M.NPlumbing107/08/2026
A.C. Morgan ElectricElectrical103/22/2026
Cresco ElectricalElectrical103/22/2026
Bent MechanicalPlumbing107/08/2026
Billy ServulusElectrical103/21/2026
VMC Plumbing & HeatingPlumbing107/08/2026
CC Controlled Plumbing CoPlumbing106/28/2026
Egl HeatingPlumbing107/08/2026
Fred J. RiehmPlumbing108/01/2026
AJC Interior Renovation IGeneral Contractor107/08/2026
Arthur CzechGeneral Contractor107/08/2026
Trincity ElectricElectrical103/22/2026
Apollo Electric NYGElectrical103/21/2026
Glenns Plumbing ServicesPlumbing107/14/2026
Powerone Elect'l ContractingElectrical103/21/2026
Associated Electric Cont of NElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Broadway Inspections8735109/30/2026
Cherico King Architect5674208/21/2026
Robert F. Germain Jr. PE5100308/03/2026
PSI Agency254107/22/2026
EDG2578205/18/2026
Crosscheck Inspection Services544809/25/2025
Glickman Schlesinger Architects67681009/25/2025
Outsource Special Inspection2827308/21/2025
Enthink Engineers6247504/25/2025
Jong Hae Chang Architect6169101/17/2025
TSS Engineers4492108/29/2024
H2 Consulting PE835105/18/2024
Jaj Engineering930104/25/2024
Katz Engineering238405/24/2023
Buildtech Engineering6369103/13/2023
Jeremy K McKeon, P.E7263108/14/2022
Versai8133109/15/2021
Architecture Work Office6054111/06/2019
Kit Middleton Architect P1204109/11/2019
R Marsac Consulting329106/11/2019
Building Lifecycle
All (300)Filed (56)Permit Issued (60)Signed Off (31)Violation (13)Inspection (36)Objection (74)Special Inspection (30)
10/06/2026
Permit issued — General Construction
M01424556-I1-GC
09/30/2026
Filed — Alteration
FILING HEREWITH KITCHEN AND BATHROOM RENOVATION WITH THE REMOVAL AND INSTALLATION OF FIXTURES IN KIND AS SHOWN ON THE DRAWINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01424556-I1
09/30/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/23/2026
Signed off — Alteration
Minor interior renovation of existing apartment unit as per plan submitted herewith. No change in use, egress, or occupancy under this application
M01386182-I1
09/17/2026
Permit issued — Plumbing
M01413884-S1-PL
09/17/2026
Permit issued — General Construction
M01413884-I1-GC
09/15/2026
Special inspection requirement — Fire-Resistance Rated Construction
Salvatore Chiarelli
09/15/2026
Special inspection requirement — Energy Code Compliance Inspections
Salvatore Chiarelli
09/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Salvatore Chiarelli
09/09/2026
Special inspection requirement — Tenant Protection Plan Compliance
Salvatore Chiarelli
09/03/2026
Permit issued — Suspended Scaffold
M01062980-I1-SC
09/03/2026
Permit issued — Sidewalk Shed
M01109813-I1-SH
08/21/2026
Filed — Alteration
IT IS PROPOSED TO RENOVATE EXISTING KITCHEN & BATHROOM IN APT-8E ON 8TH FLOOR. REPLACE PLUMBING FIXTURES & APPLIANCE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01413884-I1
08/21/2026
Filed — Alteration
IT IS PROPOSED TO RENOVATE EXISTING KITCHEN & BATHROOM IN APT-8E ON 8TH FLOOR. REPLACE PLUMBING FIXTURES & APPLIANCE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01413884-S1
08/21/2026
Special inspection requirement — Lighting in dwelling units
Cherico King
08/21/2026
Special inspection requirement — Lighting controls
Cherico King
08/21/2026
Special inspection requirement — Interior lighting power
Cherico King
08/13/2026
Permit issued — General Construction
M01149072-I1-GC
08/12/2026
Signed off — Alteration
Garage repairs as shown on the drawings filed herewith. No change in use, egress, or occupancy.
M01252026-I1
08/10/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
08/04/2026
Special inspection requirement — Tenant Protection Plan Compliance
08/03/2026
Filed — Alteration
INSTALL (1) NEW GAS FIRED DOMESTIC HOT WATER HEATER WITH (2) NEW STORAGE TANKS. RECONNECT LOW PRESSURE GAS LINE. NO CHANGE IN MEANS OF EGRESS, USE GROUP OR OCCUPANCY.
M01250421-P2
07/31/2026
Permit issued — Plumbing
M01400331-S2-PL
07/29/2026
Signed off — Alteration
Modifications to the existing plumbing system on the 9th floor (Apartments 9L & 9M) as per plans. No change to use, egress or occupancy.
M00541788-I1
07/29/2026
Permit issued — General Construction
M01400331-I1-GC
07/24/2026
Signed off — Alteration
M00541732-I1
07/23/2026
Permit issued — General Construction
M01386182-I1-GC
07/23/2026
Objection raised — Scope
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection raised — Other
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection raised — Other
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection raised — Other
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection raised — Other
07/23/2026
Objection resolved — Addressed
07/23/2026
Objection raised — Inspections
07/23/2026
Objection resolved — Addressed
07/22/2026
Filed — Alteration
COMBINE APTS. 12H & 12J., RENOVATE 12H BATHROOM IN-KIND. REPLACE EXG KITCHEN W/ NEW LAUNDRY ROOM TOTAL SF KITCHEN LAUNDRY RM 44 SF BATHROOM SF 36 SF
M01400331-S2
07/22/2026
Filed — Alteration
COMBINE APTS. 12H & 12J., RENOVATE 12H BATHROOM IN-KIND. REPLACE EXG KITCHEN W/ NEW LAUNDRY ROOM TOTAL SF KITCHEN LAUNDRY RM 44 SF BATHROOM SF 36 SF
M01400331-I1
07/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
07/17/2026
Special inspection requirement — Tenant Protection Plan Compliance
07/13/2026
Permit issued — Plumbing
M01149072-S1-PL
07/09/2026
Permit issued — General Construction
M01317655-I1-GC
06/30/2026
Special inspection requirement — Final
Salvatore Chiarelli
06/26/2026
Filed — Alteration
Modifications to the existing plumbing system on the 9th floor (Apartments 9L & 9M) as per plans. No change to use, egress or occupancy.
M00541788-P1
06/25/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/17/2026
Objection resolved — Resolved
06/15/2026
Special inspection requirement — Final
VIVEK SHAH
06/15/2026
Special inspection requirement — Post-installed Anchors
VIVEK SHAH
06/15/2026
Special inspection requirement — Concrete - Cast-In-Place
VIVEK SHAH
06/15/2026
Special inspection requirement — Tenant Protection Plan Compliance
JONAR MADRIAGA
06/15/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
VIVEK SHAH
06/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Cherico King
06/11/2026
Special inspection requirement — Tenant Protection Plan Compliance
LAWRENCE MAREK
06/08/2026
Objection raised — Scope
06/08/2026
Special inspection requirement — Fire-Resistance Rated Construction
Cherico King
06/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Cherico King
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedFJB Contracting10/06/2026
DOB NOWPlumbingPermit IssuedZFM09/17/2026
DOB NOWGeneral ConstructionPermit IssuedAsa Building Maintenance09/17/2026
DOB NOWSuspended ScaffoldPermit IssuedCentral Construction Management09/03/2026
DOB NOWSidewalk ShedPermit IssuedCentral Construction Management09/03/2026
DOB NOWGeneral ConstructionPermit IssuedTotal Builder Construction08/13/2026
DOB NOWPlumbingPermit IssuedFred J. Riehm07/31/2026
DOB NOWGeneral ConstructionPermit IssuedFJB Contracting07/29/2026
DOB NOWGeneral ConstructionSigned-offRST Renovation07/23/2026
DOB NOWPlumbingPermit IssuedGlenns Plumbing Services07/13/2026
DOB NOWGeneral ConstructionPermit IssuedAgalliu Contracting07/09/2026
DOB NOWGeneral ConstructionPermit IssuedCentral Construction Management03/18/2026
DOB NOWPlumbingPermit IssuedAnthony Disabato01/26/2026
DOB NOWGeneral ConstructionPermit IssuedAgalliu Contracting01/16/2026
DOB NOWGeneral ConstructionSigned-offCentral Construction Management01/05/2026
DOB NOWStructuralPermit IssuedCentral Construction Management11/06/2025
DOB NOWPlumbingSigned-offAnthony Disabato10/28/2025
DOB NOWGeneral ConstructionSigned-offFreedom GS10/27/2025
DOB NOWGeneral ConstructionSigned-offFreedom GS10/27/2025
DOB NOWGeneral ConstructionSigned-offFreedom GS10/27/2025
DOB NOWSupported ScaffoldPermit IssuedCentral Construction Management10/22/2025
DOB NOWGeneral ConstructionSigned-offFreedom GS10/01/2025
DOB NOWGeneral ConstructionPermit IssuedCentral Construction Management09/29/2025
DOB NOWPlumbingSigned-offCC Controlled Plumbing Co09/22/2025
DOB NOWSidewalk ShedPermit IssuedCentral Construction Management09/16/2025
DOB NOWSuspended ScaffoldPermit IssuedCentral Construction Management09/16/2025
DOB NOWGeneral ConstructionPermit IssuedNest Inc Interior Contracting09/11/2025
DOB NOWPlumbingSigned-offAnthony Disabato07/21/2025
DOB NOWPlumbingSigned-offAnthony Disabato07/21/2025
DOB NOWGeneral ConstructionSigned-offFreedom GS07/15/2025
DOB NOWGeneral ConstructionPermit IssuedNest Inc Interior Contracting06/25/2025
DOB NOWGeneral ConstructionPermit IssuedNest Inc Interior Contracting06/10/2025
DOB NOWGeneral ConstructionSigned-offFreedom GS06/10/2025
DOB NOWPlumbingPermit IssuedEgl Heating02/05/2025
DOB NOWGeneral ConstructionPermit IssuedNest Inc Interior Contracting01/29/2025
DOB NOWPlumbingSigned-offA.M.N01/07/2025
DOB NOWStructuralPermit IssuedCentral Construction Management11/13/2024
DOB NOWSupported ScaffoldPermit IssuedCentral Construction Management10/15/2024
DOB NOWGeneral ConstructionSigned-offAsa Building Maintenance10/08/2024
DOB NOWPlumbingSigned-offPlumbing P & H10/07/2024
+ 60 more permits on file
8 projects · most recent 08/21/2026
Gas Water/Sanitary
FiledStatusContractorScope
08/21/2026Permit IssuedZFMGas, Water/Sanitary
08/03/2026Signed-offCC Controlled Plumbing CoGas
07/22/2026Permit IssuedFred J. RiehmGas, Water/Sanitary
06/26/2026Signed-offBT's Plumbing and HeatingGas, Water/Sanitary
09/25/2025Permit IssuedAccurate MechanicalGas, Water/Sanitary
06/26/2025Permit IssuedGlenns Plumbing ServicesGas, Water/Sanitary
10/04/2021Permit IssuedAccurate MechanicalGas, Water/Sanitary
11/06/2019Signed-offBMV MechanicalWater/Sanitary
25 projects · most recent 10/19/2026
General Wiring
FiledStatusContractorScope
10/19/2026Permit IssuedArgon ElectricalGeneral Wiring
10/05/2026Permit IssuedBNH ElectricalGeneral Wiring
09/09/2026Permit IssuedThe Metro Group ElectricGeneral Wiring
09/09/2026Permit IssuedThe Metro Group ElectricGeneral Wiring
09/09/2026Permit IssuedThe Metro Group ElectricGeneral Wiring
09/03/2026Permit IssuedMontgomery Electrical ContractingGeneral Wiring
07/01/2026Permit IssuedMontgomery Electrical ContractingGeneral Wiring
06/17/2026Permit IssuedCresco ElectricalGeneral Wiring
06/08/2026CompleteAccurate Electrical—
05/21/2026Permit IssuedPaul's ElectricGeneral Wiring
05/19/2026CompleteGlendale Electl ContngGeneral Wiring
04/17/2026CompleteEverest Electrical ContractingGeneral Wiring
02/03/2026CompleteArma ElectricGeneral Wiring
01/22/2026Permit IssuedEmpire Lic Electrical ContractorsGeneral Wiring
07/26/2025CompleteArma ElectricGeneral Wiring
2 projects · most recent 05/18/2026
Concrete
FiledStatusContractorScope
05/18/2026Signed-offCentral Construction ManagementConcrete
10/16/2024Permit IssuedCentral Construction Management1 scope_items
2 projects · most recent 03/04/2025
Sidewalk Shed Scaffold
FiledStatusContractorScope
03/04/2025Permit IssuedCentral Construction ManagementSidewalk Shed
03/04/2025Permit IssuedCentral Construction ManagementScaffold
1 project · most recent 10/02/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
10/02/2024Permit IssuedCentral Construction ManagementSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 49
DateTypeResultReport
09/30/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/10/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/25/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/03/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/22/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/14/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/20/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/31/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/01/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/30/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/13/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/13/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/20/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/20/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/10/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/17/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/11/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/21/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/23/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/12/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/23/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/12/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/19/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
Latest 25 of 49.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
09/15/2026Energy Code Compliance InspectionsSalvatore Chiarelliprogress
09/15/2026Fire-Resistant Penetrations and JointsSalvatore Chiarellispecial
09/15/2026Fire-Resistance Rated ConstructionSalvatore Chiarelliprogress
09/09/2026Tenant Protection Plan ComplianceSalvatore Chiarellispecial
08/21/2026Lighting in dwelling unitsCherico Kingenergy_progress
08/21/2026Interior lighting powerCherico Kingenergy_progress
08/21/2026Lighting controlsCherico Kingenergy_progress
08/04/2026Tenant Protection Plan Compliance—special
08/04/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
07/17/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
07/17/2026Tenant Protection Plan Compliance—special
06/30/2026FinalSalvatore Chiarelliprogress
06/15/2026Concrete - Cast-In-PlaceVIVEK SHAHspecial
06/15/2026Post-installed AnchorsVIVEK SHAHspecial
06/15/2026Structural Stability – Alterations of existing buildingsVIVEK SHAHspecial
06/15/2026Tenant Protection Plan ComplianceJONAR MADRIAGAspecial
06/15/2026FinalVIVEK SHAHprogress
06/11/2026Fire-Resistant Penetrations and JointsCherico Kingspecial
06/11/2026Tenant Protection Plan ComplianceLAWRENCE MAREKspecial
06/08/2026Tenant Protection Plan ComplianceCherico Kingspecial
06/08/2026Fire-Resistant Penetrations and JointsCherico Kingspecial
06/08/2026Energy Code Compliance InspectionsCherico Kingprogress
06/08/2026Fire-Resistance Rated ConstructionCherico Kingprogress
05/14/2026Tenant Protection Plan Compliance—special
05/14/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
Latest 25 of 150.
▾Documents — 2,102 on file (BIS + DOB NOW)
▸Plans & Drawings93
▸DOB NOWPlans/Sketch83
10/04/2026M01424556-I1Request digital key ↗
09/06/2026M00925560-I1Request digital key ↗
09/06/2026M00013748-I1Request digital key ↗
Showing 3 of 83 on file for this type
▸DOB NOWPlans/Sketch - Plumbing7
09/05/2026M00255772-I1Request digital key ↗
09/05/2026M00268827-I1Request digital key ↗
09/05/2026M00191092-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/05/2026M00192909-I1Request digital key ↗
09/05/2026M00200784-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Applications & Permits412
▸BISPLAN / WORK APPROVAL APPLICATION164
01/26/2026123729563Open ↗
10/16/2025123729563Open ↗
02/26/2024123265224Open ↗
Showing 3 of 164 on file for this type
▸BISWORK PERMIT APPLICATION163
05/07/2021123768164Open ↗
02/12/2021140974774Open ↗
02/08/2021140974774Open ↗
Showing 3 of 163 on file for this type
▸DOB NOWLPC Approval/Permit80
10/04/2026M01424556-I1Open ↗
09/05/2026M00255772-I1Open ↗
09/03/2026M00486068-I1Open ↗
Showing 3 of 80 on file for this type
▸BISApplication Withdrawal/Address Change Form OP-1133
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWState DEC Permit2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Seals & Professional Certifications443
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION183
04/29/2020123671561Open ↗
04/03/2020123774415Open ↗
04/03/2020123774415Open ↗
Showing 3 of 183 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature92
10/04/2026M01424556-I1Open ↗
09/05/2026M00088467-I1Open ↗
09/05/2026M00200784-I1Open ↗
Showing 3 of 92 on file for this type
▸DOB NOWProgress Inspector Seal & Signature82
10/08/2026M01033775-I1Open ↗
10/05/2026M01424556-I1Open ↗
10/03/2026M00268827-P1Open ↗
Showing 3 of 82 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature43
10/08/2026M01033775-I1Open ↗
10/08/2026M01033775-I1Open ↗
10/08/2026M01033775-I1Open ↗
Showing 3 of 43 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY7
11/27/2020140974774Open ↗
Showing 1 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
11/27/2020140974774Open ↗
Showing 1 of 2 on file for this type
▸Trade Schedules & Equipment127
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE55
02/03/2020123671561Open ↗
Showing 1 of 55 on file for this type
▸BISSELF-CERT PLUMBING NOTICE43
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 43 on file for this type
▸BISSCHEDULE B - PLUMBING28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection46
▸BISTenant Protection Plan and Notes34
05/13/2020120280524Open ↗
02/18/2020123865647Open ↗
04/16/2021140974774Open ↗
Showing 3 of 34 on file for this type
▸DOB NOWTenant Protection Plan9
09/05/2026M00255772-I1Open ↗
Showing 1 of 9 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Environmental & Asbestos170
▸DOB NOWDEP ACP-5: Asbestos Assessment Report77
10/04/2026M01424556-I1Open ↗
09/05/2026M00088467-I1Open ↗
09/05/2026M00200784-I1Open ↗
Showing 3 of 77 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)63
01/29/2021140974774Open ↗
11/27/2020140974774Open ↗
02/18/2020123865647Open ↗
Showing 3 of 63 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
09/05/2026M00255772-I1Open ↗
Showing 1 of 3 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance186
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS103
04/29/2020123671561Open ↗
04/03/2020123774415Open ↗
03/12/2020123671561Open ↗
Showing 3 of 103 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS41
02/21/2022123811795Open ↗
04/27/2021123865647Open ↗
05/13/2020122181085Open ↗
Showing 3 of 41 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY9
02/27/2024123265224Open ↗
02/21/2022123811795Open ↗
06/08/2021123768164Open ↗
Showing 3 of 9 on file for this type
▸BISTR8: Energy Code Progress Inspections8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.6
09/03/2026M00486068-I1Open ↗
09/03/2026M00541732-I1Open ↗
09/03/2026M00587916-I1Open ↗
Showing 3 of 6 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS4
02/27/2024123265224Open ↗
07/21/2022140974774Open ↗
07/18/2022123668986Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)4
02/27/2024123265224Open ↗
07/21/2022140974774Open ↗
07/18/2022123668986Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
11/27/2020140974774Open ↗
Showing 1 of 3 on file for this type
▸BISLIGHTING IN DWELLING UNITS3
02/27/2024123265224Open ↗
07/21/2022140974774Open ↗
07/18/2022123668986Open ↗
▸BISLIGHTING CONTROLS2
02/27/2024123265224Open ↗
07/21/2022140974774Open ↗
▸BISNYCECC ANALYSIS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
11/27/2020140974774Open ↗
▸Inspections & Test Reports25
▸BISTECHNICAL REPORT: RESPONSIBILITY22
02/28/2024123265224Open ↗
02/27/2024123265224Open ↗
03/18/2022123811795Open ↗
Showing 3 of 22 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
07/18/2022123668986Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
03/16/2020123811795Open ↗
▸Approvals, Objections & Sign-offs223
▸BISLANDMARKS APPROVAL89
01/30/2021140974774Open ↗
04/29/2020123671561Open ↗
02/21/2020123865647Open ↗
Showing 3 of 89 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST75
03/01/2024123265224Open ↗
08/03/2022140974774Open ↗
07/25/2022123668986Open ↗
Showing 3 of 75 on file for this type
▸BISADMINISTRATIVE OBJECTIONS22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION19
04/04/2022123729563Open ↗
04/03/2020123774415Open ↗
03/12/2020123671561Open ↗
Showing 3 of 19 on file for this type
▸BISLANDMARKS SIGNOFF9
07/25/2022123668986Open ↗
07/22/2022140974774Open ↗
02/22/2022123811795Open ↗
Showing 3 of 9 on file for this type
▸BISSUPERSEDING LETTER5
05/07/2021123768164Open ↗
07/22/2020123768164Open ↗
07/15/2020123768164Open ↗
Showing 3 of 5 on file for this type
▸BISFINAL3
02/27/2024123265224Open ↗
07/21/2022140974774Open ↗
07/18/2022123668986Open ↗
▸BISCCD1-Construction Code Determination1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership164
▸BISCOST AFFIDAVIT148
03/01/2024123265224Open ↗
03/18/2022123811795Open ↗
02/21/2022123811795Open ↗
Showing 3 of 148 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW35
02/27/2024123265224Open ↗
07/21/2022140974774Open ↗
07/18/2022123668986Open ↗
Showing 3 of 5 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
01/29/2021140974774Open ↗
▸Filing & Intake Forms174
▸BISEFILING COVER SHEET68
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 68 on file for this type
▸BISADDITIONAL INFORMATION52
01/30/2021140974774Open ↗
01/29/2021140974774Open ↗
09/01/2020123791682Open ↗
Showing 3 of 52 on file for this type
▸BISBOROUGH INTAKE FORM46
05/07/2021123768164Open ↗
10/02/2020123791245Open ↗
05/13/2020120280524Open ↗
Showing 3 of 46 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
11/27/2020140974774Open ↗
Showing 1 of 8 on file for this type
▸Other Documents30
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸DOB NOWProof of Historic Building8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWManufacturer's Specifications2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWCalculations2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTENANT/OCCUPANT PROTECTION PLAN 2008 CODE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDHCR DOCUMENT1
03/12/2020122505011Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type