| Owner | Filings | Most Recent |
|---|---|---|
| Thor 693 | 216 | 03/21/2026 |
| Takashimaya Fifth Ave | 83 | 03/21/2026 |
| Savitt Partners | 32 | 03/21/2026 |
| 693 Fifth Owner | 31 | 07/08/2026 |
| G&S Realty 1 | 2 | 03/21/2026 |
| The Hardman Group | 1 | 03/22/2026 |
| Thor | 1 | 03/21/2026 |
| Thor Equities | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/10/2016 | $455.0M | — | — → — | $4,491/sf building |
| 06/10/2016 | $68.2M | — | — → — | $673/sf building |
| 06/10/2016 | $1.8M | — | — → — | $17/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FL&M Engineering Design & Inspection | 2 | 09/15/2026 |
| Odc Associates | 1 | 09/11/2026 |
| Mihai Radu Architects | 4 | 07/02/2026 |
| Judge Architecture | 3 | 06/29/2026 |
| Newtec Engineering | 3 | 06/19/2026 |
| Elterman Finer Architects | 1 | 05/21/2026 |
| Aza Engineering | 2 | 05/04/2026 |
| RLM Engineering | 24 | 11/26/2025 |
| Vincent J. Liotta P.E | 1 | 06/20/2025 |
| Alan Tansey Architecture | 2 | 12/19/2024 |
| Jack Green Associates | 1 | 11/22/2024 |
| DPM Architecture | 5 | 11/11/2024 |
| Yorkos Engineering Design Consulting | 2 | 10/12/2024 |
| Atelier New York Architecture | 1 | 09/09/2024 |
| 2L Engineering | 2 | 07/10/2024 |
| Zheng & Associates | 1 | 05/06/2024 |
| Robert Derector Associates | 3 | 07/24/2023 |
| Arias Architecture | 2 | 06/23/2023 |
| Salvator A. Caradonna JR | 1 | 04/28/2023 |
| Socotec | 1 | 02/02/2023 |
| Luke Licalzi, P.E | 1 | 07/06/2022 |
| Merritt Engineering Consultants | 1 | 07/05/2022 |
| Lilker Associates Consulting Engineering | 6 | 08/26/2020 |
| Severud Associates | 1 | 08/23/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Rethy Associates | 44 | 03/21/2026 |
| Smep Design & Consultation | 2 | 03/21/2026 |
| J.A.M. Associates | 6 | 03/21/2026 |
| Milrose Consultants | 7 | 03/21/2026 |
| Merritt Engineering Consultant | 2 | 03/21/2026 |
| Idm Associates | 2 | 03/21/2026 |
| Sme Professional Design & Consultan | 2 | 03/21/2026 |
| All in Permit Consultants | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Ecostruction Group | General Contractor | 8 | 07/08/2026 |
| LT Fire Protection | Fire Protection | 6 | 07/08/2026 |
| Nucor Construction | General Contractor | 4 | 03/21/2026 |
| W5 Group | General Contractor | 4 | 07/08/2026 |
| James E Fitzgerald | General Contractor | 4 | 07/08/2026 |
| Abcat Associates | General Contractor | 4 | 07/08/2026 |
| A&A Plumbing | Plumbing | 3 | 07/08/2026 |
| Sentinel Builders | General Contractor | 2 | 07/08/2026 |
| J.r.best Electric | Electrical | 2 | 03/21/2026 |
| Structural Preserv System | General Contractor | 2 | 03/21/2026 |
| Americon Construction | General Contractor | 2 | 07/08/2026 |
| R.C.M. Electric | Electrical | 2 | 03/21/2026 |
| Mill Brook Fire Protection | Fire Protection | 2 | 07/08/2026 |
| Structural Preserv System | Scaffold | 2 | 03/21/2026 |
| William C. Gerakaris P&H | Plumbing | 2 | 07/08/2026 |
| MC Superstructure | Scaffold | 1 | 09/16/2026 |
| Spring Scaffolding | Scaffold | 1 | 07/08/2026 |
| National Maintenance | Sign hanger | 1 | 07/08/2026 |
| Alltype Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Capitol Fire Sprinkler Co | Fire Protection | 1 | 07/08/2026 |
| Doval Plumbing & Heating | Fire Protection | 1 | 07/23/2026 |
| Doval Plumbing & Heating | Plumbing | 1 | 06/28/2026 |
| Encore Fire Protection Services | Fire Protection | 1 | 07/08/2026 |
| Full Capacity Fire | Fire Protection | 1 | 07/08/2026 |
| G. C. Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| MPS Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| MPS Plumbing & Heating | Plumbing | 1 | 07/02/2026 |
| Prostar Plumbing and Heating | Plumbing | 1 | 07/08/2026 |
| RRP Plumbing | Fire Protection | 1 | 07/08/2026 |
| Vand Mechanical | Plumbing | 1 | 07/08/2026 |
| Elecserv | Electrical | 1 | 03/22/2026 |
| Zatos Plumbing and Heating | Plumbing | 1 | 07/08/2026 |
| Mega Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Tri-Electric | Electrical | 1 | 03/21/2026 |
| Deboccia Electric Construction | Electrical | 1 | 03/21/2026 |
| Defalco Associates, LLC/ | Electrical | 1 | 03/21/2026 |
| Boilermatic Welding Industries | specialty_contractor | 1 | 07/08/2026 |
| Four Star Air Con'd Co | General Contractor | 1 | 07/01/2026 |
| Great Interior Renovations | General Contractor | 1 | 06/28/2026 |
| Hick Holdings | General Contractor | 1 | 07/08/2026 |
| HNL Construction Company | General Contractor | 1 | 07/08/2026 |
| Power Cooling | General Contractor | 1 | 04/09/2026 |
| Prodigy Construction | General Contractor | 1 | 04/09/2026 |
| Signa Development | General Contractor | 1 | 06/27/2026 |
| Superior HVAC | specialty_contractor | 1 | 04/09/2026 |
| Torovoli Construction | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Outsource Special Inspection | 2827 | 3 | 07/02/2026 |
| Judge Architecture | 748 | 4 | 06/29/2026 |
| Obaid Mian | 849 | 3 | 06/19/2026 |
| Sam Mather Architect | 773 | 1 | 05/21/2026 |
| JMV Consulting Engineering | 804 | 1 | 05/21/2026 |
| Aza Engineering | 7235 | 2 | 05/04/2026 |
| Keyowner Engineering | 4817 | 1 | 02/17/2026 |
| RLM Engineering | 6913 | 19 | 11/26/2025 |
| Vincent J. Liotta P. E | 1974 | 1 | 06/20/2025 |
| Jack Green Associates | 422 | 1 | 11/22/2024 |
| Yorkos Engineering, Desig | 6991 | 2 | 10/12/2024 |
| Atelier NY Architecture | 2438 | 1 | 09/09/2024 |
| Leo Y Lee Associates | 2481 | 3 | 07/10/2024 |
| WB Engineering | 533 | 3 | 07/24/2023 |
| Merritt Engineering Consulting | 460 | 1 | 07/05/2022 |
| Lilker Associates Consulting | 816 | 3 | 04/07/2020 |
| Alan Margolin & Associates | 423 | 1 | 08/23/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | MC Superstructure | 09/15/2026 |
| DOB NOW | Sprinklers | Permit Issued | Doval Plumbing & Heating | 07/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Four Star Air Con'd Co | 06/29/2026 |
| DOB NOW | General Construction | Permit Issued | Great Interior Renovations | 06/26/2026 |
| DOB NOW | Plumbing | Permit Issued | Doval Plumbing & Heating | 06/26/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | Structural Preservation System | 06/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | MPS Plumbing & Heating | 05/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | HNL Construction Company | 05/13/2026 |
| DOB NOW | General Construction | Permit Issued | Signa Development | 05/05/2026 |
| DOB NOW | Plumbing | Permit Issued | MPS Plumbing & Heating | 04/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | Alltype Fire Protection | 03/05/2026 |
| DOB NOW | Plumbing | Signed-off | Zatos Plumbing and Heating | 03/02/2026 |
| DOB NOW | General Construction | Signed-off | Superior HVAC | 02/26/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Prodigy Construction | 02/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | Encore Fire Protection Services | 12/30/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Ecostruction Group | 12/03/2025 |
| DOB NOW | General Construction | Permit Issued | Ecostruction Group | 12/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Ecostruction Group | 12/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Ecostruction Group | 12/03/2025 |
| DOB NOW | General Construction | Permit Issued | Ecostruction Group | 12/03/2025 |
| DOB NOW | General Construction | Permit Issued | Ecostruction Group | 12/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Ecostruction Group | 12/02/2025 |
| DOB NOW | General Construction | Signed-off | Ecostruction Group | 12/02/2025 |
| DOB NOW | Sprinklers | Signed-off | Ralph W. Landolfi JR | 06/24/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Power Cooling | 06/23/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | Structural Preservation System | 03/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Sentinel Builders | 11/22/2024 |
| DOB NOW | Sprinklers | Signed-off | Leguci Piping & Heating | 11/08/2024 |
| DOB NOW | Plumbing | Signed-off | Prostar Plumbing and Heating | 11/07/2024 |
| DOB NOW | General Construction | Signed-off | Abcat Associates | 10/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Abcat Associates | 10/03/2024 |
| DOB NOW | Sprinklers | Signed-off | LT Fire Protection | 09/26/2024 |
| DOB NOW | Plumbing | Signed-off | G. C. Plumbing & Heating | 09/25/2024 |
| DOB NOW | General Construction | Signed-off | Sentinel Builders | 09/13/2024 |
| DOB NOW | General Construction | Signed-off | Torovoli Construction | 09/11/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Abcat Associates | 07/30/2024 |
| DOB NOW | Plumbing | Signed-off | Vand Mechanical | 07/24/2024 |
| DOB NOW | Sprinklers | Signed-off | LT Fire Protection | 07/17/2024 |
| DOB NOW | General Construction | Signed-off | Abcat Associates | 05/24/2024 |
| DOB NOW | Plumbing | Signed-off | A&A Plumbing | 06/26/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/02/2026 | Signed-off | Superior HVAC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Price Price FDC Series Fan Powered Terminal Unit
FD-1-3-30
*does not have an efficiency rating in COP/EER/SEER 42,000 BTU · Exhaust Fan ×3 Price FDC Series Fan Powered Terminal Unit FDC-1-3-20 *does not have an efficiency rating in COP/EER/SEER 19,000 BTU · Exhaust Fan ×1 |
| 06/19/2026 | Permit Issued | Four Star Air Con'd Co | Air Conditioning Systems, Ventilation Systems | |
| 06/20/2025 | Signed-off | Power Cooling | Air Conditioning Systems | Cooling Carrier 30MPW0665S-20117 70 tons · Chiller ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | MPS Plumbing & Heating | 75 heads |
| 06/19/2026 | Permit Issued | Doval Plumbing & Heating | Sprinkler System |
| 11/26/2025 | — | — | — |
| 11/26/2025 | — | — | 44 heads |
| 11/26/2025 | Permit Issued | Encore Fire Protection Services | 46 heads |
| 11/26/2025 | — | — | — |
| 03/24/2023 | Signed-off | LT Fire Protection | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | MPS Plumbing & Heating | Water/Sanitary |
| 06/19/2026 | Permit Issued | Doval Plumbing & Heating | Water/Sanitary |
| 11/26/2025 | — | — | Water/Sanitary |
| 11/26/2025 | — | — | Water/Sanitary |
| 11/26/2025 | — | — | Water/Sanitary |
| 11/26/2025 | — | — | Water/Sanitary |
| 11/22/2024 | — | — | Water/Sanitary |
| 03/24/2023 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/13/2026 | Complete | A&L Electric & Automation | General Wiring |
| 07/15/2026 | Permit Issued | Cobra Electrical NYC | General Wiring |
| 05/06/2026 | Permit Issued | R & T Electrical | General Wiring |
| 03/07/2025 | Complete | A.S.K. Electrical | General Wiring |
| 09/09/2024 | Complete | Elecserv | 5 meters |
| 08/23/2024 | Permit Issued | Mega Electrical Contracting | General Wiring |
| 07/24/2024 | Complete | AL-Lectric Elect'l Contracting | General Wiring |
| 10/03/2023 | Complete | Crosswire Electrical | General Wiring |
| 01/13/2023 | Complete | Metropolis Electric | General Wiring |
| 10/24/2022 | Complete | Commercial Electric Cont | General Wiring |
| 08/26/2022 | Complete | Top Shelf Electric | — |
| 08/15/2022 | Complete | Patriot Electric | General Wiring |
| 12/18/2020 | Complete | Flag Electric | — |
| 11/12/2020 | Complete | Update Systems Electrical | General Wiring |
| 03/31/2020 | Complete | E-J Electric Installation Co | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | — | — | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/04/2026 | Permit Issued | Structural Preservation System | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/24/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/16/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/30/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/27/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/14/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/11/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/04/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/18/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/18/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/05/2025 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 01/16/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/14/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/14/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/15/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/01/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/26/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/26/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/25/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/24/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/03/2026 | Concrete - Cast-In-Place | Prabhu Perumalsamy | special |
| 09/03/2026 | Fire-Resistance Rated Construction | Prabhu Perumalsamy | progress |
| 09/03/2026 | Structural Stability – Alterations of existing buildings | Prabhu Perumalsamy | special |
| 09/03/2026 | Sprayed fire-resistant materials | Prabhu Perumalsamy | special |
| 09/03/2026 | Structural Steel - Details | Prabhu Perumalsamy | special |
| 09/03/2026 | Final | Prabhu Perumalsamy | progress |
| 09/03/2026 | Structural Steel - Welding | Prabhu Perumalsamy | special |
| 09/03/2026 | Structural Steel - High Strength Bolting | Prabhu Perumalsamy | special |
| 09/03/2026 | Fire-Resistant Penetrations and Joints | Prabhu Perumalsamy | special |
| 07/07/2026 | HVAC-R and service water heating system controls | JONAR MADRIAGA | energy_progress |
| 07/07/2026 | Lighting controls | JONAR MADRIAGA | energy_progress |
| 07/07/2026 | HVAC-R and service water piping design and insulation | JONAR MADRIAGA | energy_progress |
| 07/07/2026 | Maintenance information | JONAR MADRIAGA | energy_progress |
| 07/07/2026 | HVAC-R and service water heating equipment | JONAR MADRIAGA | energy_progress |
| 07/07/2026 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 07/07/2026 | Post-installed Anchors | JONAR MADRIAGA | special |
| 07/07/2026 | Mechanical Systems | JONAR MADRIAGA | special |
| 07/07/2026 | Metering | JONAR MADRIAGA | energy_progress |
| 07/07/2026 | Final | JONAR MADRIAGA | progress |
| 07/07/2026 | Energy Code Compliance Inspections | JONAR MADRIAGA | progress |
| 07/07/2026 | Interior lighting power | JONAR MADRIAGA | energy_progress |
| 06/10/2026 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 06/10/2026 | Metering | JONAR MADRIAGA | energy_progress |
| 06/10/2026 | Interior lighting power | JONAR MADRIAGA | energy_progress |
| 06/10/2026 | Lighting controls | JONAR MADRIAGA | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Zuckerman Plastic Surgery | Medical / Healthcare | Floors 11, 12, Roof | Project M01371858 |
| Dr. Dale Lange | Medical / Healthcare | Floor 17 | Project M01349942 |
| Edwynn Houk | Arts / Culture / Entertainment | Floor 6 | Project M01091729 Project M01124308 Project M01091740 |
| Burberry | Retail | Floor 1 | Project M00856307 |
| MD2 / Doctor's Office | Medical / Healthcare | Floor 15 | Project M08040970 Project M08039273 Project M08040996 |
| Carpenters Workshop | Arts / Culture / Entertainment | Floor 19 | Project M00587460 |
| Savitt | Office | Floors 8, 9, 11, 12 | Project M00246821 Project M00247003 Project M00212787 Project M00212719 |