| Owner | Filings | Most Recent |
|---|---|---|
| MANN GROUP | 64 | 07/08/2026 |
| LACHMAN CONSTRUCTION & DE | 4 | 03/22/2026 |
| OWNER OF 44 NORTH 6 ST | 1 | 03/22/2026 |
| 161 WYTHE AVENUE OWNER | 6 | 03/21/2026 |
| 77 NORTH 6 | 2 | 03/21/2026 |
| 77 N 6TH | 1 | 03/21/2026 |
| 77 NORTH 6 GROUP | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/14/2023 | $11.4M | — | — → — | $3,800/sf building |
| 12/11/2019 | $6.3M | — | — → — | $2,100/sf building |
| 12/06/2016 | $3.6M | — | DEGREE VENTURE CAPITAL LLC → 77-79 NORTH 6 LLC | $1,200/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SA-DA ARCHITECTURE | 6 | 11/15/2022 |
| SHAHRISH SHUVO ENGINEERING P.C. | 5 | 11/02/2022 |
| KLH PROFESSIONAL ENGINEERS, PSC P.C | 3 | 10/27/2022 |
| O'NEIL LANGAN ARCHITECTS, PC | 2 | 08/31/2022 |
| ENTHINK ENGINEERS LLC | 3 | 12/16/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BIG ORANGE EXPEDITING | 18 | 03/21/2026 |
| CROWN DESIGN CONSULTING | 4 | 03/21/2026 |
| MARY MCKEOWN | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LACHMAN CONSTRUCTION & DE | General Contractor | 27 | 07/08/2026 |
| STEADFAST DEVELOPMENT AND | General Contractor | 9 | 03/21/2026 |
| ALEXANDER STOLTZ | Electrical | 2 | 03/21/2026 |
| PETRO COOLING HVAC CORP | General Contractor | 1 | 07/08/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 1 | 07/08/2026 |
| ARCO PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| SHOR PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| SKINNER PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| SO PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| ANTHONY LUCIANO | Electrical | 1 | 03/21/2026 |
| JAM ELECTRICAL CORP 003652 | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SA-DA ARCHITECTURE | 2640 | 5 | 11/15/2022 |
| SHAHRISH SHUVO ENGINEERIN | 8524 | 2 | 10/27/2022 |
| QUALITY TESTING, LLC | 7344 | 1 | 08/01/2022 |
| SHAHRISH CONSULTING LLC | 5702 | 1 | 01/14/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | PETRO COOLING HVAC CORP | 05/11/2023 |
| DOB NOW | General Construction | Permit Issued | LACHMAN CONSTRUCTION & DE | 12/22/2022 |
| DOB NOW | General Construction | Permit Issued | LACHMAN CONSTRUCTION & DE | 09/29/2022 |
| DOB NOW | Construction Fence | Signed-off | STEADFAST DEVELOPMENT AND | 09/07/2022 |
| DOB NOW | Plumbing | Signed-off | SKINNER PLUMBING & HEATIN | 08/11/2022 |
| DOB NOW | General Construction | Signed-off | STEADFAST DEVELOPMENT AND | 08/02/2022 |
| DOB NOW | Mechanical Systems | Signed-off | STEADFAST DEVELOPMENT AND | 08/02/2022 |
| DOB NOW | Plumbing | Signed-off | ARCO PLBG AND HTG INC | 06/02/2022 |
| DOB NOW | Foundation | Signed-off | LACHMAN CONSTRUCTION & DE | 09/13/2021 |
| DOB NOW | Construction Fence | Signed-off | LACHMAN CONSTRUCTION & DE | 09/13/2021 |
| DOB NOW | General Construction | Permit Issued | LACHMAN CONSTRUCTION & DE | 09/13/2021 |
| DOB NOW | Support of Excavation | Signed-off | LACHMAN CONSTRUCTION & DE | 09/13/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 09/10/2021 |
| DOB NOW | Foundation | Signed-off | LACHMAN CONSTRUCTION & DE | 08/24/2021 |
| DOB NOW | Support of Excavation | Signed-off | LACHMAN CONSTRUCTION & DE | 08/17/2021 |
| DOB NOW | General Construction | Permit Issued | LACHMAN CONSTRUCTION & DE | 08/06/2021 |
| DOB NOW | Construction Fence | Signed-off | LACHMAN CONSTRUCTION & DE | 08/06/2021 |
| DOB NOW | General Construction | Permit Issued | LACHMAN CONSTRUCTION & DE | 07/09/2021 |
| DOB NOW | Plumbing | Signed-off | SHOR PLBG & HTG INC | 05/27/2021 |
| DOB NOW | Plumbing | Signed-off | NICHOLAS SUIDA | 03/29/2021 |
| DOB NOW | General Construction | Signed-off | LACHMAN CONSTRUCTION & DE | 02/10/2021 |
| DOB NOW | Construction Fence | Signed-off | LACHMAN CONSTRUCTION & DE | 11/05/2020 |
| BIS | OT | ISSUED | LACHMAN CONSTRUCTION & DE | 09/10/2021 |
| BIS | OT | ISSUED | LACHMAN CONSTRUCTION & DE | 08/13/2021 |
| BIS | — | ISSUED | LACHMAN CONSTRUCTION & DE | 12/15/2020 |
| BIS | FP | ISSUED | NEW YORK BUSINESS SYST INC | 08/29/2006 |
| BIS | PL | ISSUED | MI MECH INDUSTRIES INC | 05/15/2006 |
| BIS | — | ISSUED | ABSTRACT CONST & DECR CO. | 05/05/2006 |
| BIS | EQ | ISSUED | ABSTRACT CONST & DECR CO. | 05/05/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/09/2022 | Complete | M.C. ELECTRICAL NY INC | General Wiring |
| 07/21/2022 | Complete | DENMAR ELECTRIC CORP | 1 meters, 1 new_meters |
| 03/24/2022 | Complete | JAM ELECTRICAL CORP | — |
| 09/01/2021 | Complete | ELPO ELECTRICAL CONTG INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/22/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/15/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/23/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/01/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/21/2023 | Fire-Resistance Rated Construction | Alexander Stoltz | progress |
| 04/21/2023 | Interior lighting power | Alexander Stoltz | energy_progress |
| 04/21/2023 | Fenestration and door U-factor and product ratings | Alexander Stoltz | energy_progress |
| 04/21/2023 | Exterior lighting power | Alexander Stoltz | energy_progress |
| 04/21/2023 | Lighting controls | Alexander Stoltz | energy_progress |
| 04/21/2023 | Insulation placement and R values | Alexander Stoltz | energy_progress |
| 04/21/2023 | Fenestration air leakage | Alexander Stoltz | energy_progress |
| 04/21/2023 | Fenestration areas | Alexander Stoltz | energy_progress |
| 04/21/2023 | Air barrier — testing | Alexander Stoltz | energy_progress |
| 04/21/2023 | Fire-Resistant Penetrations and Joints | Alexander Stoltz | special |
| 04/21/2023 | Energy Code Compliance Inspections | Alexander Stoltz | progress |
| 11/07/2022 | HVAC and service water heating equipment | Alexander Stoltz | energy_progress |
| 11/07/2022 | HVAC and service water heating system controls | Alexander Stoltz | energy_progress |
| 11/07/2022 | HVAC insulation and sealing | Alexander Stoltz | energy_progress |
| 11/07/2022 | Fire-Resistant Penetrations and Joints | Alexander Stoltz | special |
| 11/07/2022 | Energy Code Compliance Inspections | Alexander Stoltz | progress |
| 10/31/2022 | Energy Code Compliance Inspections | Alexander Stoltz | progress |
| 10/31/2022 | HVAC insulation and sealing | Alexander Stoltz | energy_progress |
| 10/31/2022 | HVAC and service water heating equipment | Alexander Stoltz | energy_progress |
| 10/31/2022 | HVAC and service water heating system controls | Alexander Stoltz | energy_progress |
| 10/31/2022 | Fire-Resistant Penetrations and Joints | Alexander Stoltz | special |
| 10/26/2022 | Maintenance information | Shahrish Shuvo | energy_progress |
| 08/26/2022 | Final | Mary Langan | progress |
| 07/22/2022 | Lighting controls | KEVIN SNEDEKER | energy_progress |
| 07/22/2022 | Duct leakage testing, insulation and design | KEVIN SNEDEKER | energy_progress |