← Back
Office, 20+ stories, with or without commercial
909 3 AVENUE
MANHATTAN · BIN 1038570
💬 Discuss this project
1967Year Built
32Stories
O4Building Class
C1-9Zoning
1,321,050 sfGross Floor Area
10Units
LL97 Covered9 Open Violations 2 unresolved · 7 paperwork only ▸FISP: SWARMPFDNY Report ↗
Office, 20+ stories, with or without commercial · Owner of record: 909 THIRD HOLDING LLC · 82,341 sf lot · 16.04 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction5p · 1 filing · 1 doc
Floor 32Under Construction5p · 1 filing · 1 doc
Floor 31Under Construction5p · 1 filing · 1 doc
Floor 30Under Construction57p · 4 filings · 20 docs
Floor 29Under Construction13p · 3 filings · 15 docs
Floor 28Under Construction20p · 3 filings · 15 docs
Floor 27Under Construction5p · 1 filing · 1 doc
Floor 26Under Construction5p · 1 filing · 1 doc
Floor 25Under Construction5p · 1 filing · 1 doc
Floor 24Under Construction14p · 5 filings · 19 docs
Floor 23Under Construction5p · 1 filing · 1 doc
Floor 22Under Construction5p · 1 filing · 1 doc
Floor 21Under Construction5p · 1 filing · 1 doc
Floor 20Under Construction14p · 6 filings · 20 docs
Floor 19Under Construction14p · 5 filings · 20 docs
Floor 18Under Construction5p · 1 filing · 1 doc
Floor 17Under Construction19p · 5 filings · 17 docs
Floor 16Under Construction5p · 1 filing · 1 doc
Floor 15Under Construction5p · 1 filing · 1 doc
Floor 14Under Construction11p · 5 filings · 20 docs
Floor 13Under Construction5p · 1 filing · 1 doc
Floor 12Under Construction15p · 8 filings · 20 docs
Floor 11Under Construction9p · 2 filings · 13 docs
Floor 10Under Construction8p · 3 filings · 14 docs
Floor 9Under Construction6p · 2 filings · 18 docs
Floor 8Under Construction5p · 1 filing · 1 doc
Floor 7Under Construction5p · 1 filing · 1 doc
Floor 6Under Construction6p · 2 filings · 4 docs
Floor 5Under Construction9p · 4 filings · 17 docs
Floor 4Under Construction5p · 1 filing · 1 doc
Floor 3Under Construction5p · 1 filing · 1 doc
Floor 2Under Construction6p · 2 filings · 7 docs
Floor 1Under Construction12p · 2 filings · 4 docs
Cellar7p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
VORNADO REALTY TRUST16509/22/2026
962 THIRD AVENUE ASSOCIATES407/08/2026
909 THIRD HOLDING603/22/2026
909 THIRD FEE OWNER LLC V603/22/2026
VORNADO OFFICE MANAGEMENT,LLC41403/22/2026
VOCNARDO OFFICE MGMT LLC103/22/2026
VORNADO MGMT CO.103/22/2026
MENDIN COMPANY1203/22/2026
MENHID COMPANY103/22/2026
HRH CONSTRUCTION103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/11/2021$191.7M—909 THIRD FEE OWNER LLC → 909 THIRD HOLDING LLC$145/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ICON INTERIORS INCGeneral Contractor2307/08/2026
AMBASSADOR CONSTRUCTION CGeneral Contractor1107/08/2026
STARR INDUSTRIES LLCGeneral Contractor607/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor409/22/2026
TRI-STAR CONSTRUCTION CORPGeneral Contractor403/21/2026
SIRINA FIRE PROT CORPFire Protection307/08/2026
A&A PLUMBING CORPPlumbing307/08/2026
S&E BRIDGE & SCAFFOLD LLC.General Contractor307/08/2026
CLUNE CONSTRUCTION CO LPGeneral Contractor307/08/2026
DONNELLY MECHANICAL CORPGeneral Contractor307/08/2026
PSI PARTNERS, LLCFire Protection307/08/2026
S.B.A. PLUMBING CORPPlumbing207/08/2026
ABCO-PEERLESS SPRKLR CORPFire Protection207/08/2026
SKYLINE FIRE SPRINKLER COFire Protection207/08/2026
UNITED FIRE PROT CORPFire Protection207/08/2026
UPRIGHT FIRE PROTCTN LLCFire Protection207/08/2026
LHOTSE CORPGeneral Contractor207/08/2026
STRUCTURE TONE, LLCGeneral Contractor207/08/2026
EVEREST SCAFFOLDING INCGeneral Contractor107/08/2026
ALLSTATE SPRINKLER LLCFire Protection107/08/2026
PAR PLUMBING CO., INCPlumbing107/08/2026
UNI-LITE ELECTRIC, LLCElectrical103/22/2026
POLO ELECTRIC CORP. D/B/AElectrical103/22/2026
BOROWIDE ELECT'L CONTR'SElectrical103/22/2026
GREGORY PAPANTONIOUElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HANSEN ENGINEERING PC81742404/02/2026
PCS ENGINEERING3745104/02/2026
ASDA ARCHITECTURE + DESIG2015403/30/2026
MILROSE CONSULTANTS LLC2003201/29/2026
SKYLINE ENGINEERING, PLLC267611/04/2025
ALAN D MARCUS, PE1761702/18/2025
DNA CONTROLLED INSPECTION554311/20/2023
OBAID MIAN849104/26/2023
G&G SPRINKLER SERVICES LL2782411/02/2022
AK ENGINEERING PC678303/25/2022
Building Lifecycle
All (300)Filed (72)Permit Issued (72)Signed Off (43)Facade (FISP) (6)Violation (43)Inspection (34)Special Inspection (30)
09/21/2026
Permit issued — Sidewalk Shed
M01422212-I1-SH
07/20/2026
Signed off — Alteration
Interior demolition of non load bearing partitions on the 20th floor as indicated on drawings.
M01353161-I1
07/09/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01364626-I1
07/07/2026
Inspection — Pass-Final SP - More than 10 Requested Floors
Pass
View inspection ↗
06/30/2026
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01422212-I1
06/30/2026
Permit issued — Sidewalk Shed
M01422212-I1-SH
06/09/2026
Inspection — Pass-Final SP - More than 10 Requested Floors
Pass
View inspection ↗
06/04/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/28/2026
Permit issued — Sidewalk Shed
M01364626-I1-SH
05/22/2026
Permit issued — General Construction
M01359281-I1-GC
04/14/2026
Permit issued — Plumbing
M01374265-I1-PL
04/14/2026
Permit issued — Sprinklers
M01366604-I1-EW-SP
04/10/2026
Permit issued — Sprinklers
M01374188-I1-EW-SP
04/09/2026
Filed — Alteration
Facade work on the 1st through 32nd floor; roof work as indicated on drawings.
M01359281-I1
04/09/2026
Permit issued — Suspended Scaffold
M01381412-I1-SC
04/02/2026
Filed — Alteration
Suspended Scaffold for Facade Restoration as Shown on Plans
M01381412-I1
04/02/2026
Filed — Alteration
Removal of sprinkler heads; install temporary sprinkler loop on the 20th floor as indicated on drawings.
M01374188-I1
04/02/2026
Permit issued — Mechanical Systems
M01374290-I1-MS
04/01/2026
Special inspection requirement — Post-installed Anchors
Michael Walsh
04/01/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
03/31/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ryan Hansen
03/30/2026
Filed — Alteration
Mechanical demolition on the 17th floor as indicated on drawings.
M01374290-I1
03/30/2026
Filed — Alteration
Removal of plumbing fixtures on the 17th floor as indicated on drawings.
M01374265-I1
03/25/2026
Filed — Alteration
Removal of sprinkler heads and installation of temporary sprinkler loop on the 17th floor as indicated on drawings.
M01366604-I1
03/25/2026
Permit issued — General Construction
M01364692-I1-GC
03/24/2026
Permit issued — General Construction
M01353161-I1-GC
03/23/2026
Filed — Alteration
Interior demolition of non load bearing partitions on the 17th floor as indicated on drawings.
M01364692-I1
03/19/2026
Filed — Alteration
Interior demolition of non load bearing partitions on the 20th floor as indicated on drawings.
M01353161-I1
03/18/2026
Special inspection requirement — Mechanical Systems
Alfonso DElia
03/18/2026
Special inspection requirement — Sprinkler Systems
Ryan Hansen
03/18/2026
Special inspection requirement — Final
Alfonso DElia
03/05/2026
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01364626-I1
03/05/2026
Permit issued — Sidewalk Shed
M01364626-I1-SH
02/26/2026
Special inspection requirement — Final
Alfonso DElia
02/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alfonso DElia
02/12/2026
Special inspection requirement — Final
Susanne Mackiw
02/09/2026
Violation issued (ECB, closed)
Elevators
02/06/2026
Permit issued — General Construction
M01342160-I1-GC
02/06/2026
Permit issued — Mechanical Systems
M01345470-I1-MS
01/29/2026
Filed — Alteration
M01342160-I1
01/29/2026
Filed — Alteration
Modification to existing HVAC system as per plans filed herewith. no change in use, egress or occupancy under this application
M01345470-I1
01/29/2026
Special inspection requirement — Final
Alfonso DElia
01/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alfonso DElia
01/27/2026
Special inspection requirement — Lighting controls
Christopher Drutjons
01/27/2026
Special inspection requirement — Duct leakage testing, insulation and design
Christopher Drutjons
01/27/2026
Special inspection requirement — Energy Code Compliance Inspections
Christopher Drutjons
01/27/2026
Special inspection requirement — Interior lighting power
Christopher Drutjons
01/12/2026
Special inspection requirement — Final
Christopher Drutjons
01/12/2026
Special inspection requirement — Mechanical Systems
Christopher Drutjons
11/07/2025
Permit issued — Sprinklers
M01299106-I1-EW-SP
11/06/2025
Permit issued — General Construction
M01244394-I1-GC
11/05/2025
Special inspection requirement — Sprayed fire-resistant materials
Matthew Wavro
11/05/2025
Special inspection requirement — Sprinkler Systems
Matthew Wavro
11/05/2025
Special inspection requirement — Final
Matthew Wavro
11/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Matthew Wavro
11/05/2025
Special inspection requirement — Post-installed Anchors
Matthew Wavro
11/04/2025
Filed — Alteration
ALTERATIONS TO EXISTING SPRINKLER SYSTEMS AS PER PLANS FILED HEREWITH
M01299106-P1
11/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Matthew Wavro
11/04/2025
Special inspection requirement — Post-installed Anchors
Matthew Wavro
10/31/2025
Permit issued — Mechanical Systems
M01299092-I1-MS
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC09/21/2026
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC06/30/2026
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC05/28/2026
DOB NOWGeneral ConstructionPermit IssuedLHOTSE CORP05/22/2026
DOB NOWPlumbingPermit IssuedA&A PLUMBING CORP04/14/2026
DOB NOWSprinklersPermit IssuedPSI PARTNERS, LLC04/14/2026
DOB NOWSprinklersPermit IssuedPSI PARTNERS, LLC04/10/2026
DOB NOWSuspended ScaffoldPermit IssuedLHOTSE CORP04/09/2026
DOB NOWMechanical SystemsPermit IssuedCLUNE CONSTRUCTION CO LP04/02/2026
DOB NOWGeneral ConstructionPermit IssuedCLUNE CONSTRUCTION CO LP03/25/2026
DOB NOWGeneral ConstructionSigned-offCLUNE CONSTRUCTION CO LP03/24/2026
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC03/05/2026
DOB NOWGeneral ConstructionPermit IssuedICON INTERIORS INC02/06/2026
DOB NOWMechanical SystemsPermit IssuedICON INTERIORS INC02/06/2026
DOB NOWSprinklersPermit IssuedFULL CAPACITY FIRE CORP11/07/2025
DOB NOWGeneral ConstructionPermit IssuedICON INTERIORS INC11/06/2025
DOB NOWMechanical SystemsPermit IssuedICON INTERIORS INC10/31/2025
DOB NOWGeneral ConstructionSigned-offICON INTERIORS INC02/21/2025
DOB NOWMechanical SystemsPermit IssuedDONNELLY MECHANICAL CORP09/12/2024
DOB NOWSprinklersSigned-offMORA FIRE PROTECTION LLC12/05/2023
DOB NOWGeneral ConstructionSigned-offICON INTERIORS INC11/21/2023
DOB NOWMechanical SystemsSigned-offICON INTERIORS INC11/21/2023
DOB NOWProtection and Mechanical MethodsPermit IssuedS&E BRIDGE & SCAFFOLD LLC09/28/2023
DOB NOWSprinklersSigned-offH.J. FLOOD INC.08/11/2023
DOB NOWSprinklersSigned-offSKYLINE FIRE SPRINKLER CO07/26/2023
DOB NOWProtection and Mechanical MethodsPermit IssuedS&E BRIDGE & SCAFFOLD LLC07/25/2023
DOB NOWMechanical SystemsSigned-offAMBASSADOR CONSTRUCTION C07/17/2023
DOB NOWPlumbingSigned-offS.B.A. PLUMBING CORP07/13/2023
DOB NOWGeneral ConstructionSigned-offAMBASSADOR CONSTRUCTION C07/12/2023
DOB NOWMechanical SystemsSigned-offSTRUCTURE TONE, LLC06/28/2023
DOB NOWSprinklersSigned-offH.J. FLOOD INC.06/27/2023
DOB NOWPlumbingSigned-offA&A PLUMBING CORP06/26/2023
DOB NOWGeneral ConstructionSigned-offICON INTERIORS INC06/09/2023
DOB NOWPlumbingSigned-offA & M WARSHAW PLBG & HTG06/08/2023
DOB NOWGeneral ConstructionSigned-offSTRUCTURE TONE, LLC06/07/2023
DOB NOWPlumbingSigned-offA&A PLUMBING CORP05/01/2023
DOB NOWMechanical SystemsSigned-offICON INTERIORS INC04/29/2023
DOB NOWSprinklersSigned-offSTANDARD FIRE SUPP CORP04/28/2023
DOB NOWMechanical SystemsPermit IssuedDONNELLY MECHANICAL CORP04/26/2023
DOB NOWGeneral ConstructionSigned-offICON INTERIORS INC04/19/2023
+ 60 more permits on file
3 jobs · most recent 04/02/2026
FiledStatusContractorScope
04/02/2026Permit IssuedPSI PARTNERS, LLC92 heads
03/25/2026Permit IssuedPSI PARTNERS, LLC247 heads
11/04/2025Permit IssuedFULL CAPACITY FIRE CORP80 heads
4 jobs · most recent 04/02/2026
Water/Sanitary
FiledStatusContractorScope
04/02/2026———
03/30/2026Permit IssuedA&A PLUMBING CORPWater/Sanitary
03/25/2026———
11/04/2025———
25 jobs · most recent 04/14/2026
General Wiring Lighting
FiledStatusContractorScope
04/14/2026Permit IssuedCLOONAGH ELECTRICAL CORP—
04/06/2026Permit IssuedA.S.K. ELECTRICAL CORPGeneral Wiring
02/26/2026Permit IssuedBOROWIDE ELECT'L CONTR'S—
12/24/2025CompleteA.S.K. ELECTRICAL CORPGeneral Wiring
11/08/2023CompleteUNITED ELEC & LIGHTING COGeneral Wiring
08/03/2023CompleteC. W. GREENE INCGeneral Wiring
06/20/2023CompleteUNI-LITE ELECTRIC, LLCGeneral Wiring
05/01/2023CompleteUNITED ELEC & LIGHTING COGeneral Wiring
04/18/2023CompleteROBERT B SAMUELS, INCGeneral Wiring
02/07/2023CompletePOLO ELECTRIC CORP. D/B/AGeneral Wiring
01/23/2023CompleteLMEC ELECTRIC INCGeneral Wiring, Lighting
08/02/2022Permit IssuedPOLO ELECTRIC CORP. D/B/A—
05/24/2022Permit IssuedPOLO ELECTRIC CORP. D/B/A4 meters
04/20/2022CompleteNEAD ELECTRIC INC.General Wiring
03/11/2022CompleteADCO ELEC'L CORPGeneral Wiring
2 jobs · most recent 06/30/2026
Sidewalk Shed
FiledStatusContractorScope
06/30/2026Permit IssuedANDAMIO SCAFFOLDING LLCSidewalk Shed
03/05/2026Signed-offANDAMIO SCAFFOLDING LLCSidewalk Shed
1 job · most recent 04/02/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
04/02/2026Permit IssuedLHOTSE CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 34
DateTypeResultReport
07/07/2026Pass-Final SP - More than 10 Requested FloorsPassView ↗
06/09/2026Pass-Final SP - More than 10 Requested FloorsPassView ↗
06/04/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/29/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/23/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/12/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/17/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/08/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/08/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/08/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/06/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/27/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/22/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/22/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/18/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/11/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/21/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/06/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/01/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/04/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/07/2023Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
07/05/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/30/2023Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
Latest 25 of 34.
▾Special Inspection Requirements (DOB NOW) — 118
DateRequirementInspectorRole
04/01/2026Post-installed AnchorsMichael Walshspecial
04/01/2026Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
03/31/2026Fire-Resistant Penetrations and JointsRyan Hansenspecial
03/18/2026FinalAlfonso DEliaprogress
03/18/2026Sprinkler SystemsRyan Hansenspecial
03/18/2026Mechanical SystemsAlfonso DEliaspecial
02/26/2026FinalAlfonso DEliaprogress
02/26/2026Fire-Resistant Penetrations and JointsAlfonso DEliaspecial
02/12/2026FinalSusanne Mackiwprogress
01/29/2026Fire-Resistant Penetrations and JointsAlfonso DEliaspecial
01/29/2026FinalAlfonso DEliaprogress
01/27/2026Energy Code Compliance InspectionsChristopher Drutjonsprogress
01/27/2026Duct leakage testing, insulation and designChristopher Drutjonsenergy_progress
01/27/2026Interior lighting powerChristopher Drutjonsenergy_progress
01/27/2026Lighting controlsChristopher Drutjonsenergy_progress
01/12/2026FinalChristopher Drutjonsprogress
01/12/2026Mechanical SystemsChristopher Drutjonsspecial
11/05/2025Fire-Resistant Penetrations and JointsMatthew Wavrospecial
11/05/2025Post-installed AnchorsMatthew Wavrospecial
11/05/2025Sprinkler SystemsMatthew Wavrospecial
11/05/2025FinalMatthew Wavroprogress
11/05/2025Sprayed fire-resistant materialsMatthew Wavrospecial
11/04/2025Fire-Resistant Penetrations and JointsMatthew Wavrospecial
11/04/2025Post-installed AnchorsMatthew Wavrospecial
10/28/2025Sprinkler SystemsMatthew Wavrospecial
Latest 25 of 118.
▾Documents — 4,380 on file (BIS + DOB NOW)
▸Plans & Drawings73
▸DOB NOWPlans/Sketch64
09/06/2026M01353161-I1Request digital key ↗
09/06/2026M00049562-I1Request digital key ↗
09/02/2026M00683696-I1Request digital key ↗
Showing 3 of 64 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
09/05/2026M00226986-I1Request digital key ↗
09/04/2026M00373295-I1Request digital key ↗
09/03/2026M00448570-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/05/2026M00227050-I1Request digital key ↗
09/04/2026M00373248-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/04/2026M00383266-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00392688-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00373287-I1Request digital key ↗
▸Applications & Permits742
▸BISPLAN / WORK APPROVAL APPLICATION423
08/22/2025123276506Open ↗
08/25/2023123397715Open ↗
07/28/2023123397715Open ↗
Showing 3 of 423 on file for this type
▸BISWORK PERMIT APPLICATION314
11/02/2020140958079Open ↗
10/21/2020140958079Open ↗
10/05/2020140945468Open ↗
Showing 3 of 314 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLACE OF ASSEMBLY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications1,147
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION659
05/06/2020123913079Open ↗
05/06/2020123913079Open ↗
03/17/2020123722196Open ↗
Showing 3 of 659 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST133
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 133 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT100
09/25/2020140958079Open ↗
08/31/2020140945468Open ↗
08/07/2020140936414Open ↗
Showing 3 of 100 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM87
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 87 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature71
09/06/2026M01353161-I1Open ↗
09/06/2026M00049562-I1Open ↗
09/05/2026M00227050-I1Open ↗
Showing 3 of 71 on file for this type
▸DOB NOWProgress Inspector Seal & Signature48
09/26/2026M00839860-I1Open ↗
09/26/2026M00839860-I1Open ↗
09/23/2026M00846390-P1Open ↗
Showing 3 of 48 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature38
09/29/2026M00846427-I1Open ↗
09/26/2026M00839860-I1Open ↗
09/23/2026M00846390-P1Open ↗
Showing 3 of 38 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION6
09/25/2020140958079Open ↗
08/31/2020140945468Open ↗
08/07/2020140936414Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY5
08/31/2020140945468Open ↗
08/07/2020140936414Open ↗
Showing 2 of 5 on file for this type
▸Trade Schedules & Equipment469
▸BISSELF-CERT PLUMBING NOTICE134
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 134 on file for this type
▸BISSCHEDULE B - PLUMBING105
09/18/2020123579715Open ↗
Showing 1 of 105 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE70
01/22/2020123684717Open ↗
Showing 1 of 70 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA64
06/30/2025122226769Open ↗
06/22/2023123762384Open ↗
06/08/2022123072664Open ↗
Showing 3 of 64 on file for this type
▸BISEQUIPMENT USE PERMITS47
03/13/2020123722196Open ↗
03/13/2020123722196Open ↗
Showing 2 of 47 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT20
03/13/2020123722196Open ↗
Showing 1 of 20 on file for this type
▸BISSPRINKLER INSP REPORT : FP-8519
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISSTANDPIPE INSP REPORT : FP-846
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos394
▸BISASBESTOS: CERTIFICATION (DEP ACP5)185
08/31/2020140945468Open ↗
08/07/2020140936414Open ↗
06/02/2020123913079Open ↗
Showing 3 of 185 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'108
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 108 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report66
09/06/2026M01353161-I1Open ↗
09/05/2026M00227050-I1Open ↗
09/04/2026M00373287-I1Open ↗
Showing 3 of 66 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS: EXEMPTION (ASB4)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Energy Compliance190
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS128
03/17/2020123722196Open ↗
03/17/2020123722196Open ↗
03/02/2020123716657Open ↗
Showing 3 of 128 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS36
01/08/2021123913079Open ↗
11/13/2020123376587Open ↗
10/22/2020140936414Open ↗
Showing 3 of 36 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY8
01/08/2021123913079Open ↗
11/13/2020123376587Open ↗
10/22/2020140936414Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISTR8: Energy Code Progress Inspections5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
08/07/2020140936414Open ↗
Showing 1 of 2 on file for this type
▸BISNYCECC ANALYSIS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports33
▸BISTECHNICAL REPORT: RESPONSIBILITY20
07/31/2023123397715Open ↗
07/27/2023123397715Open ↗
02/09/2023123397715Open ↗
Showing 3 of 20 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
02/09/2023123397715Open ↗
▸Approvals, Objections & Sign-offs375
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST209
07/01/2025122226769Open ↗
08/28/2023123397715Open ↗
06/23/2023123762384Open ↗
Showing 3 of 209 on file for this type
▸BISADMINISTRATIVE OBJECTIONS111
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 111 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION38
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 38 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFINAL2
02/09/2023123397715Open ↗
01/27/2022140958079Open ↗
▸Cost, Insurance & Ownership484
▸BISCOST AFFIDAVIT480
06/14/2023123762384Open ↗
01/25/2022140945468Open ↗
01/21/2022140945468Open ↗
Showing 3 of 480 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
03/26/2025122226769Open ↗
06/14/2023123762384Open ↗
02/09/2023123397715Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms424
▸BISEFILING COVER SHEET270
05/06/2020123913079Open ↗
Showing 1 of 270 on file for this type
▸BISBOROUGH INTAKE FORM82
05/15/2020123415330Open ↗
05/01/2020123684717Open ↗
03/17/2020123722196Open ↗
Showing 3 of 82 on file for this type
▸BISADDITIONAL INFORMATION57
04/01/2021140958079Open ↗
02/14/2020123716657Open ↗
01/31/2020123722196Open ↗
Showing 3 of 57 on file for this type
▸BISeFiling Job Application Cover Sheet15
09/25/2020140958079Open ↗
08/31/2020140945468Open ↗
08/07/2020140936414Open ↗
Showing 3 of 15 on file for this type
▸Other Documents18
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISSupporting Document: Fee Exempt2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWCalculations1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWManufacturer's Specifications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type