← Back
BuildNYC
Elevator cooperative
Shore Ridge
9425 SHORE ROAD · Bay Ridge · BIN 3155519
💬 Discuss this project
1953Year Built
6Stories
D4Building Class
R7AZoning
70,458 sfGross Floor Area
54Units
LL97 CoveredRent Stabilized1 Active Violation ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: Shore Ridge Apartment · 15,500 sf lot · 4.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofFacade repairs and roof replacement4p · 1 filing · 20 docs
Floor 6Unit 6E, Unit 6F2p · 4 filings · 20 docs
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Cellar2 filings · 9 docs
BasementEbmg LLC1p · 1 filing · 15 docs
Sub-BasementEbmg LLC6p · 2 filings · 19 docs
Site & exteriorFacade repairs and roof replacement15p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Shore Ridge Apt2103/22/2026
Ebmg403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kamen Tall Architects306/25/2025
Sebastian M D'Alessandro410/22/2024
Gannett Fleming411/22/2023
Enthink Engineers109/14/2022
Green Design101/25/2021
Royal T&E106/18/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Metropolis Group603/21/2026
Cornerstone Consulting203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Skyline Restorationspecialty_contractor707/08/2026
Andamio ScaffoldingScaffold507/08/2026
Varsity Plumbing and HeatingPlumbing307/08/2026
Sato ConstructionGeneral Contractor203/21/2026
Phoenix Sutton STRScaffold203/21/2026
Everest ScaffoldingScaffold203/21/2026
Zaim ContractorGeneral Contractor203/21/2026
Spring ScaffoldingGeneral Contractor103/21/2026
Denali ElectricElectrical103/21/2026
A+ Electric of Greater NYElectrical103/21/2026
Borowide Elect'l ContractorsElectrical103/22/2026
JNR Plumbing Inc DbaPlumbing107/08/2026
Alonso Hall ContractingGeneral Contractor111/14/2006
Clark & Wilkins IndustriesGeneral Contractor107/12/2004
Joseph Ferrigno Plumbing & HeatingPlumbing112/27/2006
Liberty Construction & REGeneral Contractor108/18/2011
Panarama InternationalGeneral Contractor204/06/2004
Signature ScaffoldingGeneral Contractor205/15/2013
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Kamen Tall Architects3606306/25/2025
Sebastian M. D'Alessandro1127410/22/2024
Delta Testing Labs687102/01/2024
Gregory V. Perotto, P.E.947211/22/2023
Building Lifecycle
02/20/2027
Facade inspection report due (FISP Cycle 9, sub-cycle A)
The filing window opened 02/21/2025. No Cycle 9 filing on record yet
09/24/2026
Boiler inspection report filed
Initial · no defects · Accepted
08/10/2026
Signed off — Alteration
SEPARATE PREVIOUSLY COMBINED APARTMENTS # 6F AND # 6E AS PER PLANS. RESTORE GAS STOVE AT APT. # 6E. NO CHANGE IN EGRESS, USE OR OCCUPANCY.
B01123270-I1
08/10/2026
Signed off — Alteration
SEPARATE PREVIOUSLY COMBINED APARTMENTS # 6F AND # 6E AS PER PLANS. RESTORE GAS STOVE AT APT. # 6E. NO CHANGE IN EGRESS, USE OR OCCUPANCY.
B01123231-I1
04/28/2026
Co-op apartment 6C sold for $685,000
188 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offSuffolk Construction03/21/2025
DOB NOWPlumbingSigned-offJNR Plumbing Inc Dba01/15/2025
DOB NOWGeneral ConstructionSigned-offSkyline Restoration03/01/2023
DOB NOWGeneral ConstructionSigned-offSkyline Restoration02/03/2023
DOB NOWPlumbingSigned-offVarsity Plumbing and Heating09/30/2022
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding09/14/2022
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding09/08/2022
DOB NOWGeneral ConstructionSigned-offSkyline Restoration02/18/2022
DOB NOWGeneral ConstructionSigned-offSkyline Restoration11/08/2021
DOB NOWPlumbingSigned-offVarsity Plumbing and Heating09/24/2021
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding09/17/2021
DOB NOWSidewalk ShedSigned-offEverest Scaffolding01/29/2021
DOB NOWSidewalk ShedSigned-offPhoenix Sutton STR06/18/2018
BISOTISSUEDSato Construction03/07/2014
BISEQISSUEDSignature Scaffolding05/15/2013
BISOTISSUEDSato Construction03/13/2013
BISOTISSUEDSato Construction10/12/2012
BISEQISSUEDSignature Scaffolding07/17/2012
BISOTISSUEDLiberty Construction & RE08/18/2011
BISPLISSUEDJoseph Ferrigno P&H12/27/2006
BISFSISSUEDStar Industrial Service12/27/2006
BISOTISSUEDAlonso Hall Contracting11/14/2006
BISEQISSUEDClark & Wilkins Industries07/12/2004
BISOTISSUEDPanorama International04/06/2004
BISEQISSUEDSpring Scaffolding03/23/2004
BISOTISSUEDPanorama International12/15/2003
BISBLISSUEDBeta Steam and Pwer10/17/1991
1 project · most recent 11/22/2023
FiledStatusContractorScope
11/22/2023———
3 projects · most recent 10/22/2024
Gas Plumbing-Sprinkler Water/Sanitary
FiledStatusContractorScope
10/22/2024Signed-offJNR Plumbing Inc DbaGas
07/26/2024——Gas
11/22/2023Signed-offVarsity Plumbing and HeatingGas, Plumbing-Sprinkler, Water/Sanitary
5 projects · most recent 02/03/2026
General Wiring
FiledStatusContractorScope
02/03/2026CompleteA+ Electric of Greater NYGeneral Wiring
01/28/2026Permit IssuedDenali Electric—
12/19/2021Permit IssuedJte Electrical Services—
01/27/2021CompleteBorowide Elect'l Contractors—
06/14/2018Permit IssuedElpo Electrical Contg—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
01/30/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/14/2023Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
02/14/2023Certified Sprinkler (PL) - SP - RoughingCertifiedView ↗
02/13/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/10/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 23
DateRequirementInspectorRole
06/27/2025FinalScott Kamenprogress
06/27/2025MasonryScott Kamenspecial
06/27/2025Post-installed AnchorsScott Kamenspecial
06/27/2025Energy Code Compliance InspectionsScott Kamenprogress
06/16/2025FinalScott Kamenprogress
06/16/2025MasonryScott Kamenspecial
06/16/2025Post-installed AnchorsScott Kamenspecial
06/16/2025Energy Code Compliance InspectionsScott Kamenprogress
10/07/2024FinalSebastian D'Alessandroprogress
10/07/2024Tenant Protection Plan ComplianceSebastian D'Alessandrospecial
10/07/2024Fire-Resistant Penetrations and JointsSebastian D'Alessandrospecial
10/07/2024Tenant Protection Plan ComplianceSebastian D'Alessandrospecial
10/07/2024Fire-Resistant Penetrations and JointsSebastian D'Alessandrospecial
07/26/2024Fire-Resistant Penetrations and JointsSebastian D'Alessandrospecial
07/16/2024FinalSebastian D'Alessandroprogress
01/08/2024Insulation placement and R valuesRICHARD GREENWALDenergy_progress
01/08/2024MasonryScott Kamenspecial
01/08/2024Post-installed AnchorsRICHARD GREENWALDspecial
01/08/2024Energy Code Compliance InspectionsScott Kamenprogress
01/08/2024FinalScott Kamenprogress
12/14/2023Fire-Resistant Penetrations and JointsGregory Perottospecial
11/12/2020Final—progress
11/12/2020Mechanical Systems—special
120 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account